By Tashi Meena , Law, Judgments & Legal Insights.
Add Tashi Meena on Google
Case Law
Subject : Civil Law - Municipal Law
Mumbai:
The Bombay High Court, in a strongly-worded judgment, dismissed a petition by Vikas Premises Co-operative Society Ltd., refusing to halt the demolition of the 129-year-old "
The Court held that procedural mechanisms like referring conflicting structural audit reports to the Technical Advisory Committee (TAC) cannot be invoked by a party that has shown gross negligence, suppressed facts, and allowed a building to become an imminent threat to human life.
The case revolved around '
The petitioner society, which owns the building, challenged these actions, arguing they were arbitrary and illegal.
Senior Advocate Mr. Aniruddh Joshi, representing the society, argued that the BMC’s actions were premature. He contended that the BMC had first issued a notice under Section 353B, giving the society 30 days to submit a structural audit report, but then proceeded with drastic measures before this period expired.
The petitioner’s primary plea was that there were two conflicting structural audit reports:
1. Mahimtura Consultants' Report: This report, initially obtained by the society in 2024, suggested the building was repairable. However, the same consultant later classified the building as C-1 in June 2025, stating it needed to be evacuated immediately. The society claimed this re-classification was done without its authority.
2. Vishwakarma Enterprises' Report: A new report commissioned by the society suggested that the building could be repaired with major structural strengthening.
Based on these conflicting views, the petitioner insisted that the matter be referred to the TAC, as per established procedure, before any demolition could take place.
Ms. K. H. Mastakar, appearing for the BMC, defended the corporation's swift action, citing the extreme urgency of the situation. She highlighted that a call from the Disaster Control Cell on June 20, 2025, reported that the building was "in a dangerous condition and likely to fall."
The BMC’s counsel pointed out that on-site inspections revealed "major vertical cracks" and that the society’s own consultant (Mahimtura) had confirmed that the society had failed to take any remedial action for over a year, leading to the structure's severe deterioration.
The High Court's decision turned on critical facts that the petitioner had suppressed in its petition, which came to light only after the court's probing.
The Bench discovered that the society was in possession of another report from
The judgment quoted:
"In our view, this amounts to material suppression, as the Petitioner had in its possession the report which showed that the building was infact C-1. It was incumbent upon the Petitioner to have specifically set this out and then, if at all, explained the same. The Petitioner having not done so, has clearly approached this Court with unclean hands. On this ground alone, the Petition must fail."
Furthermore, the Court found that the society's managing committee, despite being aware of the grave condition, had consciously decided in February 2025 not to carry out urgent beam and column repairs, citing a potential redevelopment plan that never materialized. The Court deemed this conduct "absolutely unconscionable" for putting "commercial considerations above issues of not only the safety of their own members but also the public at large."
Relying on its own suo motu PIL in the
"The very purpose of the TAC...was to reconcile conflicting structural audit reports. However, this mechanism was intended for situations where there was a genuine dispute...This procedure was not contemplated to aide those Societies which have done absolutely nothing to ensure that their premises are kept well maintained and don’t pose a risk...In any event, the safety of human life and property in the vicinity takes precedence over any so-called procedural lapses, even assuming such existed."
The High Court dismissed the writ petition, upholding the BMC's demolition notice. It imposed costs of ₹5,00,000 on the society, to be deposited with the Cancer Ward of KEM Hospital, Mumbai.
Refusing the petitioner's last-minute plea to allow members to remove their belongings, the Court stated that entry into the building would be at their own risk and that the society would be held liable for any untoward incident.
#BombayHighCourt #DilapidatedBuilding #PublicSafety
Kerala High Court Salutes R. Rajesh's Supreme Sacrifice, Urges Vigilance in Kochi Flood Prevention
08 Aug 2026
Supreme Court Backs Balanced Calcutta High Court Order on TMC Frozen Accounts in ED Probe
12 Aug 2026
Subsisting Contract Cannot Create Continuing Cause of Action for Time-Barred Debt: Supreme Court
13 Aug 2026
Supreme Court Records Centre's Assurance That Pre-2026 Transgender Identity Cards Stay Valid
17 Aug 2026
Allahabad High Court Grants Bail to Javed Akhtar in GST ITC Fraud Case, Citing Undue Delay
19 Aug 2026
SC Collegium Recommends Appointing Advocate, Judicial Officer to Gauhati High Court
19 Aug 2026
Supreme Court Rules Caste Abuse Inside Closed Room Not Public View Under SC/ST Act
21 Aug 2026
Bombay High Court Pulls Up BMC for Defying Assurance on Bandra Football Ground
21 Aug 2026
RPNLUP Denies Recruitment Irregularities, Files Police Complaint Amid State Law Department Inquiry
21 Aug 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.