RANJAN GOGOI,ROHINTON FALI NARIMAN
ASSOCIATE BUILDERS – Appellant
Versus
DELHI DEVELOPMENT AUTHORITY – Respondent
C.A. No.-010531-010531 / 2014
25-11-2014
Page 1
JUDGMENT
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 10531 OF 2014
(ARISING OUT OF SLP (CIVIL) NO.14767 OF 2012)
Associate Builders …Appellant
Versus
Delhi Development Authority …Respondent
J U D G M E N T
R.F.Nariman,J.
1.
Leave granted.
2.
The appellant herein was awarded a certain construction work contract
by the DDA vide a letter of award dated 14th May, 1992. DDA was building a
colony consisting of 7,000 houses in Trilok Puri in the trans-Yamuna area. 168
Middle Income Group houses and 56 Lower Income Group houses, Grade-A
Pocket- B (balance work) was awarded for the tendered amount of
Rs.87,66,678/-. The contract was to be completed in 9 months. Admittedly, it
was ultimately completed only in 34 months, the contractor completing 166
Middle Income Group houses and 36 Lower Income Group houses. The total
value of work that was done amounted to Rs.62,84,845/-. As many as 15
1
Page 2
JUDGMENT
claims were made by the contractor and the High Court of Delhi appointed one
Shri K.D. Bali to arbitrate the present dispute.
3.
We are concerned here with claims 9, 10, 11 and 15, for these claims
have been allowed by the Arbitrator and the DDA’s objections have been
dismissed by the learned Single Judge of the High Court of Delhi. The
Division Bench in an appeal under Section 37 of the Arbitration Act, 1996 has
stepped in to set aside the judgment of the Single Judge and negative these
claims. We are also concerned with claims 12 and 13 which have been scaled
down by the Division Bench.
4.
Claims 9, 10, 11 and 15 read as follows:
“Claim No.9: Claimants claim Rs. 20,950/- on account of hire
charges of centering shuttering due to delay in laying of
conduiting.
a) That the respondents had granted certain work of
electrification but the said agency did not lay the conduit
resulting in delay in removing the shuttering and causing hire
charges. This fact was reported to the respondents vide
claimant's letter dated 30.10.92 followed by reminders and also
found place in hindrance register.
b) That this is the actual expenditure incurred and thus the
claimant is entitled for its refund.
c) That the detailed break-up of this claim has been appended
separately.
Claim No.10: Claimants claim Rs.33,450/- being the hire
charges of shuttering due to stoppage of work in block no. 100
and 101.
a) That the department had virtually stopped the work in block
100 & 101 on 20.7.93 and it continued up to 26.2.94. During
this period no work was allowed to be executed in these two
2
Page 3
JUDGMENT
blocks resulting in blockade or centering and shuttering in the
said two blocks.
b) That by stoppage of work in these two blocks the claimants
had suffered hire charges of shuttering due to respondent's
lapses and defaults.
c) It is further stated that there was no justification for stoppage
of work and the action was arbitrary and totally unjust.
d) That the detail of this claim has been outlined and appended
separately and the same shall from part of the statement of
facts.
Claim No. 11: Rs.2,00,000/- payable as damages on account of
hire charges of tools & plants and scaffolding.
a) That due to prolongation of the contract on account of the
respondents the claimants had to maintain tools & plants,
scaffolding etc, during the prolongation of the contract resulting
in expenditure for the same.
b) That the said articles remained at site beyond the stipulated
period and the claimants suffered loss due to the said
prolongation.
Claim No. 15: Claimants claim damages Rs.6,25,979/- on
account of establishment due to prolongation of the contract.
a) That the claimants had contemplated maintenance of
establishment during stipulated peri
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.