Court Decision
Subject : Energy Law - Electricity Regulation
In a significant ruling, the Supreme Court addressed the appeals concerning the extension of the Scheduled Commissioning Date (SCD) under the force majeure clause of a Power Purchase Agreement (PPA). The case involved a solar power project in Karnataka, where the respondents, a special purpose vehicle and a solar power developer, faced delays attributed to various factors including government approvals and land conversion processes.
The appellants argued that the delays were due to the respondents' negligence in securing necessary approvals within the stipulated time frame. They contended that the force majeure clause should not apply as the respondents failed to provide timely notice of the claimed force majeure events. Conversely, the respondents maintained that the delays were beyond their control, citing bureaucratic inefficiencies and the government's acknowledgment of widespread issues faced by solar power developers.
The Supreme Court examined the findings of the Appellate Tribunal for Electricity (APTEL), which had previously ruled in favor of the respondents. The Court noted that the APTEL had considered the delays in obtaining land use conversion and evacuation approvals, which were not solely attributable to the respondents. The Court emphasized that the force majeure clause in the PPA was applicable, as the delays were due to factors beyond the respondents' control, including the time taken by government authorities to process necessary approvals.
The Court also highlighted that the appellant had previously granted a six-month extension, indicating recognition of the challenges faced by the respondents. This acknowledgment played a crucial role in the Court's decision to uphold the APTEL's findings.
Ultimately, the Supreme Court dismissed the appeals, affirming that the respondents were entitled to the benefits of the force majeure clause. The Court ruled that the commissioning of the project within the extended period negated the imposition of liquidated damages and the reduction of the tariff. This decision reinforces the importance of recognizing external factors affecting project timelines in the renewable energy sector.
#ElectricityLaw #ForceMajeure #SolarEnergy #SupremeCourtSupremeCourt
'Living Separately' Under Section 13B HMA Means Cessation Of Marital Obligations, Regardless Of Residence: Patna High Court
30 Apr 2026
Consolidated SCNs under Sections 73/74 CGST Act Permissible Across Multiple FYs: Karnataka HC
01 May 2026
Allahabad HC Stays NCLT Principal Bench Order Mandating Joint Scrutiny of Allahabad Bench Filings
01 May 2026
Bombay HC Grants Interim Protection from Arrest Despite Pending Anticipatory Bail in Lower Court Due to Accused's Marriage: Sections 351(2), 64(2)(m), 74 IPC
01 May 2026
Heavy Machinery Barred in Mining Leases Except Dredging: Uttarakhand HC Directs DM to Enforce Rule 29(17) of Minor Mineral Rules
01 May 2026
No Deemed Confirmation After Probation Without Written Order Under Model Standing Orders Clause 4A: Bombay High Court
01 May 2026
CJI Declares Sikkim India's First Paperless Judiciary
01 May 2026
CJI Declares Sikkim India's First Paperless State Judiciary
02 May 2026
Unsigned Employment Contract Can Determine Notional Income in Motor Claims: Bombay High Court
02 May 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.