2009 MarsdenLR 4348 ; 2009 MarsdenLR 1

LOW HOP BING, ZAINUN ALI, ABDUL MALIK ISHAK
ASIAPOOLS (M) SDN BHD – Appellant
Versus
IJM CONSTRUCTION SDN BHD – Respondent


Table of Content
1. undisputed facts regarding contractual relationships and claims. (Para 1 , 2 , 3 , 4 , 5 , 31 , 32 , 33 , 35 , 36 , 37 , 38)
2. arguments regarding the interpretation of payment clauses. (Para 6 , 7 , 11 , 12)
3. court observations on contractual payment interpretations. (Para 8 , 14 , 16 , 19 , 20 , 21 , 34 , 40 , 42)
4. key ruling on 'pay-when-paid' clause implications. (Para 10 , 25 , 52)
5. final conclusion affirming lower court's judgment. (Para 26 , 27 , 53)
JUDGMENT

Low Hop Bing JCA:

Appeal

[1] Parties are referred to in their capacities in the Sessions Court.

[2] The Kuala Lumpur Sessions Court had allowed the plaintiff's claim with costs against the defendant.

[3] The defendant's appeal to the High Court was allowed with costs. The High Court made a further order that the judgment sum of RM271,458.29, paid by the defendant to the plaintiff, be returned to the defendant, together with interest at 8% p.a.

[4] The plaintiff has now appealed to this court.

Finding Of Facts

[5] The facts at the trial are not in dispute. The plaintiff was the nominated sub-contractor to build, inter alia, a swimming pool for a 161-unit condominium in Seremban. The defendant had ear

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top