SupremeToday Landscape Ad
Back
Next

CIPAA 2012 Sections 15 and 37

Adjudication Decision Under CIPAA Valid Despite Pending Civil Suit: High Court Invokes Section 37 to Reject Jurisdictional Challenge - 2026-01-20

Subject : Civil Law - Construction Contract Disputes

Adjudication Decision Under CIPAA Valid Despite Pending Civil Suit: High Court Invokes Section 37 to Reject Jurisdictional Challenge

Supreme Today News Desk

High Court Rejects Bid to Invalidate CIPAA Adjudication Amid Ongoing Civil Suit

Introduction

The High Court of Malaya, in a judgment delivered by Judicial Commissioner Azlan Sulaiman, dismissed an application by MN Permai Netcom Sdn Bhd (now Netcomx Sdn Bhd) to declare or set aside an adjudication decision under the Construction Industry Payment and Adjudication Act 2012 (CIPAA), ruling that the existence of a pending civil suit does not invalidate the adjudication process. Hallmark Season Sdn Bhd, the successful claimant in the adjudication, had sought enforcement of the decision awarding it over RM1.6 million. The court emphasized the independent and concurrent nature of adjudication under CIPAA, upholding its role in providing swift payment resolutions in construction disputes.

Case Background

MN Permai engaged Hallmark in May 2022 via a Letter of Award to perform works on a construction project in Kulim High Tech, Kedah. In August 2023, Hallmark and another contractor, Teraju Mentari Sdn Bhd, filed a civil suit (Kuala Lumpur Civil Suit No: WA-22NCvC-451-08/2023) against MN Permai, claiming unpaid sums under the project. MN Permai counterclaimed for larger amounts. In March 2024, the High Court dismissed Hallmark's and Teraju's summary judgment application, setting the matter for trial in January 2026.

Undeterred, Hallmark issued a Payment Claim under CIPAA in April 2024 for the same sum claimed in the civil suit. Adjudication proceedings followed, resulting in an August 28, 2024, decision ordering MN Permai to pay Hallmark RM1,638,644.99 plus interest, costs, and the adjudicator's fees within 30 days. MN Permai, arguing the adjudication was invalid due to the ongoing civil suit, filed Originating Summons No: WA-24C-145-09/2024 (OS 145) seeking to declare it void, set it aside, or stay it. Hallmark countered with Originating Summons No: WA-24C-154-10/2024 (OS 154) for enforcement under Section 28 of CIPAA. The court heard both summonses together for prudence.

The main legal questions were: (1) Does a pending civil suit and dismissal of summary judgment bar adjudication under CIPAA? (2) Were there grounds under Section 15 of CIPAA to set aside the decision for jurisdictional excess, denial of natural justice, or lack of impartiality? (3) Should enforcement be stayed pending the civil suit's trial?

Arguments Presented

MN Permai contended that the adjudication decision was invalid due to the prior civil suit, invoking doctrines like res judicata, estoppel, and abuse of process. It argued the adjudicator lacked jurisdiction (Section 15(d) CIPAA) because the High Court's dismissal of summary judgment bound the adjudicator, making the proceedings duplicative and an impermissible collateral attack. MN Permai also alleged denial of natural justice (Section 15(b)), claiming the adjudicator refused an oral hearing on the jurisdictional issue, misled it by promising to decide preliminaries first, and issued the decision prematurely without allowing a response to Hallmark's reply or adequate submissions. Further, it accused the adjudicator of bias (Section 15(c)) for deciding without witnesses, pre-judging, and awarding costs unfairly. For a stay under Section 16(1)(b), MN Permai highlighted the civil suit's readiness for trial and Hallmark's alleged financial instability, suggesting justice required awaiting the full trial.

Hallmark maintained that adjudication under CIPAA operates independently and concurrently with litigation, as per Section 37, which allows parallel proceedings without affecting each other unless settled or finally decided. It argued the summary judgment dismissal did not resolve the dispute, merely requiring trial, and thus did not impair adjudication's jurisdiction. Hallmark defended the process as compliant with CIPAA's timelines and the adjudicator's discretion under Section 25, denying any natural justice breach since submissions were adequately addressed in documents. It sought straightforward enforcement under Section 28, asserting no payment had been made and no impediments existed post the jurisdictional challenge.

Legal Analysis

The court, applying Section 37 of CIPAA, held that adjudication can proceed concurrently with civil suits, as the provision explicitly states that court references do not end or affect adjudication unless the dispute is settled or finally decided. The summary judgment dismissal, the court noted, only meant no summary entitlement to payment, not a final resolution, thus not triggering res judicata or estoppel. Drawing on Terminal Perintis Sdn Bhd v Tan Ngee Hong Construction Sdn Bhd , it distinguished jurisdictional types: MN Permai's challenge fell under "competency jurisdiction," but Section 37 preserved the adjudicator's authority over payment claims regardless of litigation.

On natural justice (Section 15(b)), the court cited Ireka Engineering and Construction Sdn Bhd v PWC Corp Sdn Bhd to emphasize procedural fairness, but found no material breach. The adjudicator's discretion under Sections 12 and 25 to conduct proceedings documentarily, without oral hearings or successive decisions, was upheld. References to Econpile (M) Sdn Bhd v IRDK Ventures Sdn Bhd clarified that challenges to merits or peripheral issues do not constitute breaches; MN Permai's jurisdictional arguments were fully addressed in submissions. For impartiality (Section 15(c)), the court rejected unsubstantiated claims, stressing the seriousness of such allegations absent evidence of bias or conflicts, per Section 24 declarations.

Precedents like Martego Sdn Bhd v Arkitek Meor & Chew Sdn Bhd (across High Court, Court of Appeal, and Federal Court) reinforced adjudication's "temporary finality" and independence from litigation or arbitration, allowing a "both and" approach. View Esteem Sdn Bhd v Bina Puri Holdings Bhd and ASM Development (KL) Sdn Bhd v Econpile (M) Sdn Bhd guided the stay denial, requiring "clear errors" or "special circumstances"—neither present here. The court distinguished merits challenges (e.g., evidence assessment) as non-grounds for setting aside, per Alpha Galaxy Sdn Bhd v Euro Destar (M) Sdn Bhd , deferring them to final arbitration or trial. This aligns with CIPAA's "pay now, argue later" ethos, as in Foster Wheeler E & C (Malaysia) Sdn Bhd v Arkema Thiochemicals Sdn Bhd , to expedite construction payments without awaiting lengthy litigation.

Key Observations

  • On concurrent proceedings: "A dispute in respect of payment under a construction contract may be referred concurrently to adjudication, arbitration or the court... a reference to arbitration or the court... shall not bring the adjudication proceedings to an end nor affect the adjudication proceedings." (Section 37 CIPAA, quoted in judgment).
  • On temporary finality: "Adjudication under CIPAA was never designed to be in conflict with Arbitration and Litigation and so its process may be activated at any time when there is a valid payment claim under a construction contract." ( Martego Sdn Bhd v Arkitek Meor & Chew Sdn Bhd , High Court).
  • On natural justice: "Breaches of the rules will be material in cases where the adjudicator has failed to bring to the attention of the parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable potential importance." ( Econpile (M) Sdn Bhd v IRDK Ventures Sdn Bhd ).
  • On jurisdiction: "The word 'jurisdiction' is used in section 15(d) as in the Adjudicator having acted in 'excess of his jurisdiction' as a ground for setting aside an Adjudication Decision." ( Terminal Perintis Sdn Bhd v Tan Ngee Hong Construction Sdn Bhd ).
  • On purpose of CIPAA: "The underlying intent and purpose of the Act is to provide within the construction industry an expeditious mechanism for settling payment disputes... on a provisional interim basis pending the final determination." (Judgment, para [29]).

Court's Decision

The court dismissed OS 145 in full, refusing to declare the adjudication decision void (as CIPAA provides only for setting aside under Section 15), and rejected all grounds for setting aside or staying it. Prayer 1 was dismissed for lack of statutory basis; jurisdictional, natural justice, and impartiality challenges failed under Section 15; and the stay application under Section 16(1)(b) lacked clear errors or special circumstances. OS 154 was allowed, enforcing the decision as a High Court judgment under Section 28, with orders for payment of RM1,638,644.99 plus 5% interest, costs of RM20,000, and the adjudicator's fees. MN Permai was ordered to pay RM20,000 costs on OS 145, while Hallmark received RM5,000 on OS 154.

This ruling reinforces CIPAA's objective of rapid payment enforcement in construction disputes, preventing respondents from using parallel litigation to evade obligations. It may encourage more adjudication initiations alongside suits, reducing cash flow issues for contractors, but underscores that final resolutions remain in courts or arbitration, potentially increasing multi-track proceedings. Future cases will likely cite this to dismiss similar jurisdictional blocks, promoting the "pay now, argue later" principle without undermining ongoing trials.

adjudication decision - pending civil suit - jurisdictional challenge - natural justice - temporary finality - pay now argue later

#CIPAA #ConstructionAdjudication

Breaking News

View All
SupremeToday Portrait Ad
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top