Case Law
Subject : Dispute Resolution - Arbitration
The Court affirmed that parties acting under an original agreement, even as non-signatories, are bound by its arbitration clause, leaving the final determination of jurisdiction to the arbitral tribunal under the 'kompetenz-kompetenz' principle.
Kolkata: In a significant ruling on the law of arbitration, the Calcutta High Court, presided over by Justice Shampa Sarkar , has allowed an application for the appointment of an arbitrator, holding that successors in interest who adopt a principal agreement in its entirety are prima facie bound by its arbitration clause, even if they were not original signatories.
The Court appointed a three-member arbitral tribunal to adjudicate the dispute between property owner
The case originated from a license agreement dated January 19, 2001, between the petitioner's predecessor, Smt. Duija Devi Shaw, and the respondent's predecessor,
Over time,
Disputes arose when the petitioner alleged non-payment of license fees from 2018 and the respondent's failure to vacate the premises after the agreement expired in December 2020. The petitioner invoked arbitration, which the respondent contested.
Petitioner's Stance: Advocate Shaunak Ghosh, representing the petitioner, argued that the supplementary agreement incorporated all terms of the original contract by reference, including the arbitration clause. He emphasized that both parties were successors to the original signatories and that the respondent, by its conduct and admissions in its affidavit, had acted under and accepted the terms of the 2001 agreement.
Respondent's Counter: Senior Advocate S. N. Mitra, for Indus Towers, contended that the 2014 supplementary agreement did not contain an arbitration clause. He argued that a mere general reference to the original contract was insufficient to incorporate the arbitration clause, which is a separate agreement. Citing precedents like M.R. Engineers and Contractors Pvt. Ltd. v. Som Datt Builders Ltd. , he asserted that the supplementary agreement should have made a specific reference to the arbitration clause to make it binding.
Justice Shampa Sarkar , in her judgment, navigated the complex issue by focusing on the conduct of the parties and the doctrine of kompetenz-kompetenz (the arbitral tribunal's power to rule on its own jurisdiction).
The Court noted that the respondent had, by its own admission, continued to occupy the premises and make payments under the terms of the original 2001 agreement. The supplementary agreement's language, making it "co-extensive and co-terminus" with the principal one, suggested an intention to adopt the original contract in its entirety.
"Whether non-signatories to the principal agreement is bound by the terms and conditions of the principal agreement shall be finally decided by the learned arbitral tribunal, but this court, prima facie, finds that both the parties are intrinsically connected with the principal agreement and chose to abide by the terms and conditions, in their entirety."
The Court distinguished the M.R. Engineers case, stating that here, the parties had accepted the entirety of the principal agreement, not just made a general reference to it.
Citing a series of recent Supreme Court judgments, including Cox & Kings Ltd. v. SAP (India) (P) Ltd. and Adavya Projects Pvt. Ltd. v. Vishal Structurals Pvt. Ltd. , the Court highlighted that the issue of whether a non-signatory is a party to an arbitration agreement is a jurisdictional question best left for the arbitral tribunal to decide under Section 16 of the Arbitration and Conciliation Act, 1996. The referral court's role is limited to a prima facie examination of the existence of an arbitration agreement.
The Court allowed the application, appointing a three-member arbitral tribunal comprising Mr.
This judgment reinforces the pro-arbitration stance of Indian courts, emphasizing minimal judicial interference and upholding the principle that jurisdictional challenges, including the impleadment of non-signatories, fall squarely within the domain of the arbitral tribunal. It serves as a reminder that a party's conduct and the clear intent expressed in subsequent agreements can be sufficient to bind them to an arbitration clause from a preceding contract.
#Arbitration #CalcuttaHighCourt #ContractLaw
Delayed Registration of Birth Certificate Without Statutory Compliance Is Not Proof of Minority: Sikkim High Court
12 Jun 2026
Personal Participation in Contract Work Creates Employer-Employee Tie Under Employees Compensation Act: Kerala High Court
12 Jun 2026
Supreme Court Dismisses Plea Against Rajya Sabha Nomination Rejection
12 Jun 2026
Insufficient Evidence to Prove Minority or Kidnapping: Gujarat High Court Acquits Two in Atrocity Act Case
29 Jan 2026
Ex-Parte Order Without Notice or Jurisdiction Constitutes 'Gross Abuse of Process': Rajasthan High Court
15 Jun 2026
Mandatory Administrative Enquiry Precedes FIR Against Public Servants Under SC/ST Act: Uttarakhand High Court
16 Jun 2026
Assigning Administrative Charges to Tainted Officials Violates Natural Justice: MP High Court Quashes PWD Order
16 Jun 2026
Outsourced Employees Lack Right to Promotion; Unauthorized Designation Upgrades Are Legally Void: Uttarakhand High Court
16 Jun 2026
Calcutta HC Questions Speaker’s Power to Appoint LoP
16 Jun 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.