Court Decision
2024-12-18
Subject: Energy Law - Electricity Regulation
In a significant ruling, the Appellate Tribunal for Electricity (ATE) has overturned a previous decision by the Maharashtra Electricity Regulatory Commission (MERC) that denied
The ATE analyzed the contractual provisions of the PPA and the implications of the MoD principles. It found that while MSEDCL argued that the scheduling was based on least-cost principles, the responsibility to provide a schedule lay with them. The Tribunal emphasized that MSEDCL's failure to schedule power corresponding to the minimum off-take guarantee directly led to
The Tribunal ruled in favor of
#EnergyLaw #ElectricityRegulation #PowerPurchaseAgreement
Whose View Is It Anyway? Juniors Uncredited
16 Feb 2026
Private Property Disputes Not Human Rights Violations; HRC Lacks Jurisdiction Under PHRA: Gujarat HC
16 Feb 2026
Supreme Court Rejects Stay on RTI Data Amendments
16 Feb 2026
DIFC Court: Strong Reasons Required to Block Arbitration
17 Feb 2026
Bar Leaders Oppose High Courts Saturday Sittings
17 Feb 2026
Platforms Defend Satire Against Ramdev's Personality Rights Injunction
17 Feb 2026
Kerala HC Orders Comprehensive Reforms in Sabarimala Prasadam Sales to Curb Systemic Misappropriation: Vigilance Probe Extended
19 Feb 2026
Delhi High Court Questions Jurisdiction in Nautiyal Personality Rights Suit
19 Feb 2026
Willful Non-Compliance with Court Orders Amounts to Disrespect: Rajasthan HC Summons Principal Secy, Medical Dept
19 Feb 2026
The court emphasized the need to consider certain electricity-related issues afresh based on relevant legal precedents.
Claim relating to unpaid fixed charges and underpaid variable charges – If there is any risk in supply, same has to be shared between generator and fuel supplier.
The main legal point established in the judgment is that the capacity declaration based on RLNG could be done unilaterally, unencumbered by the requirement of the appellant’s consent in the latter ha....
Power purchase agreements must be aligned with regulatory frameworks and cannot be enforced if unapproved, particularly regarding classifications impacting fixed charges.
(1) Appeal to Supreme Court – Requirement under Section 125 of Electricity Act, 2003 is not merely a ‘question of a law’ but a ‘substantial question of law’ – APTEL as an appellate body is to hear ap....
Tariff modifications in power purchase agreements must comply with regulatory approvals as per Section 86(1)(b) of the Act, ensuring valid determination of electricity purchase prices.
Court should be slow in interfering with decision taken by expert bodies.
The court upheld that coal supply from power generation must be allocated equitably among all electricity distribution companies, as mandated by regulatory guidelines, rejecting attempts to prioritiz....
The court determined that a mandamus was necessary to compel payment of the admitted sum of Rs.5.37 crores owed to the petitioner, reflecting the importance of timely financial compliance.
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.