CIPAA 2012 Adjudication Enforcement
Subject : Civil Law - Construction Disputes
In a significant ruling for Malaysia's construction sector, the High Court dismissed attempts by developer Granstep Development Sdn Bhd to set aside an adjudication decision under the Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012), denied a stay of execution, and granted leave to enforce payment of RM893,890.24 to main contractor Pembinaan Bina Bumi Sdn Bhd (PBB). Delivered by Judicial Commissioner Sumathi Murugiah, the decision underscores the Act's aim to protect cash flow in the industry, rejecting claims of jurisdictional overreach and breaches of natural justice. The case arose from a dispute over Certificate of Payment No. 30 (CP 30) for a residential development project in Ampang, Selangor.
PBB was appointed as the main contractor by Granstep for the "Main Building Works for Cadangan Pembangunan Perumahan Berpagar" project, a 24-storey apartment block with 176 units, parking, and public facilities on land in Bandar Ampang, Selangor. The appointment was formalized via a Letter of Award dated 22 January 2020, incorporating the PAM 2006 Standard Form of Building Contract.
Granstep paid PBB in full for all certificates up to CP No. 29. The dispute centered on CP No. 30, issued by the project architect on 30 May 2023 for RM1,426,889.73, comprising RM161,130.53 for PBB, RM732,759.71 as retention sum, and RM532,999.49 for a nominated sub-contractor (NSC). Granstep withheld RM893,890.24 from PBB's portion, claiming set-off for Liquidated and Ascertained Damages (LAD) due to 152 days of delay in completing Section 3 works (calculated at RM12,800 per day, totaling RM1,945,600).
PBB issued a Payment Claim under CIPAA on 1 August 2023. Granstep responded on 14 August 2023, denying the claim and counterclaiming the balance LAD of RM1,051,709.76. Adjudication commenced on 28 August 2023, with Adjudicator Goh Li Kian appointed. The adjudicator ruled in PBB's favor on 15 January 2024, ordering payment of the disputed amount plus interest and costs. Granstep then initiated three originating summonses: one to set aside the decision, one for a stay pending arbitration (initiated by Granstep on 18 July 2023 with Ar. Lim Fang Keong as arbitrator), and one by PBB to enforce the decision. The court heard them together.
The main legal questions were: (1) Did the adjudicator exceed jurisdiction under Section 15(d) CIPAA by treating CP 30 as an interim rather than final claim, and was PBB an "unpaid party"? (2) Was there a denial of natural justice under Section 15(b)? (3) Should execution be stayed under Section 16? (4) Should the decision be enforced under Section 28?
Granstep, as respondent and applicant in the setting aside and stay applications, argued that the adjudicator lacked jurisdiction under Section 15(d) CIPAA because CP 30 was a final certificate, outside CIPAA's scope for interim payments, and PBB was not an "unpaid party" due to the valid set-off for LAD exceeding the claimed amount. On natural justice under Section 15(b), Granstep claimed the adjudicator ignored its set-off defense and counterclaim, failed to summon the architect for sworn evidence on extension of time (EOT) issues, did not allow submissions on the architect's independence, made inconsistent EOT findings, overlooked the retention sum's protective role, and denied an EOT extension for its adjudication response.
For the stay under Sections 16(1)(a) and (b), Granstep contended that without a stay, the ongoing arbitration would be rendered nugatory, as the LAD claim (RM1,945,600) surpassed the adjudication amount, and enforcement would cause irreparable harm.
PBB countered that CIPAA applies to all payment claims under construction contracts, regardless of interim or final status, per Section 4 definitions, making it an "unpaid party" since CP 30 was for work done and unpaid. PBB argued no natural justice breach occurred, as the adjudicator considered all submissions without needing a hearing or architect testimony, given the decision to defer complex EOT/LAD issues to arbitration. PBB emphasized CIPAA's objective of timely payments to sustain cash flow. On enforcement under Section 28, PBB highlighted non-payment and no valid grounds for setting aside or staying, assuring ability to refund if arbitration ruled against it.
The court, applying precedents like Martego Sdn Bhd v. Arkitek Meor & Chew Sdn Bhd (Federal Court), affirmed CIPAA's broad scope under Section 4 to cover all payment claims for work done, rejecting distinctions between interim and final claims to avoid undermining the Act's cash flow protection purpose. In Martego , the Federal Court emphasized that confining CIPAA to interim claims would contradict legislative intent for speedy, economical dispute resolution.
On the "unpaid party" issue, the court held that set-off is merely a defense, not altering PBB's status as recipient of an unpaid certificate for rendered services. For natural justice under Section 15(b), drawing from MRCB Builders Sdn Bhd v. Wazam Ventures Sdn Bhd and ACFM Engineering & Construction Sdn Bhd v. Esstar Vision Sdn Bhd , the court clarified that adjudication requires procedural fairness but not merits review; errors of law or fact are for arbitration/litigation per Section 13(c). The adjudicator's extensive deliberation on set-off (AD paras 144-159) and deferral of EOT/LAD to another forum was proper, avoiding unqualified findings without evidence. No request for architect testimony was denied, per Section 25(a), and response filing complied with timelines under Section 25(p). In Alpha Galaxy Sdn Bhd v. Euro Destar (M) Sdn Bhd , the court reiterated that setting aside is limited to jurisdictional or serious procedural flaws, not dissatisfaction with outcomes.
For the stay under Section 16, citing Pasukhas Sdn Bhd v. Empire Multiple Sdn Bhd and Syarikat Berpakat v. Lim Kai Kok , the court exercised discretion, requiring special circumstances beyond mere arbitration pendency to avoid stultifying CIPAA. Granstep showed no evidence of irreparable harm. Enforcement under Section 28 was straightforward, as conditions in Inai Kiara Sdn Bhd v. Puteri Nusantara Sdn Bhd were met: favorable decision, non-payment, and no prohibitions.
The ruling distinguishes CIPAA adjudication as provisional and expeditious, preserving cash flow without preempting fuller dispute resolution via arbitration.
The High Court dismissed Granstep's setting aside application (OS no. BA-24C-8-02/2024) and stay application (OS no. BA-24C-9-02/2024), allowing PBB's enforcement application (OS no. BA-24C-5-01/2024). Granstep was ordered to pay PBB RM893,890.24 plus interest at 7.65% from 27 July 2023 to 15 January 2024, additional 5% p.a. post-deadline, and costs of RM59,249.68, with court costs of RM10,000 to PBB.
This decision reinforces CIPAA's role in ensuring prompt payments, preventing developers from using set-offs or arbitration to indefinitely delay contractor cash flow. It signals to the industry that adjudication decisions are robust against weak challenges, potentially reducing disputes and encouraging compliance, while deferring complex issues like LAD to arbitration. Future cases may see stricter scrutiny of "special circumstances" for stays, promoting efficiency in construction payments.
adjudication decision - set-off defense - liquidated damages - natural justice - jurisdiction challenge - cash flow protection
#CIPAA #Adjudication
Habeas Corpus Inapplicable to Child Custody Disputes Needing Detailed Welfare Inquiry: Delhi High Court
30 Apr 2026
Physical Assault and Threats Creating Psychological Fear Attract Section 8 Goa Children's Act: Bombay HC at Goa Refuses FIR Quashing
30 Apr 2026
Failure to Frame Specific Issues Under Section 13 HMA Leads to 'Ballpark Assessment': Patna High Court Remands Divorce Case
30 Apr 2026
No Sane Person De-Boards Running Train: Gujarat HC Upholds Rs 8 Lakh Compensation under Section 124A Railways Act
30 Apr 2026
Supreme Court Orders Action Against Noida Bar Strikes
30 Apr 2026
Delhi High Court Preserves Sunjay Kapur Assets Pending Trial
30 Apr 2026
PIL Dismissed with ₹25K Costs for Concealing Credentials & Pending Criminal Cases: Allahabad High Court
30 Apr 2026
Pendency of EP Against One Judgment Debtor No Bar to Proceed Against Guarantor: Andhra Pradesh High Court
30 Apr 2026
Madras High Court Denies Anticipatory Bail in Film Leak
30 Apr 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.