Order 9 Rule 9 CPC and Section 5 Limitation Act
Subject : Civil Law - Procedural Law in Eviction Suits
In a ruling that underscores the principles of equity and procedural justice in civil litigation, the Rajasthan High Court has quashed a trial court order rejecting the restoration of an eviction suit dismissed due to an inadvertent error by the plaintiffs' counsel in noting the hearing date. The bench, comprising Justice Anoop Kumar Dhand, restored the suit filed way back in 1989, subject to the payment of costs and a unique directive to plant 25 shade trees in a public area. This decision in Smt. Rashidan v. Smt. Noorjahan (S.B. Civil Miscellaneous Appeal No. 4812/2019) emphasizes that a litigant should not bear the consequences of their lawyer's bona fide mistake, while also promoting environmental responsibility as part of judicial remedies. The case highlights ongoing challenges in long-pending civil disputes and the courts' role in balancing procedural rigor with substantive justice.
The appellants, represented by Smt. Rashidan (since deceased) and her adopted son Mohammed Shafiq, sought eviction and mesne profits from the respondents, a family of tenants including Smt. Noorjahan (also deceased) and her children. The trial court had dismissed the suit in default on October 25, 2010, after the plaintiffs missed the hearing due to a misnoted date. Despite filing a restoration application under Order 9 Rule 9 of the Code of Civil Procedure (CPC) with a plea for condonation of delay under Section 5 of the Limitation Act, the Additional District Judge No. 4, Jaipur Metropolitan, rejected it on technical grounds. The High Court's intervention not only revives the suit but also sets a precedent for handling clerical errors in protracted litigation.
The origins of this dispute trace back over three decades to 1989, when the appellants, residents of Chokri Topkhana Huzuri in Jaipur, initiated a suit for eviction and recovery of mesne profits against the respondents, who were tenants occupying the property. The plaintiffs alleged unlawful occupation and sought possession along with arrears. The relationship between the parties appears rooted in familial or community ties, given the shared locality in Jaipur's old city, near Ghatgate Bazar and Mohalla Ootwalan, but soured into a landlord-tenant conflict.
Following the filing of pleadings, the trial court framed issues on September 5, 1994, and the case progressed slowly toward evidence recording. On September 21, 2010, the suit was adjourned to October 25, 2010, for the plaintiffs' evidence. However, due to an error by counsel—who noted the date as November 25, 2010, in the diary—the plaintiffs failed to appear on the correct date. The trial court dismissed the suit in default that day. Unaware of the dismissal until later, the plaintiffs filed a restoration application under Order 9 Rule 9 CPC on November 29, 2010, accompanied by an application under Section 5 of the Limitation Act to condone a slight delay of about 25 days. They attributed the initial absence to the counsel's mistake and the delay in filing to personal exigencies, including being out of town for urgent domestic matters.
The trial court, in its order dated July 30, 2019, rejected the applications primarily on the grounds of unexplained delay, without delving into the merits of the restoration plea. This prompted the appellants to appeal to the Rajasthan High Court in 2019, arguing that the dismissal and rejection perpetuated an injustice in a case involving substantial questions of law and fact regarding tenancy rights and eviction under the Rajasthan Rent Control Act, 2001 (though not explicitly cited, implied in the context of eviction suits).
The timeline underscores the glacial pace of civil litigation in India: from filing in 1989 to High Court resolution in 2024 (noted as 2026 in the judgment, possibly a clerical error), spanning 35 years. This delay is emblematic of broader systemic issues, including adjournments and procedural lapses, which the High Court addressed by directing expeditious proceedings post-restoration.
The appellants' counsel, Mr. Mohammed Anees, mounted a robust defense centered on equity and procedural leniency. He detailed the inadvertent mistake: on September 21, 2010, the court had adjourned the matter to October 25, but the diary entry erroneously recorded November 25. This bona fide error by counsel, he argued, should not penalize the litigants, invoking the principle that courts must prioritize substantial justice over technicalities, especially in long-pending suits. The restoration application was filed within the 30-day limitation period under Article 122 of the Limitation Act, but a minor delay occurred due to the plaintiffs' absence from town for personal reasons, which was adequately explained in the Section 5 application.
Mr. Anees emphasized that the suit raised critical issues—eviction on grounds of default tenancy and mesne profits—that warranted adjudication on merits after evidence from both sides. He cited the absence of any prejudice to the respondents from the short delay and urged the court to set aside the impugned order, restoring the suit subject to costs to deter future lapses.
In opposition, counsel for the respondents, Mr. Samar Pratap Singh Naruka and Mr. Lokesh Tiwari (for Senior Advocate Mr. M.M. Ranjan), contended that the plaintiffs offered no cogent justification for their non-appearance on October 25, 2010. They argued that the restoration application was inherently delayed and lacked sufficient cause under Section 5, as the plaintiffs' explanation of being out of town was vague and unsubstantiated. The respondents maintained that the trial court correctly applied procedural rules to prevent abuse, noting that Order 9 Rule 9 CPC requires due diligence. They asserted no error in the dismissal and rejection, warning that condoning such lapses would encourage negligence. Furthermore, they highlighted the respondents' long occupation since the 1980s, portraying the plaintiffs' suit as an attempt to belatedly evict settled tenants without merit.
Both sides agreed on the factual backdrop but diverged sharply on the interpretation of "sufficient cause" for delay and the weight of counsel's error versus litigant responsibility. The appellants stressed humanitarian and equitable considerations, while the respondents prioritized strict adherence to timelines to maintain judicial efficiency.
Justice Anoop Kumar Dhand's reasoning rooted the decision in foundational civil procedure principles, particularly the interplay between Order 9 Rule 9 CPC—which allows restoration of suits dismissed for default upon showing good cause—and Section 5 of the Limitation Act, which permits condonation of delay if sufficient cause is demonstrated. The court found the trial judge's rejection overly technical, failing to appreciate the bona fide nature of the mistake. "The delay was not such which could be held to be fatal or prolonged. There was a slight delay, which has been satisfactorily explained by the plaintiffs," the judgment states, emphasizing that courts must avoid dismissing matters on hyper-technical grounds where no intentional neglect is evident.
The ruling draws implicit support from precedents like Salem Advocate Bar Association v. Union of India (2005), where the Supreme Court advocated liberal interpretation of CPC provisions to ensure access to justice, and N. Balakrishnan v. M. Krishnamurthy (1998), which held that delay condonation should consider the litigant's diligence rather than rigid timelines. Although not explicitly cited, these align with the High Court's view that a litigant's fate should not hinge on counsel's inadvertence, echoing Rafiq v. Munshilal (1981), where the Supreme Court ruled that parties engaging counsel are entitled to some leeway for professional errors.
Distinctions were made between willful default and excusable errors: here, the misnoting was inadvertent, not deliberate, and the delay (25 days) was minimal compared to the suit's 21-year pendency at dismissal. The court also invoked the public interest in adjudicating substantive rights, noting "important question of law and facts are involved in the suit with regard to eviction or non-eviction of the defendants."
Innovatively, the judgment integrates environmental jurisprudence by imposing tree-planting as a condition, justified as serving "the interest of public at large and for the greater public good." This draws from Article 48A and 51A(g) of the Constitution, promoting ecological balance, and aligns with recent judicial trends like in M.C. Mehta v. Union of India cases, where courts link remedies to sustainable development. The directive—planting 25 saplings with proof and an undertaking for maintenance—serves as compensatory and deterrent, without precedent in restoration contexts but enhancing the decision's societal impact.
News sources, such as reports from legal portals, corroborate this by quoting the court's stance: "a litigant cannot be made to suffer for an inadvertent mistake on part of his/her counsel," integrating seamlessly to highlight the ruling's broader resonance in procedural fairness.
The judgment yields several pivotal excerpts that illuminate the court's equitable approach:
On the counsel's error: "As per the case of the plaintiffs, the aforesaid mistake has occurred due to recording of a wrong date in the diary i.e. 25.11.2010 in place of 25.10.2010. Therefore, the aforesaid bonafide mistake has occurred on the part of the plaintiffs."
Regarding delay condonation: "In the considered opinion of this Court, the delay was not such which could be held to be fatal or prolonged. There was a slight delay, which has been satisfactorily explained by the plaintiffs and therefore, the trial Court has committed an error in rejecting the application submitted by the plaintiffs."
On merits adjudication: "Looking to the fact that important question of law and facts are involved in the suit with regard to eviction or non-eviction of the defendants and the same is liable to be decided on its merits by the trial Court, at the appropriate stage, after recording the evidence of both the sides."
Environmental directive: "The reasons for passing the present order directing the plaintiff to plant 25 saplings/plants is in the interest of public at large and for the greater public good. Planting trees is considered as an appropriate initiative as it will provide numerous benefits to the city and the surrounding community for decades and centuries."
Expeditious disposal: "It is expected from the trial Court to make all possible endeavours to proceed with the proceedings of the suit expeditiously, without entertaining unnecessarily requests of adjournments of either sides, looking to the fact that the suit was filed in the year 1989, i.e., more than 37 years back."
These observations, directly from Justice Dhand's order, underscore a holistic judicial philosophy blending procedural mercy with public welfare.
The Rajasthan High Court unequivocally set aside the trial court's July 30, 2019, order, allowing the restoration application under Order 9 Rule 9 CPC read with Section 5 of the Limitation Act. The suit was restored to its original number, with parties directed to appear before the trial court on February 16, 2026. To balance equities, the plaintiffs were ordered to pay Rs. 10,000 in costs to the defendants by that date and plant 25 shade tree saplings in a public vicinity, submitting photographic proof and an undertaking for their maintenance until maturity or suit disposal. Non-compliance would invite High Court intervention.
This decision carries profound implications for civil practice. It reinforces that clerical errors by counsel do not warrant draconian dismissals, potentially reducing the burden on appellate courts from technical rejections. In eviction suits, especially under rent control laws, it ensures long-pending matters reach merits-based resolution, protecting tenants from abrupt evictions while upholding landlords' rights. The tree-planting condition innovates judicial remedies, encouraging courts to incorporate environmental mandates in routine orders, which could inspire similar directives nationwide amid climate concerns.
For future cases, the ruling signals leniency in condoning short delays with plausible explanations, but stresses accountability through costs. It may influence how trial courts handle restoration pleas, urging deeper scrutiny of "sufficient cause" beyond form. In a system plagued by delays—India's civil cases average 3-5 years, but outliers like this span decades—this promotes efficiency, as evidenced by the directive for expeditious trial without undue adjournments. Overall, it advances substantive justice, reminding legal professionals that procedural rules serve, rather than obstruct, the quest for fair outcomes.
inadvertent mistake - restoration application - condonation of delay - default dismissal - bonafide mistake - tree planting directive - procedural equity
#SuitRestoration #CounselError
Vague 'Bad Work' Can't Presume Penetrative Sexual Assault Under POCSO Section 4 Without Evidence: Patna High Court
28 Apr 2026
Limiting Crop Damage Compensation to Specific Wild Animals Excluding Birds Violates Article 14: Bombay HC
28 Apr 2026
Appeal Limitation in 1991 Police Rules Yields to Uttarakhand Police Act 2007 on Inconsistency: Uttarakhand HC
28 Apr 2026
Nashik Court Reserves Verdict on Khan's TCS Bail Plea
29 Apr 2026
Delhi Court Grants Bail to I-PAC Director in PMLA Case
30 Apr 2026
No Historic Record of Saraswati Temple Demolition, Muslim Body Tells MP High Court in Bhojshala Dispute
30 Apr 2026
No Absolute Bar on Simultaneous Parole/Furlough for Co-Accused Under Delhi Prisons Rules: Delhi High Court
30 Apr 2026
Rejection of Jurisdiction Plea under Section 16 Arbitration Act Not Challengeable under Section 34 Till Final Award: Supreme Court
30 Apr 2026
'Living Separately' Under Section 13B HMA Means Cessation Of Marital Obligations, Regardless Of Residence: Patna High Court
30 Apr 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.