SupremeToday Landscape Ad
Back
Next

Case Law

Expedition in Approaching Court Crucial for Section 9 Relief; Bombay HC Modifies ₹63 Crore Deposit Order in Arbitration Case - 2025-07-01

Subject : Civil Law - Arbitration Law

Expedition in Approaching Court Crucial for Section 9 Relief; Bombay HC Modifies ₹63 Crore Deposit Order in Arbitration Case

Supreme Today News Desk

Bombay HC Modifies ₹63 Cr Pre-Arbitral Deposit, Cites Delay in Seeking Relief

Mumbai: In a significant ruling on pre-arbitral interim measures, the Bombay High Court has modified a lower court's order that directed Ashoka Buildcon Ltd. (ABL) to deposit over ₹63 crore. The High Court bench, comprising Justices A.S. Chandurkar and Rajesh Patil , underscored that a party's expedition in approaching the court under Section 9 of the Arbitration and Conciliation Act, 1996, is a critical factor in determining its entitlement to discretionary relief.

The Court partly allowed an appeal filed by ABL, substantially reducing the security amount it must provide, linking the relief directly to the part of the claim where the subcontractor, Maha Active Engineers India Pvt. Ltd. ( MAEIPL ), had acted promptly.

Background of the Dispute

The case originates from a 2008 contract where the Maharashtra State Electricity Distribution Company Ltd. (MSEDCL) awarded a project to ABL, who then subcontracted a portion of the work to MAEIPL . The work was completed in 2011.

MAEIPL claimed that ABL withheld substantial payments. After years of communications, MAEIPL invoked arbitration in December 2019. However, the dispute gained new impetus when ABL won a separate arbitral award of over ₹48 crore against MSEDCL in February 2020. Following a court order in December 2023, MSEDCL deposited a portion of this award amount for ABL's benefit.

Seizing this opportunity, MAEIPL filed an application under Section 9 of the Arbitration Act in January 2024, seeking an order to secure its total outstanding claim of ₹113 crore, and specifically asked the court to direct ABL to deposit ₹63.27 crore. The Nashik District Court allowed this application, prompting ABL to appeal to the High Court.

Arguments in the High Court

Ashoka Buildcon Ltd. (Appellant):

- Delay and Laches : Senior Advocate Mr. Nikhil Sakhardande, for ABL, argued that MAEIPL had approached the court with considerable delay. He pointed to significant gaps in communication and action, particularly between 2016 and 2019, and again from 2019 until the 2024 application.

- Lack of Prima Facie Case: ABL contended that MAEIPL failed to establish the three pillars for interim relief: a prima facie case, the balance of convenience, and irreparable loss.

- Arbitrary Amount: The appellant argued that the ₹63.27 crore figure was arbitrary and lacked a clear basis, having inflated from an initial claim of ₹2.44 crore.

Maha Active Engineers India Pvt. Ltd. (Respondent):

- Justified Delay: Senior Advocate Mr. Sharan Jagtiani, for MAEIPL , countered that the delay was due to ongoing settlement discussions and ABL's dominant position as the main contractor. He argued that they acted swiftly once it became clear ABL had received funds from MSEDCL but had no intention to settle their dues.

- Strong Prima Facie Case: MAEIPL asserted that ABL’s vague denials in its reply, without a specific counter-narrative, amounted to an admission, thus establishing a strong prima facie case.

- Need for Protection: It was argued that the order was necessary to protect the subject matter of the dispute and prevent the future arbitral award from becoming a mere "paper award."

Court's Analysis and Ruling

The High Court meticulously analyzed the timeline of the dispute and the conduct of the parties. While acknowledging the limited scope of interference in discretionary orders under Section 37, the bench found grounds to intervene.

The judgment drew a crucial distinction between the different parts of MAEIPL 's claim:

"The aforesaid conduct of MAEIPL as is evident from its pleadings can be dissected into two parts; one part being its entire claim that it has to recover from ABL... and the other part based on the award passed by the Sole Arbitrator on 15th February 2020..."

The Court observed that MAEIPL had been inactive for long periods, particularly from December 2016 to December 2019. However, it noted that MAEIPL acted with "expedition" immediately after the court order of December 19, 2023, which facilitated ABL's recovery from MSEDCL. The court held:

"We are therefore inclined to hold that MAEIPL has invoked the jurisdiction under Section 9 of the Act of 1996 with expedition only in view of the Consent Minutes of Order dated 19th December 2023. Thus, on the backdrop of the said arrangement between MSEDCL and ABL, the claim of MAEIPL deserves consideration under Section 9 to that extent."

Finding that the lower court had not provided reasons for arriving at the ₹63.27 crore figure, the High Court decided to modify the relief. It based the new security amount on MAEIPL 's own pleaded entitlement stemming directly from the arbitral award ABL won against MSEDCL.

The Final Decision

The High Court partly allowed the appeal and modified the lower court's order. ABL is now directed to:

1. Deposit an amount of ₹9,74,12,889 in cash.

2. Furnish a bank guarantee for ₹14,61,19,333.

This total security of ₹24.35 crore is based on MAEIPL 's specific claim related to the funds flowing from the ABL-MSEDCL award. The Court also upheld the injunction restraining ABL from entering into any compromise with MSEDCL that would prejudice MAEIPL 's rights.

#ArbitrationAct #BombayHighCourt #InterimRelief

Breaking News

View All
SupremeToday Portrait Ad
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top