The conducted an emergency hearing on a Sunday during the Puja holidays to address the critical blockade of the by local agitators. The intervention came after the filed an regarding the obstruction of all 11 gates by a group led by local MLA Sweta Singh and members of the . The court, presided over by Justice Sujit Narayan Prasad, prioritized the matter after it was brought to the attention of the Chief Justice, noting the severe risks associated with the forced cessation of operations at the integrated steel facility.
Ensuring Operational Continuity and Safety
The management of the
had informed the court that the blockade, which began in the early hours of
, created a
"near to be a hostage situation."
With approximately 3,500 employees and workers trapped inside the plant premises, the facility faced immediate concerns regarding food, water, and medical supplies. More critically, the plant serves as a continuous-process unit that has remained operational since its inception in 1966. Management warned that any unplanned, forced shutdown without the standard seven-day preparation period would jeopardize the safety of the facility.
The company explicitly highlighted the technical hazards, stating that a sudden halt could lead to the
"solidification of approximately 12,000 tons of molten steel in the blast furnaces, causing equipment damage running into thousands of crores of rupees, besides posing serious environmental hazards and potential threats to human life."
The facility, which handles high-pressure gas pipelines and molten iron, requires around-the-clock maintenance to prevent catastrophic industrial accidents.
District Administration Intervention
During the proceeding, the Deputy Commissioner of Bokaro, Ajay Nath Jha, appeared through virtual mode and confirmed that the district administration had taken proactive measures to disperse the protesters. He informed the bench that the administration engaged in intensive persuasion with the agitators to ensure the restoration of essential services.
Following these efforts, the Deputy Commissioner reported that Gate No. 01 was the first to be reopened, allowing the stranded workforce to exit and return to their residences. When questioned by the court regarding the remaining ten gates, the district official confirmed that all points of had been cleared. The petitioner’s counsel, appearing for SAIL, verified that movement into and out of the plant had resumed, though the company expressed ongoing apprehension regarding the stability of the situation.
In response to the court’s rigorous questioning, the Deputy Commissioner provided a
regarding the protection of the plant. As recorded in the
,
"The Deputy Commissioner, Bokaro has reiterated before this Court not only once but thrice that the apprehension of disruption shall not be permitted to emerge. He has assured that all effective measures will be adopted to prevent any obstruction in the
of employees and executives to and from the unit at the commencement and conclusion of their duty shifts."
Relying on this assurance, the court decided against summoning the Secretary of the
at this stage.
Historical Employment Litigation Context
The petition also touched upon the long-standing legal history regarding employment demands for displaced persons whose land was acquired decades ago for the plant's construction. Counsel for the petitioner referenced previous directives, specifically an order from , which sought to bring finality to the issue of job claims.
The
had previously observed that after four decades of the project's completion, the persistent litigation was not sustainable. In its 2008 ruling, the apex court directed that 970 individuals identified in a specific category be considered for employment preference when vacancies arose, noting that
"consideration of the names of persons for employment does not give them a right to appointment."
A subsequent order in
further affirmed that the court was
"not inclined to entertain any application in a
which itself is no more pending before this Court,"
effectively directing that the matter be given a
.
Procedural Status and Future Oversight
The High Court chose not to issue notices to the MLA or the Visthapit Apprentice Sang at this stage, opting instead to monitor the administration's compliance with its assurance. Justice Sujit Narayan Prasad emphasized the necessity of preventing any resurgence of the blockade, stating that the court would maintain its oversight of the situation.
The matter has been formally scheduled for further hearing on , as the first case of the day. To ensure accountability, the court has directed the Deputy Commissioner and the Superintendent of Police of Bokaro to file outlining the measures taken to maintain law and order, specifically confirming their commitment to preventing further obstructions at the plant gates. The court’s intervention has effectively restored operational access to the facility, mitigating the immediate risk of industrial damage and ensuring the safety of the workforce during the remainder of the holiday period.
industrial safety - administrative accountability