The National Company Law Tribunal (NCLT), New Delhi Bench, has dismissed an insolvency petition filed by M/s Metro Infratech against Jaishnavi Eminence Pvt. Ltd., ruling that the operational creditor failed to meet the mandatory financial threshold required to initiate the Corporate Insolvency Resolution Process (CIRP) under the Insolvency and Bankruptcy Code (IBC), 2016. The tribunal determined that significant portions of the alleged debt were either contractually barred or prematurely claimed, rendering the remaining balance insufficient to trigger insolvency proceedings.

The dispute centered on an alleged operational debt of ₹3,47,63,938.93, which Metro Infratech claimed was outstanding from work orders executed for the provision and laying of Granular Sub-Base and Wet Mix Macadam. During the proceedings, the operational creditor sought recovery of this amount through a Section 9 IBC application. However, the tribunal’s scrutiny revealed that the core of the claimed default relied upon charges for royalty and retention money that did not qualify as legally enforceable debt within the context of the operational contract.

Contractual Clauses Bar Independent Royalty Claims

The adjudicating authority, comprising Judicial Member Manni Sankariah Shanmuga Sundaram and Technical Member Reena Sinha Puri, focused heavily on the specific terms stipulated in the work orders. Regarding the claim of ₹82,79,009 for royalty payments, the bench highlighted that Clause 8 of the agreement dated March 15, 2021, explicitly precluded such independent demands. The contract stipulated that all statutory duties, levies, and royalties were deemed to be included in the contractor's initial quoted rates, explicitly barring subsequent claims for these costs.

In its order, the tribunal observed, “Except CGST/SGST/IGST, all other taxes, duties levies, labour cess royalties or any other statutory obligation shall be deemed to be included in the quoted rates of the contractor. No claim on this account will be entertained or allowed at any stage subsequently.” By invoking this provision, the NCLT concluded that the royalty amount had been improperly included in the calculation of the total debt, thereby significantly reducing the operational creditor’s claim.

Timing Disputes Over Retention Money

The petition also faltered on the inclusion of ₹2,61,11,564 in retention money. The tribunal’s analysis of Clauses 16 and 17 of the work order established that the retention money was only refundable after the completion of a 24-month Defect Liability Period, which commenced from the certified date of completion. Given that the work was completed on May 15, 2022, the defect liability period extended until May 15, 2024.

The tribunal noted that Metro Infratech had declared the date of default as May 23, 2022, despite the fact that the retention money was not contractually due until two years later. Consequently, the bench held that the retention money could not be classified as a debt in default at the time the petition was filed. The tribunal stated, “In view of this, we are of a view that the retention money has also been wrongly included in the default amount so claimed, in the present Petition.”

Statutory Thresholds and Future Proceedings

Once the tribunal stripped the claim of the contested royalty and prematurely demanded retention money, the remaining amount stood at only ₹4,13,604.93. This sum, related to a final sales invoice from May 20, 2022, failed to meet the statutory threshold of ₹1 crore prescribed under Section 4 of the IBC. Referring to the precedent set by the Supreme Court in the case of Mobilox Innovations Private Limited v. Kirusa Software Private Limited , the NCLT emphasized that an application under Section 9 is only maintainable if the operational debt exceeds this minimum threshold.

The corporate debtor had further contended that the accounts had been fully settled in 2023 through a series of cross-debit adjustments necessitated by the contractual chain involving the main contractor, Welspun. While the tribunal acknowledged the complexity of the commercial accounting, it ultimately found that the failure to reach the jurisdictional financial limit rendered a detailed examination of those factual disputes unnecessary for the purpose of the current insolvency petition.

By dismissing the petition, the NCLT has reinforced the principle that the insolvency framework is designed for the resolution of genuinely distressed companies and cannot be utilized as a substitute for civil recovery proceedings where the debt is either disputed, below statutory thresholds, or not yet due. The operational creditor remains free to pursue alternative legal avenues, such as civil suits or pending proceedings under Section 138 of the Negotiable Instruments Act, 1881, for the recovery of any remaining dues, provided those claims are grounded in enforceable contractual rights. The ruling serves as a cautionary note for operational creditors to meticulously verify their claims against contractual stipulations before initiating the high-stakes process of corporate insolvency.