SupremeToday Landscape Ad
Back
Next

Section 42 of Sale of Goods Act, 1930

Usage of Goods Post-Delivery Constitutes 'Deemed Acceptance' Under Section 42 of Sale of Goods Act: Bombay High Court - 2026-06-03

Subject : Civil Law - Contract Disputes

Listen Audio Icon Pause Audio Icon
Usage of Goods Post-Delivery Constitutes 'Deemed Acceptance' Under Section 42 of Sale of Goods Act: Bombay High Court

Supreme Today News Desk

Beyond the Point of No Return: Bombay HC Clarifies 'Deemed Acceptance' in Sales Contracts

In a significant ruling for commercial law, the Bombay High Court has reaffirmed that once a buyer integrates goods into a production process, they effectively lose the right to reject those goods under the Sale of Goods Act, 1930. The decision, delivered by Justice Sandeep V. Marne, highlights the stringent nature of "deemed acceptance" protocols in industrial supply chain contracts.

The Spark of Conflict: From Heat Exchangers to Arbitration

The dispute arose between Godrej and Boyce Manufacturing Company Limited (the Petitioner) and Remi Sales and Engineering Limited (the Respondent). The core contention centered on a supply order of 8,339 stainless steel tubes intended for high-temperature oil and gas refinery heat exchangers.

Shortly after the Petitioner integrated the tubes into their heat exchangers, they reported observing pitting, rusting, and discoloration. While the Respondent initially agreed to a cleaning and pickling process as a remedial measure, the Petitioner eventually attempted to reject the entire inventory, subsequently refusing to pay the outstanding invoice of nearly Rs. 4.47 crore. Following the invocation of the arbitration clause in 2017, the Arbitral Tribunal ruled largely in favor of the Respondent, leading to the current challenge under Section 34 of the Arbitration and Conciliation Act, 1996 .

The Legal Tug-of-War: Contract vs. Statute

The Petitioner argued that Clause 6(b) of their purchase order granted them the right to reject goods even after acceptance, essentially overriding the default provisions of Section 42 of the Sale of Goods Act. They asserted that because the goods were critical components for high-pressure environments, the "deemed acceptance" provisions should not apply until a comprehensive, exhaustive inspection was completed.

Conversely, the Respondent maintained that the Arbitral Tribunal correctly applied established statutory principles. They argued that the Petitioner's voluntary decision to use the tubes in the manufacturing process constituted a clear act of acceptance. Furthermore, they contended that the Petitioner failed to prove any material breach of specifications, noting that the tubes had passed multiple third-party inspections.

Judicial Analysis: The Boundaries of Acceptance

Justice Sandeep V. Marne, presiding over the High Court , scrutinized the interplay between the contract and the statutory framework. The Court held that the act of inserting the tubes into the heat exchangers was unequivocally "inconsistent with the ownership of the seller," thereby triggering the deeming fiction under Section 42.

The Court distinguished between a right to reject goods and a right to claim under warranty. Once the goods were used, the buyer’s rights shifted from rejection to compensation for breach of warranty—a claim the Petitioner had failed to substantiate with necessary evidence.

Key Observations

The High Court ’s ruling emphasized that contractual clauses cannot be read in a vacuum to defeat statutory frameworks. Notable reflections from the Bench included:

  • "Section 42 creates a deeming fiction where the goods are deemed to have been accepted when the buyer intimates to the seller that he has accepted them, or when... he does any act in relation to them which is inconsistent with the ownership of the seller."
  • "The act of buyer using or consuming the goods would certainly constitute acceptance of the goods by the buyer."
  • "The rusting/pitting/discoloration observed prior to cleaning was not a material defect since the same was cured by cleaning process with due approval of the Petitioner."
  • "If any defect is noticed in the consumed tubes, it would be a claim for warranty and not a right to reject the tubes."

Final Outcome and Industry Implications

The High Court ultimately dismissed the Arbitration Petition, upholding the Arbitral Award. The ruling reinforces a crucial principle for industry players: the timing of discovery matters. By waiting until after the integration of goods to initiate rejection, the Petitioner forfeited their contractual right to void the sale.

This decision serves as a cautionary tale for procurement and quality control departments. It underscores that unless explicit contractual mechanisms are precisely drafted to provide for post-installation rejection, industrial users must conduct rigorous quality assurance before the point of use, or risk being forced into expensive and complex warranty litigation rather than a clean rejection of defective materials.

deemed acceptance - sale of goods - contractual interpretation - arbitration award - manufacturing defects

#ContractLaw #Arbitration

logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top