The High Court of Madhya Pradesh at Indore has dismissed an application for the appointment of a sole arbitrator , ruling that the dispute resolution provision in a 2015 development agreement does not constitute a valid, binding arbitration clause . Justice Vinay Saraf, presiding over the case, determined that because the agreement expressly permitted parties to seek relief from civil courts if arbitration failed, it lacked the essential element of finality required for an enforceable arbitration mechanism under the Arbitration and Conciliation Act, 1996 .

The dispute involved M/S Global Buildocon , a developer, and landowners Harsh Chauhan and another, concerning a residential project named "Global Towers" proposed for development on 1.225 hectares of land situated in Village Bada Bangarda, Tehsil Hatod, District Indore. The development agreement, executed on March 26, 2015 , and registered in April of the same year , sought to construct a P+6 multi-dwelling residential unit. However, the project stalled after the landowners reportedly failed to meet critical conditions regarding the renewal of permissions from the Town and Country Planning Department and the physical handover of the demarcated land.

The developer claimed to have invested ₹1 crore in advance payments and an additional ₹25 lakh for stamp duty and registration expenses. Following years of inactivity, the developer issued a notice in March 2026 , demanding a full refund of these amounts with interest. Upon the landowners' refusal to settle the claim and their denial of the existence of a valid arbitration agreement, the developer filed an application under Section 11(6) of the Arbitration and Conciliation Act, seeking the court’s intervention to appoint a sole arbitrator .

Evaluating the Dispute Resolution Clause

The central legal controversy revolved around Clause 5 of the development agreement. The developer’s counsel, Senior Advocate Vishal Baheti , argued that the clause served as a valid arbitration agreement, noting that the mention of subsequent civil court recourse did not negate the parties' initial intent to refer disputes to a private tribunal . Counsel relied upon Supreme Court precedents, including the judgment in Zhejiang Bonly Elevator Guide Rail Manufacture Company Limited v. Jade Elevator Components , to suggest that clauses providing options for either arbitration or litigation could still be interpreted as valid arbitration agreements when the petitioner exercises the choice of arbitration.

Conversely, Advocate Aniket Naik , representing the respondents, argued that Clause 5 was fundamentally flawed. He contended that for a clause to constitute a binding arbitration agreement, it must mandate that the decision of the private forum be final and binding on all involved parties. By explicitly stating that parties could approach civil courts if the arbitration failed to resolve the dispute, the agreement effectively stripped the arbitral process of its binding character.

Justice Saraf, after carefully examining the wording of the agreement, sided with the respondents. The court observed, “The Clause 5 cannot be treated as an arbitration clause, because the clause itself provides that if the arbitrators are failed to decide the dispute, the parties will be free to approach Civil Court or any other Court.”

The court clarified that a genuine arbitration agreement requires a clear, unmistakable intention for the dispute to be settled by a private tribunal , with the understanding that the tribunal’s decision is final and conclusive. Relying on established legal standards from the Supreme Court , including the rulings in K.K. Modi v. K.N. Modi and the recent Alchemist Hospitals Ltd. v. ICT Health Technology Services India (P) Ltd. , the court held that mere usage of the word "arbitration" does not convert an optional or non-binding dispute resolution mechanism into a statutory arbitration agreement .

Assessing the Limitation Period for Claims

Beyond the validity of the arbitration clause, the High Court also addressed the merits of the underlying financial claim, labeling it as " dead wood ." Under the provisions of the Arbitration and Conciliation Act, the law of limitation applies to arbitration proceedings. The court noted that the development agreement was executed in 2015, with the advance payments made concurrently. However, the formal demand for the return of these funds was only raised by the developer in March 2026 —nearly eleven years after the initial transaction.

Citing the ruling in Vidya Drolia v. Durga Trading Corporation , the court emphasized its duty to conduct a preliminary examination of the dispute to filter out "manifestly ex-facie non-existent and invalid arbitration agreements" or claims that are clearly time-barred . The court held that the developer's request for recovery, being filed well beyond the standard three-year limitation period applicable to money recovery suits , rendered the claim " dead wood ."

In its final order, the High Court declined to appoint an arbitrator, emphasizing that the absence of a binding arbitration agreement precludes the exercise of powers under Section 11 of the Arbitration and Conciliation Act . The court concluded that, given the circumstances of the agreement and the nature of the claim, the parties remain free to pursue their remedies through the competent civil court in accordance with law. The application was subsequently dismissed, with no order issued regarding costs, leaving the developer to seek redress through traditional litigation channels if they wish to continue pursuing the claim.