FEDERAL COURT PUTRAJAYA
ANG MING LEE & ORS – Appellant
Versus
MENTERI KESEJAHTERAAN BANDAR PERUMAHAN DAN KERAJAAN TEMPATAN & ANOR AND OTHER.... – Respondent
[1] There were six related appeals before us which were heard together. Four (4) appeals were filed by the purchasers of individual condominium units in Sri Istana Condominium ("the project"). The other two appeals were filed by the developer of the project, BHL Construction Sdn Bhd. The issue in these appeals concerns reg 11(3) of the Housing Development (Control and Licensing) Regulations 1989 ("the Regulations").
Background Facts
[2] By a Sale and Purchase Agreement dated 3 May 2012 ("the SPA"), entered into between the developer and the purchasers, it was agreed that the delivery of vacant possession of the units shall be 36 months from the date of signing of the respective SPAs. The SPAs were made pursuant to the statutorily prescribed form under Schedule H of the Regulations. Subparagraph 25(2) of Schedule H provides that if the developer fails to deliver vacant possession within 36 months, the developer shall be liable to pay the purchaser liquidated damages ("LAD").
[3] Vide a letter dated 20 October 2014, the developer applied for an extension of time for the delivery of vacant possession of the units to the purchasers. The application for the extension of time was made to th
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.