Case Law
2025-11-28
Subject: Civil Law - Arbitration Law
Kolkata: In a significant ruling on the scope of interim measures in arbitration, the Calcutta High Court has held that a post-award petition under Section 9 of the Arbitration and Conciliation Act, 1996, cannot be used to seek reimbursement for a monetary liability that arose after the arbitral award was published.
Justice Gaurang Kanth, while dismissing the petition in Rakesh Kumar Jindal and Anr. v. Anoop Kumar Jindal and Ors. (A.P. 117 of 2022) , clarified that the court's power under Section 9 is ancillary and protective in nature, intended to preserve the subject matter of arbitration or secure the fruits of the award. It does not extend to adjudicating fresh disputes or granting final monetary reliefs that were not part of the original arbitration.
The dispute arose between partners of the firm M/s. Chander Niwas, which owns a valuable multi-storied property at Shakespeare Sarani, Kolkata. Following disputes, the matter was referred to arbitration, culminating in an award on December 23, 2019. This award is currently under challenge by both parties in separate petitions under Section 34 of the Act.
Subsequent to the award, the firm faced a substantial property tax liability of over Rs. 1.89 crore to the Kolkata Municipal Corporation (KMC). To take advantage of a limited-period waiver scheme offered by the KMC, which reduced the payable amount to approximately Rs. 44.42 lakh, the petitioners paid the entire sum from their personal funds to protect the firm's primary asset.
Having received only partial reimbursement of Rs. 20 lakh from a court-appointed Receiver, the petitioners filed the present Section 9 application, seeking a direction for the other three respondent partners to pay their respective shares, calculated at Rs. 5,50,108/- each.
For the Petitioners: Mr. Shreyaan Bhattacharyya, counsel for the petitioners, argued that the payment was made in good faith to secure a substantial benefit for the partnership firm as a whole. He contended that the respondents, being equal partners, reaped the benefits of this action and could not evade their statutory liability to reimburse the petitioners. The action was taken to prevent coercive measures against the firm's property, thus falling within the protective ambit of Section 9.
For the Respondents: Senior Advocate Mr. Sudip Deb, representing the respondents, countered that the petition was not maintainable. He submitted that the KMC tax liability arose after the arbitral award was rendered and was therefore a "post-award event" not contemplated in the award. He argued that the petitioners were essentially seeking enforcement of a fresh monetary claim under the guise of a Section 9 application, which is beyond the court's jurisdiction for interim measures. Such a claim, he asserted, requires factual adjudication of accounts between partners, which is impermissible in a Section 9 proceeding.
Justice Kanth undertook a detailed analysis of the scope of Section 9, reaffirming its limited and ancillary nature. The court identified the central issue as whether a post-award claim for reimbursement can be entertained under this provision.
The judgment emphasized that the power under Section 9 is not for adjudicating new disputes but for preserving the status quo or ensuring the eventual award is not rendered a paper decree. The court observed:
> "The jurisdiction under Section 9 does not extend to the adjudication of fresh disputes, alteration of substantive rights, or granting of final reliefs that effectively amount to execution of the award."
The court found that the petitioners' claim was not an interim measure "in aid of" the existing award but a fresh claim requiring a factual determination of rights and obligations. Granting such a relief would amount to pre-judging matters that are intrinsically linked to the overall partnership accounts, which are the subject of the pending Section 34 proceedings.
The court also drew support from a prior order of a Division Bench in the same dispute, which had observed that issues of liability and reimbursement among partners should be adjudicated in the proceedings challenging the award itself.
Finding no grounds to entertain the petition, the High Court dismissed it. The court concluded that the claim for reimbursement of a post-award liability falls outside the limited scope of Section 9.
> "The prayer for reimbursement of Corporation Tax, being a post-award liability, falls outside the ambit of Section 9, which is confined to interim and protective measures and does not extend to the adjudication of substantive monetary claims."
However, the court granted liberty to the petitioners to raise their claims and contentions in the pending Section 34 proceedings, ensuring their grievance can be addressed in the appropriate legal forum.
#ArbitrationAct #Section9 #CalcuttaHighCourt
No Imminent Threat of Infringement Bars Ex-Parte Injunction in Trademark Suit: Belagavi Principal District Court
12 Feb 2026
Centre Justifies Wangchuk Detention as Ladakh Violence Halting Measure
12 Feb 2026
Court Rejects Selective Arbitration Under Section 21
12 Feb 2026
Family Judge Exposes Weaponized Litigation in Custody Dispute
14 Feb 2026
Centre Notifies Two High Court Chief Justice Appointments
16 Feb 2026
Deep Chandra Joshi Appointed Acting NCLT President
16 Feb 2026
Debunking the Myth That Indians Lack Privacy Concepts
16 Feb 2026
Whose View Is It Anyway? Juniors Uncredited
16 Feb 2026
Private Property Disputes Not Human Rights Violations; HRC Lacks Jurisdiction Under PHRA: Gujarat HC
16 Feb 2026
The classification of land as 'Rasta' falls under the definition of 'public premises' in the eviction statute, thus the eviction proceedings initiated against unauthorized occupants are legally valid....
The main legal point established is that the retrospective cancellation of GST registration must be based on objective criteria and cannot be done mechanically. The proper officer must consider the c....
Disobedience of court orders, abuse of political power, and refusal to vacate the premises can lead to contempt of court proceedings and enforcement actions by law enforcement authorities.
Financial companies must seek relief through legal channels when police seize pledged items under allegations of theft, ensuring adherence to established guidelines and protocols.
The rights of a pledgee over pledged gold are limited to those of the pledger, and ownership must be established through civil proceedings, necessitating guidelines for handling pledged stolen gold.
Right to exemption from personal appearance in trials for handicapped individuals was upheld by the court.
The disposal of seized property without notice and due process violates constitutional rights, rendering such actions illegal and unconstitutional.
The main legal principle established is the authority of the Tendering Authority to waive non-essential tender conditions and the requirement for rational decision-making in such matters.
The court allowed the withdrawal of the petition, emphasizing a procedural ruling in civil jurisdiction.
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.