The High Court of Jammu & Kashmir and Ladakh at Srinagar has set aside recovery notices issued by the Food Corporation of India (FCI) against a private godown operator, ruling that state-run entities cannot unilaterally impose financial penalties outside the scope of an existing contract. The Division Bench of Justice Sanjeev Kumar and Justice Mohd. Yousuf Wani observed that internal administrative decisions made by the corporation’s High Level Committee cannot override binding lease agreements, nor can they create financial liabilities that were never contemplated by the contracting parties at the time of execution.

The dispute involved M/s Alpine Agro Services, which had been contracted under the Private Entrepreneur Guarantee (PEG) scheme to construct and operate a 17,500 metric tonne storage facility in Shilvat. Under the terms of the agreement, the firm was obligated to complete specific infrastructure requirements, including the macadamization and black-topping of internal access roads. While the firm successfully established the facility, it failed to complete the black-topping work within the initial timeframe, partially attributing the delay to severe regional law and order disturbances in 2016. Although the firm eventually finished the work in mid-2017, the FCI maintained that the initial delay constituted a breach of contract that warranted financial consequences beyond those originally defined in the lease.

The legal crux of the case rested on the FCI’s attempt to apply a uniform, pan-India policy formulated by its High Level Committee to an existing, specific contract. This policy, developed to address similar deficiencies in other godowns across the country, suggested calculating damages based on an artificial cost-saving formula rather than actual financial loss. The corporation subsequently sought to implement these recoveries through retroactive administrative orders, bypassing the specific dispute-resolution mechanisms outlined in the original Lease and Service Agreement.

In overturning the dismissal of the initial writ petition, the High Court emphasized that contractual sanctity must be maintained, even when dealing with state instrumentalities. The Bench noted that the corporation had already exercised its discretion in a previous instance by imposing a specific penalty of ₹1,58,002 in 2018, which the appellant had paid without protest. The Court criticized the corporation’s subsequent move to reopen the matter and impose additional, significantly higher liabilities years after the fact based on evolving administrative policies.

“In the absence of any specific clause in the terms and conditions of the Lease and Service Agreement executed between the appellant and the respondent-Corporation, the respondent-Corporation could not have unilaterally imposed a penalty, that too on the basis of calculations made at its own level,” the Court remarked.

The Bench further clarified the limited applicability of the doctrine of unjust enrichment in this context. The FCI had argued that the appellant had benefited financially by delaying the black-topping work, thereby enjoying an unearned advantage at the corporation's expense. However, the Court dismissed this, noting that the godown remained fully operational and was, in fact, being utilized to its optimum capacity throughout the period in question. Because the lack of black-topping did not prevent the corporation from storing foodgrains or otherwise hinder the facility’s utility, the Court found no evidence of real-world loss that would trigger the compensation provisions under the Contract Act, 1872.

The judges observed that the corporation possessed clear contractual options if it had truly viewed the infrastructure deficiency as a material breach. Specifically, the lease agreement empowered the FCI to execute the black-topping work independently and recover the actual costs from the rent payable to the appellant. By choosing not to invoke these provisions and instead continuing to use the facility without protest, the corporation effectively signaled that the infrastructure was sufficient for its requirements.

Addressing the broader policy implications, the Court stated, “The decision of the High Level Committee to alter the lease was, thus, foreign to the contract and, therefore, totally inapplicable to the case of the appellant.” While acknowledging that such committees may be useful for regulating future tendering processes or establishing standard operating procedures for new agreements, the Court held that these entities possess no inherent authority to reach back and unilaterally modify the financial obligations of existing, active contracts.

The ruling underscores the principle that government-controlled entities, despite their role in public service and infrastructure management, are bound by the same standards of fair dealing as private actors. By failing to link the recovery notices to any tangible loss or a specific contractual penalty clause, the FCI’s actions were deemed arbitrary and unreasonable. The Court concluded that the writ Court had erred in prioritizing the corporation’s internal policy decisions over the written terms that explicitly defined the relationship between the parties.

Following the decision, the High Court quashed the impugned recovery notices in their entirety. The judgment acts as a definitive protection for contractors operating under the PEG scheme, reinforcing that state instrumentalities cannot rely on generic administrative decisions to bypass specific contract terms.

As part of the final order, the Court directed the Food Corporation of India to immediately calculate and release all rental payments that had been withheld or deducted from the appellant on the strength of the invalid recovery notices. The corporation has been mandated to ensure that these outstanding payments are processed within a period of two months, bringing a finality to the long-standing dispute over the contractual obligations of the godown owner.