Homebuyer Remedies for Delayed Possession
Subject : Real Estate Law - Regulatory Compliance & Litigation
Gurugram, Haryana – The Haryana Real Estate Regulatory Authority (HRERA) has delivered a nuanced ruling that underscores both the builder's accountability for project delays and the homebuyer's obligation to assert their rights in a timely manner. In a significant order, the Authority directed developer Emaar MGF Land Limited to refund a homebuyer for a possession delay of nearly four years but permitted the builder to deduct 10% of the basic sale price as earnest money due to the homebuyer's own delay in filing the complaint.
The case, Babulal Aggarwal & anr v. Emaar MGF Land Limited , highlights a critical balance in real estate litigation: while a developer cannot indefinitely delay possession, a homebuyer's prolonged inaction after an offer of possession can have substantial financial consequences. The decision provides crucial guidance for legal practitioners navigating refund claims under the Real Estate (Regulation and Development) Act, 2016 (RERA).
The complainants, Babulal Aggarwal and another, purchased a flat in Emaar MGF's "Palm Gardens" project in Sector 83, Gurugram. The Builder Buyer Agreement, executed on September 12, 2012, stipulated a possession date of December 12, 2015. The total consideration for the flat was Rs. 1.22 crore, of which the homebuyers had paid a substantial Rs. 94.68 lakh, representing over 77% of the total price.
Despite receiving the majority of the payment, the builder failed to meet the deadline. The Occupation Certificate for the project was received on October 17, 2019, and an offer of possession was subsequently made to the homebuyers on October 23, 2019. This marked a significant delay of approximately three years and ten months from the contractually agreed-upon date.
However, the homebuyers did not immediately seek legal recourse. Instead, they filed their complaint with HRERA seeking a full refund with interest under Section 18 of the RERA Act nearly five years later, on September 5, 2024. This substantial gap between the offer of possession and the filing of the complaint became the central pivot upon which the Authority's decision turned.
Emaar MGF mounted a multi-pronged defense, arguing that the complaint was procedurally and substantively flawed. The key contentions were:
The HRERA bench, comprising Member Phool Singh Saini, carefully dissected the arguments. While implicitly rejecting the builder's force majeure and estoppel claims by proceeding to grant a refund, the Authority focused intently on the conduct of the homebuyers.
The core of the Authority's observation was the nearly five-year delay between the offer of possession in October 2019 and the filing of the complaint in September 2024. The Authority held that this "belated" action by the homebuyers justified the forfeiture of earnest money by the builder.
To determine a reasonable amount for forfeiture, the Authority traced the jurisprudence on earnest money, establishing a clear legal framework. It referenced foundational Supreme Court rulings, including Maula Bux versus Union of India (1970) and Sirdar K.B. Ram Chandra Raj Urs versus Sarah C. Urs (2015) , which established the principle that any forfeiture must be a reasonable measure of damages and not a penalty.
Further bolstering its reasoning, the Authority cited a series of National Consumer Disputes Redressal Commission (NCDRC) decisions, such as Ramesh Malhotra versus Emaar MGF (2020) and Saurav Sanyal versus IREO (2022) . These precedents have consistently held that forfeiture of up to 10% of the basic sale price is generally considered a fair and reasonable practice.
Based on this established legal position, the Authority concluded, "the builder cannot retain more than ten percent of the sale consideration as earnest money."
The Authority directed Emaar MGF to refund the amount paid by the homebuyers (Rs. 94.68 lakh) after deducting 10% of the basic sale consideration of Rs. 94.60 lakh. This amounts to a deduction of Rs. 9.46 lakh.
Furthermore, the builder was ordered to pay interest on the net refundable amount at a rate of 10.85% per annum. Critically, the interest is to be calculated not from the dates of payment by the homebuyers, but from the date of filing the complaint (September 5, 2024) until the date of the actual refund. This significantly reduces the interest liability for the builder, directly penalizing the homebuyers for their delay in seeking legal remedy.
This ruling sends a clear message to the legal community and homebuyers alike:
This case serves as a vital precedent, refining the application of Section 18 of the RERA Act. It demonstrates that while developers remain liable for their failures, regulatory bodies are increasingly willing to scrutinize the conduct of all parties and apportion costs based on their respective diligence and delays. Legal counsel advising homebuyers must now emphasize not only the strength of their claim but also the critical importance of timely filing to maximize potential relief.
#RealEstateLaw #RERA #HomebuyerRights
Rigors of Section 37 NDPS Act Prevail Over Detention Period Claims: High Court of J&K and Ladakh
11 Mar 2026
Failure to Pay Compensation Vitiates Limitation Claims in Land Acquisition: High Court of Jammu and Kashmir and Ladakh
04 Mar 2026
Discretionary Nature of Section 143-A NI Act: J&K&L High Court Upholds Interim Compensation Based on Accused's Conduct
12 Jun 2026
Salman Khan Files Delhi HC Plea Against 'Kala Hiran'
12 Jun 2026
Writ Court Cannot Exercise Jurisdiction to Grant Interim Relief After Directing Litigant to Civil Forum: MP High Court
12 Jun 2026
Delayed Registration of Birth Certificate Without Statutory Compliance Is Not Proof of Minority: Sikkim High Court
12 Jun 2026
Personal Participation in Contract Work Creates Employer-Employee Tie Under Employees Compensation Act: Kerala High Court
12 Jun 2026
Supreme Court Dismisses Plea Against Rajya Sabha Nomination Rejection
12 Jun 2026
Insufficient Evidence to Prove Minority or Kidnapping: Gujarat High Court Acquits Two in Atrocity Act Case
29 Jan 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.