Case Law
Subject : Regulatory Law - Electricity Law
New Delhi
– In a significant ruling on tariff determination, the Central Electricity Regulatory Commission (CERC), presided over by Chairperson Shri
While the Commission approved the transmission tariff for eight of the eleven assets, it disallowed the claims for three specific assets involving upgrades, directing PGCIL to file for these costs under the truing-up process of their parent projects.
PGCIL filed Petition No. 9/TT/2023 seeking approval for the transmission tariff for eleven assets from their respective Commercial Operation Dates (COD) until March 31, 2024. The project, with an initial estimated cost of ₹35,883 lakh, aimed to strengthen the transmission network in the Eastern Region through various works, including the installation of new transformers (ICTs), reactors, and the re-conductoring of existing lines.
The respondents in the case were several state power distribution companies and electricity boards from the Eastern Region, who are the primary beneficiaries of the transmission system. Notably, none of the respondents filed a reply to the petition.
The central issue revolved around the classification of costs for three specific assets:
* Asset-III: Re-conductoring of the 220 kV New Purnea–Purnea transmission line.
* Asset-VII: Conversion of a fixed line reactor to a Switchable Line Reactor (SLR) at New Purnea.
* Asset-IX: Re-conductoring of the 400 kV Rangpo–New Siliguri transmission line.
PGCIL argued that these constituted new assets under the ERSS-XX scheme and sought a separate tariff. However, the CERC disagreed, establishing a crucial regulatory principle.
The Commission observed that these works involved upgrading or modifying existing infrastructure that had not yet completed its useful life. For instance, Asset-III involved stringing new High-Temperature Low-Sag (HTLS) conductors on existing towers.
In its order, the CERC stated, “We observe that the transmission assets covered in the instant Petition are not new transmission assets. Instead, they are re-conductoring and upgrading the already existing transmission assets, which are expenses in the nature of additional capitalization in the transmission assets, for which the tariff has already been approved.”
The Commission directed PGCIL to claim the capital costs for these three assets as ACE under their respective original project petitions (Petition Nos. 207/TT/2020, 327/TT/2019, and 465/TT/2020) during the truing-up process for the 2019-24 tariff period.
The judgment also addressed significant delays in the commissioning of several assets. The original Scheduled Commercial Operation Date (SCOD) for the project was May 1, 2020. While several assets were completed on or ahead of schedule, others faced substantial delays:
*
Asset-VIII:
*
Asset-X:
*
Asset-XI:
The Commission accepted the impact of COVID-19 and applied a blanket 5-month extension to the SCOD, as per a Ministry of Power directive. This condoned the delay for Asset-VIII. However, significant delays remained for Assets X and XI.
For Asset-XI, the CERC did not condone the delay of 506 days (post-extension), reasoning that the denial of shutdown by the grid operator is a planned activity and does not constitute a force majeure event under the regulations. For Asset-X, the Commission found the justification for the remaining 183-day delay insufficient and has deferred the final decision to the truing-up stage, directing PGCIL to provide further evidence.
Regarding cost, the CERC noted that while five individual assets exceeded their initial apportioned costs, the overall estimated completion cost of the project (₹33,806.64 lakh) remained within the Revised Cost Estimate (₹34,789.00 lakh). Therefore, the Commission concluded there was no cost overrun for the project as a whole.
The CERC approved the Annual Fixed Charges (AFC) for eight assets for the 2019-24 tariff period, with detailed calculations for depreciation, interest on loan, return on equity, and other components. The tariff for Assets III, VII, and IX was disallowed in the current petition.
This order reinforces the CERC's strict interpretation of capital expenditure rules, preventing utilities from claiming tariffs for upgraded components as new assets. It emphasizes that enhancements to existing infrastructure, unless constituting a completely new system, must be accounted for as additional capitalization within the framework of the original project's tariff structure.
#CERC #ElectricityTariff #PowerGrid
Madras HC Directs Municipality to Auction Amusement Rides Licenses on Vaigai Riverbed for Chithirai Festival: Madurai Bench
17 Apr 2026
TCS Nashik Accused Seek Bail in Harassment Probe
17 Apr 2026
Insurer Liable for Gratuitous Passenger in Goods Vehicle, Can Recover from Owner: Kerala High Court
17 Apr 2026
MP High Court Issues Notice in PIL Alleging Disrespect to National Song 'Vande Mataram' by Indore Councillors: Article 51A(a)
17 Apr 2026
Bombay HC Grants NSE Ad-Interim Relief Against Fake Social Media Accounts Infringing 'NSE' Trademark: Platforms Must Takedown in 36 Hours
18 Apr 2026
Supreme Court Tags Challenges to UP Gangsters Act with Similar Organised Crime Laws from Gujarat, Maharashtra: Refers to 3-Judge Bench
18 Apr 2026
Loan Repayments for Assets Can't Reduce Maintenance Under Section 144 BNSS: Supreme Court
18 Apr 2026
Fernandez Seeks to Turn Approver in ₹200 Cr PMLA Case
18 Apr 2026
Prosecution Can't Gatekeep Witnesses: Rajasthan HC Directs Summoning of Doctor Under Section 311 CrPC for Just Decision
18 Apr 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.