The has formally referred the long-running, multi-billion dollar dispute between and the concerning natural gas extraction in the Krishna-Godavari basin to . This significant judicial intervention follows the failure of both parties to reach a mutually acceptable settlement despite having been granted multiple by the court to negotiate a resolution out of court.
A three-judge bench, presided over by Chief Justice of India Surya Kant and including Justices Joymalya Bagchi and V. Mohana, has formally requested former Supreme Court judge Justice Ranjana Prakash Desai to oversee the process. The court, recognizing the technical complexity of the matter, has further instructed that the include the assistance of two domain experts to be suggested by the competing parties. The decision marks a pivot in the , shifting the responsibility for finding a resolution from the courtroom to a structured, independent framework.
"Both sides have requested adjournment from time to time to enable the parties to explore settlement. We are informed that they themselves have not been able to find out a viable solution,"
the bench noted in its order. By appointing a retired judge of the Supreme Court, the bench intends to facilitate a more nuanced, technically proficient negotiation process that can address the intersection of
and the
in managing national natural resources.
Navigating the Mandate The shift to represents a final attempt to resolve a conflict that has persisted for years, involving massive financial stakes. Attorney General for India and Senior Advocate , representing the opposing interests, confirmed to the bench that previous private discussions between the stakeholders had failed to yield a consensus. The appointment of Justice Ranjana Prakash Desai is aimed at bringing a high-level judicial perspective to the stalemate, while the addition of party-nominated experts ensures that the technical arguments regarding gas migration are properly scrutinized.
The process is expected to address the fundamental disagreement regarding the extraction rights of the parties, which has remained a point of significant friction. By leveraging the expertise of domain specialists, the court hopes to bypass the procedural gridlock that has characterized the case in appellate courts, moving instead toward a practical resolution that balances the economic interests of a major private enterprise with the state's responsibility as a custodian of natural wealth.
Genesis of the Reservoir Conflict The root of the dispute lies in allegations regarding the interconnectivity of natural gas reservoirs. The asserted that the gas reservoirs located in its block were interconnected with the adjoining block operated by . According to ONGC, this physical connectivity allowed natural gas that should have remained in the state-operated block to migrate into the privately held zone, where it was subsequently extracted.
To investigate these claims, the previously engaged the services of the independent firm to conduct a comprehensive study on the reservoir structure. Following the firm's findings that corroborated the possibility of gas migration between the blocks, the government established a committee chaired by former Supreme Court judge Justice A.P. Shah to examine the matter in detail. Based on the findings of this committee, the government issued a formal demand notice to seeking approximately USD 1.74 billion, including interest, for the gas claimed to have been extracted from the adjacent block.
The Path Through Arbitration and High Court initially contested the government’s demand through an arbitration process initiated under the governing its operations in the KG basin. The , operating by a majority, concluded that while certain were breached by the company, these violations did not rise to the level of a material breach that would justify the relief sought by the .
However, the litigation did not cease there. The challenged the majority award before the , arguing that the findings were fundamentally flawed. In , the High Court set aside the on the grounds of . A critical aspect of the High Court’s ruling was the emphasis on the state’s duty to protect natural resources. The court held that the government, as a trustee of public assets, could not be presumed to have implicitly consented to the extraction of migrated gas simply through its silence or failure to act earlier. The judgment underscored that natural resources are held in trust for the public and that their exploitation must strictly adhere to the established legal and contractual framework.
Moving Toward a Final Resolution The Supreme Court’s decision to mandate reflects a clear judicial preference for settling this technical and financial dispute through negotiation rather than protracted litigation. By steering the parties away from the of the High Court and the Supreme Court, the bench is providing a space where a commercial settlement can be explored without the rigid constraints of a purely legal verdict.
The success of this will hinge on the parties' willingness to integrate the findings of the expert committee—chaired by Justice A.P. Shah—with current economic realities. As the matter moves to Justice Ranjana Prakash Desai’s chamber, the immediate focus remains on the identification and appointment of the two domain experts who will provide the necessary technical clarity to guide the parties toward an outcome. This process represents the current, critical procedural stage in a saga that has defined the complexities of natural resource management in the corporate sector for over a decade. All parties are now expected to cooperate in establishing the structure of these negotiations, with the court monitoring progress as they work toward a final, binding resolution.
gas extraction rights - resource management policy - corporate arbitration - interstate resource disputes - mediation proceedings