The National Company Law Tribunal (NCLT) Kolkata has dismissed an application filed under Section 9 of the Insolvency and Bankruptcy Code (IBC) by Jay Ambe Petrochem and Infra, citing the premature initiation of insolvency proceedings against Techno Global Services Private Limited. The bench, comprised of Member (Judicial) Bidisha Banerjee and Member (Technical) Rekha Kantilal Shah, concluded that the operational creditor issued a demand notice before the contractually mandated payment deadline had expired, characterizing the move as an attempt to exert undue pressure on the corporate debtor. In addition to dismissing the petition, the tribunal imposed a cost of ₹1,00,000 upon the operational creditor, payable to the Prime Minister’s National Relief Fund within 15 days.

The dispute originated from a contractual agreement entered into on October 3, 2022, between the two companies for civil works regarding the upgradation of RESA-32 at the Chhatrapati Shivaji Maharaj International Airport in Mumbai, a project overseen by Howe Engineering Projects (India) Pvt. Ltd. Following the completion of specific work phases, the operational creditor submitted several invoices dated March 25, 2023, totaling approximately ₹1.5 crore. Merely three days later, on March 28, 2023, the operational creditor issued a formal demand notice under Section 8 of the IBC, which was subsequently served by email on March 31, 2023.

Techno Global Services contested the claim, asserting that the operational creditor had committed numerous contractual breaches, including unauthorized direct contact with the client and a failure to provide the mandatory performance bank guarantee. More significantly, the corporate debtor highlighted that it had already paid ₹83,45,623 directly to vendors and sub-vendors to ensure the continuity of site operations. The debtor argued that this amount should have been deducted from the outstanding RA bills, further complicating the debt calculation and underscoring a pre-existing dispute between the parties.

Contractual Deadlines and Statutory Compliance

The tribunal’s decision hinged on the interpretation of payment terms stipulated in the original agreement. Clause 14 of the contract between the parties provided a 30-day window for payments to be settled following the submission of a clear, certified invoice. The bench observed that by issuing a demand notice on March 28, 2023, the operational creditor had acted in complete disregard of the agreed-upon grace period. The court emphasized that the existence of a clear default is a fundamental prerequisite for invoking the insolvency process, a requirement that cannot be bypassed by anticipating future payment failures.

As the tribunal noted in its ruling: “The issuance of the Demand Notice before the expiry of the contractually agreed payment period deprived the Corporate Debtor of the opportunity to discharge its payment obligations within the time expressly agreed upon between the parties. Such premature invocation of the insolvency process raises concerns regarding the bona fides of the Operational Creditor in initiating proceedings under the IBC.”

The bench further addressed the operational creditor's attempt to reconcile its claims amidst the ongoing project disputes. While the creditor argued that the payments made by the corporate debtor to third-party vendors were unauthorized and did not reduce the principal debt, the tribunal found the correspondence on record sufficiently established a plausible, pre-existing dispute. The court noted that because the parties held conflicting views on the allocation of payments and the validity of invoices, the matter necessitated further investigation that fell outside the limited summary jurisdiction of an insolvency proceeding.

Investigating Pre-existing Disputes

Under the settled legal framework established by the Supreme Court in Mobilox Innovations Pvt. Ltd. v. Kirusa Software Pvt. Ltd. , an adjudicating authority must determine whether a genuine dispute exists before admitting a Section 9 application. The Kolkata bench found that the disagreement concerning the ₹83 lakh in vendor payments was neither spurious nor illusory. It explicitly stated: “At the stage of examining the application under Section 9 of the IBC, this Tribunal cannot delve into the merits of the dispute and adjudicate upon the rights and obligations of the parties. Since the correspondence on record indicates the existence of a plausible dispute regarding the payments made to the vendors and their adjustment against the amounts claimed by the Operational Creditor, the same warrants further investigation and constitutes a pre-existing dispute for the purposes of Section 9 of the IBC.”

The tribunal’s findings indicate a firm stance against the misuse of the IBC as a recovery mechanism. By rushing to file for insolvency within days of invoice issuance, the operational creditor bypassed the internal dispute-resolution mechanisms designed into the contract. The bench remarked: “Evidently, the Operational Creditor sought to initiate the insolvency process before the debt even fell due. The deliberate disregard of the agreed payment terms and the premature issuance of Section 8 Demand Notice demonstrates that the Operational Creditor sought to exploit the provisions of IBC as a means of exerting undue pressure upon the Corporate Debtor to recover the debt.”

The dismissal of the petition marks a significant procedural warning for creditors intending to leverage the IBC in commercial disputes. By affirming that the likelihood of default cannot substitute for an actual, matured default, the NCLT has reinforced the sanctity of contractual payment schedules and the necessity of strict compliance with the statutory notice requirements. The registry of the tribunal has been directed to ensure the recovery of the imposed costs, while both parties are now expected to seek alternative remedies to resolve their underlying contractual grievances through arbitration or standard civil litigation as provided for in their original agreement. This order effectively closes the insolvency chapter of this dispute, leaving the parties to address their financial disagreements through the mechanisms they originally negotiated for their business relationship.