CERC Upholds Tariff Order, Rejects Review Plea on Coal GCV Data
New Delhi
- The Central Electricity Regulatory Commission (CERC) has dismissed a review petition filed by GRIDCO Limited, affirming its earlier decision on the tariff truing-up for
The bench, comprising Chairperson Jishnu Barua and Members Ramesh Babu V. and
Background of the Dispute
The case originated from a CERC order dated April 17, 2023, which finalized the trued-up tariff for
The IoWC is partially determined by fuel cost, which in turn depends on the GCV of coal. Regulations require using the GCV on an 'as received' basis for the three months preceding the tariff period, i.e., January to March 2014.
Arguments from Both Sides
GRIDCO's Contentions:
The review petitioner, GRIDCO, argued that the Commission committed a clear error by accepting
Admission of No Infrastructure:
Questionable Data:
The data
Deviation from Methodology: GRIDCO claimed the Commission had deviated from a provisional formula it had prescribed in a 2017 tariff order, which was meant to be used in the absence of reliable 'as received' data.
Commission's Analysis and Decision
The CERC systematically analyzed the arguments and concluded that no grounds for review were established. The Commission's reasoning rested on several key points:
Conscious Decision, Not an Error:
The Commission clarified that its decision to use the data submitted by
Truing-Up Corrects Provisional Arrangements: The Commission noted that the use of a formula based on 'as billed' GCV in the original 2017 tariff order was a provisional measure. The very purpose of a truing-up exercise is to replace such provisional figures with actual data. The judgment stated, "There is also no change in the methodology at the time of truing up of tariff... the provisional GCV value of coal... was corrected at the time of truing up of tariff by considering the ‘as received’ GCV of coal for the said three months."
High Bar for Review: Citing the Supreme Court in Parsion Devi Vs. Sumitra Devi , the Commission reiterated that a review is not an appeal in disguise. An error must be self-evident and not one that requires a detailed process of reasoning to uncover. The Commission found that GRIDCO's arguments were essentially a disagreement with the merits of the decision, not an identification of a patent error.
Consistency with Precedent:
The CERC also noted that it had recently rejected a similar review petition (Petition No. 12/RP/2024) filed by GRIDCO on the same issue concerning another
Final Order
The Commission disposed of the review petition, holding it to be not maintainable on merits. The decision reinforces the principle that a regulatory body's considered choice to rely on actual data furnished by a party during a final truing-up process, in place of a previously used provisional methodology, does not in itself constitute a reviewable "error apparent on the face of the record."