The has clarified that a (DRT) is not strictly required to transmit a to another Tribunal merely because the mortgaged property lies outside its local . In a judgment delivered on , the bench comprising Justice Pamidighantam Sri Narasimha and Justice Alok Aradhe ruled that the , grants Tribunals the discretionary power to retain , provided that such a decision is supported by a reasoned assessment of practical convenience and effective enforcement.
The ruling effectively resolves a long-standing divergence of opinion among various High Courts across the country, setting aside a judgment by the that had previously insisted upon the mandatory transfer of such certificates. By allowing the appeal filed by the , the Supreme Court restored the on properties in Tiruchirappalli, effectively permitting the to continue its recovery process despite the properties being located within the jurisdiction of the .
Discretionary Powers Under the RDB Act
The core of the legal dispute rested on the interpretation of . The provision addresses the scenario where a Tribunal, having issued a , finds that the relevant property falls under the territorial scope of another Tribunal. While some High Courts previously interpreted the word “may” in this section as an imperative “shall,” effectively forcing a transfer of the certificate, the Supreme Court rejected this construction.
Justice Alok Aradhe, writing for the bench, emphasized that the 1993 Act is a specialized, self-contained code designed to expedite the recovery of public money, and it should not be shackled by the rigid procedures of the . The Court noted that the legislature deliberately used the term “may” to grant the Tribunal . “The word 'may' in Section 19(23) cannot be read as 'shall'. It confers a on the Tribunal, and not an option on the certificate holder or the Recovery Officer,” the judgment observed.
The Court further reasoned that if the statute had intended for a mandatory territorial restriction on execution, it would have explicitly enacted one, similar to provisions found in the CPC. A mandatory requirement to transfer certificates whenever properties are located elsewhere would, in the Court's view, trigger a cycle of administrative delays, fragmented proceedings, and unnecessary litigation—all of which fundamentally contradict the RDB Act’s primary objective of providing a swift recovery mechanism for financial institutions.
Refining Execution Procedures and Safeguards
To prevent the arbitrary exercise of this discretionary power, the Supreme Court introduced a structured test and a set of mandatory safeguards for Tribunals to follow when deciding whether to retain or transmit a . These guidelines require Tribunals to conduct an objective assessment of the case, identifying the nature of the property, its occupancy status, and whether the proposed execution through the existing Recovery Officer can be completed without causing undue prejudice.
The Court emphasized that the decision to transmit a certificate must not be a reaction to a request from a certificate holder but must be an independent judicial act. Specifically, the Tribunal is now required to determine the exact location and nature of the property, examine the , assess the potential for , and ultimately issue a reasoned order. The Court stated, “The paramount consideration must be whether the proposed course would facilitate lawful, effective and expeditious enforcement of the , with due regard to the rights of the certificate debtor and of third parties.”
As a further measure of protection, these decisions must generally be finalized at the time the is issued, or as soon as possible thereafter, and importantly, before any —such as physical possession or auction—are taken against properties located outside the local limits of the issuing Tribunal. This ensures that certificate debtors receive adequate notice and an opportunity to be heard regarding the forum of execution.
Resolving a Sixteen-Year Dispute
The present case originated from credit facilities availed between and by a partnership firm, , from the ’s Tiruchirappalli branch. The subsequent default, resulting in a debt of over nine crore rupees, led to a prolonged legal battle spanning over sixteen years, characterized by dozens of applications and appeals.
The Borrower had initially moved the proceedings from the to the Chennai DRT on the grounds of perceived bias. However, once the Chennai DRT issued the and the Recovery Officer began taking possession of the mortgaged properties, the Borrower challenged the jurisdiction of the Chennai Tribunal, claiming that the attachment was void because the properties were located in the Madurai jurisdiction.
Rejecting this contention, the Supreme Court observed that the Borrower, having sought the transfer to Chennai himself, could not now challenge the forum's jurisdiction without demonstrating or a . The Court found that both properties were in a single district and were not subject to any competing claims or prior attachments that would necessitate a transfer.
The Supreme Court has now restored the attachment order dated , and directed the Recovery Officer at , Chennai, to resume the from the point where they were halted. The Tribunal is mandated to follow the newly established structured test and safeguards and is encouraged to conclude the recovery process within six months from the date of receiving the judgment. This decision provides a definitive framework for future recovery proceedings, prioritizing the administrative efficiency of the debt recovery mechanism over procedural technicalities.