Setting Aside Arbitral Award
Subject : Dispute Resolution - Arbitration
CHENNAI – In a significant ruling that reinforces the limited but crucial grounds for judicial intervention in arbitral awards, the Madras High Court has set aside an award, citing patent illegality, violations of natural justice, and mutually contradictory findings by the same arbitrator. Justice N. Anand Venkatesh, in the case of TRULIV Properties and Services Private Limited Vs C. Ravishankar , held that the arbitrator's award was riddled with "multiple infirmities both procedural and substantive," ultimately rendering a decision that "shocks the conscience" of the Court.
The judgment provides a detailed analysis of what constitutes a "perverse finding" and underscores the principle that an arbitrator cannot rewrite the contract between parties or venture beyond the scope of the pleadings.
The case originated from a lease agreement between Truliv Properties and Services Pvt. Ltd (the Petitioner) and C. Ravishankar (the Respondent), the owner of 20 flats in the 'Sobha Serene' project in Chennai. Under the agreement, Truliv invested a substantial sum of Rs. 32.4 lakhs, with further investments made in furnishing the properties.
The commercial relationship soured when Truliv discovered that the Respondent had previously given an undertaking before another arbitral tribunal not to alienate or encumber the very same properties. This pre-existing undertaking effectively jeopardized Truliv's leasehold rights and the viability of their investment. Consequently, Truliv sought to terminate the agreement and demanded a refund of its investment, a request the Respondent refused.
This led the parties to arbitration. However, the outcome was startling: the arbitrator not only dismissed Truliv's claims but also directed it to pay a staggering Rs. 1.99 crore to the Respondent as part of a counterclaim. Aggrieved by this award, Truliv filed a petition before the Madras High Court under Section 34 of the Arbitration and Conciliation Act, 1996, seeking to have the award set aside.
Justice N. Anand Venkatesh meticulously dissected the arbitral award and identified several fundamental flaws that warranted its nullification. The Court's findings highlight critical guardrails for arbitral proceedings.
The most glaring issue identified by the Court was the stark contradiction between the arbitrator's findings in an interim order under Section 17 and those in the final award. The Court observed that the arbitrator had made conflicting determinations on the same issues at different stages of the proceeding.
Justice Venkatesh stated, “the finding that was rendered at the time of passing the interim order and the finding that was rendered at the time of passing the final award are mutually contradictory. The above perverse finding is also irrational, since the same Arbitrator could not have rendered one finding at the time of passing the interim order and a completely conflicting finding at the time of passing the final award.”
This inconsistency, the Court held, went to the root of the award's validity, rendering it patently illegal. It established that an arbitrator is bound by a degree of consistency and cannot arbitrarily reverse their own reasoned findings without compelling justification.
A significant procedural overreach by the arbitrator involved a suo motu finding concerning the legal status of the Respondent’s prior undertaking. The arbitrator declared the earlier proceedings, where the undertaking was recorded, to be non est (non-existent in the eyes of the law), reasoning that the record was not signed by all tribunal members.
The High Court found this to be a "clearly a perverse finding" on multiple levels. Firstly, the Court clarified that a simple recording of an undertaking does not constitute an "order" or "award" that must comply with the formal requirements of Section 31 of the Arbitration Act. Justice Venkatesh noted, “the proceedings dated 27.12.2016 cannot even be considered to be an order, since the Arbitral Tribunal merely recorded the undertaking given by the respondent. To read Section 31 of the Act into the said proceedings and give a finding that it is non est in the eye of law, is clearly a perverse finding.”
More critically, the Respondent had never raised this argument in his pleadings. By taking up this issue suo motu , the arbitrator had ventured beyond the case presented by the parties, thereby violating the principles of natural justice and contravening Section 34(2)(d)(iv) of the Act.
Another central pillar of the Court's decision was the arbitrator's treatment of the lease agreement. The arbitrator had concluded that because the lease deed was unregistered, it should be treated as an "oral agreement" governed by Sections 106 and 108 of the Transfer of Property Act, 1882.
The High Court deemed this conclusion "wholly perverse" and a patent illegality. Justice Venkatesh strongly rebuked this line of reasoning, stating, “The finding of the learned Arbitrator has no legal basis, since the learned Arbitrator has presumed that there is an oral agreement when in fact, there was a written agreement between the parties... The Arbitrator has re-written the contract itself, which is a patent illegality falling foul of Section 34(2A) of the Act.”
The Court clarified that the provisions of the Transfer of Property Act, such as Section 108, apply only in the absence of a contract to the contrary. Here, a written contract clearly existed, and its terms could not simply be ignored or replaced by a legal fiction of an oral agreement.
Perhaps the most inequitable part of the arbitral award was the direction for Truliv to pay rent of Rs. 2.32 crore for a period of nearly four years (September 2019 to May 2023). This was awarded despite the arbitrator's own acknowledgment that the project had been halted shortly after the discovery of the Respondent's prior undertaking not to encumber the property.
The Court found this directive to be fundamentally unjust. It was the Respondent's own concealment and prior conflicting commitment that made the contract unworkable. Awarding him rent for this period was, in the Court's view, a reward for his misconduct.
Justice Venkatesh held that “the Arbitrator directing the petitioner to pay rents to the respondent for the period from 11.09.2019 to 31.05.2023 is more in the nature of giving premium for the illegality committed by the respondent... such finding also shocks the conscience of this Court.”
The Court further acknowledged the "mental agony" suffered by the Petitioner since 2019 due to the Respondent's actions and affirmed that Truliv was entitled to damages for this harm.
The decision in Truliv Properties serves as a potent reminder of the judiciary's role in ensuring that arbitration, while being an alternative dispute resolution mechanism, does not become a forum for arbitrary or unjust outcomes. By setting aside the award on the grounds of patent illegality, perversity, violation of natural justice, and for shocking the judicial conscience, the Madras High Court has reinforced the strict standards that arbitral awards must meet.
For legal practitioners, this judgment offers clear guidance on the types of errors—both substantive and procedural—that can vitiate an award. It highlights that an arbitrator's duty is to interpret the contract and adjudicate the dispute as pleaded, not to create a new narrative or a different contract for the parties. The ruling stands as a strong precedent against inconsistent reasoning and awards that reward a party's own wrongdoing.
#Arbitration #PatentIllegality #NaturalJustice
No Absolute Bar on Simultaneous Parole/Furlough for Co-Accused Under Delhi Prisons Rules: Delhi High Court
30 Apr 2026
Rejection of Jurisdiction Plea under Section 16 Arbitration Act Not Challengeable under Section 34 Till Final Award: Supreme Court
30 Apr 2026
'Living Separately' Under Section 13B HMA Means Cessation Of Marital Obligations, Regardless Of Residence: Patna High Court
30 Apr 2026
Consolidated SCNs under Sections 73/74 CGST Act Permissible Across Multiple FYs: Karnataka HC
01 May 2026
Allahabad HC Stays NCLT Principal Bench Order Mandating Joint Scrutiny of Allahabad Bench Filings
01 May 2026
Bombay HC Grants Interim Protection from Arrest Despite Pending Anticipatory Bail in Lower Court Due to Accused's Marriage: Sections 351(2), 64(2)(m), 74 IPC
01 May 2026
Heavy Machinery Barred in Mining Leases Except Dredging: Uttarakhand HC Directs DM to Enforce Rule 29(17) of Minor Mineral Rules
01 May 2026
No Deemed Confirmation After Probation Without Written Order Under Model Standing Orders Clause 4A: Bombay High Court
01 May 2026
CJI Declares Sikkim India's First Paperless Judiciary
01 May 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.