The High Court of Judicature at Bombay has issued a significant interim ruling restraining the owners of the “Delana” property in Chembur, Mumbai, from obstructing an ongoing redevelopment project led by Bindu Raheja & Sons LLP . Justice Amit Borkar, presiding over the Commercial Division , determined that project owners cannot leverage correspondence with housing societies to stall redevelopment or force developers to renegotiate binding contractual terms once a registered Development Agreement is in force. The order serves as a crucial check on tactics intended to halt construction during the pendency of contractual disputes that are subject to arbitration .

The legal challenge arose following a series of disagreements between the developer and the property owners, Stephen Francis Coutts and seven others, regarding the specifics of the redevelopment plan for their Chembur property. Although a registered Development Agreement dated 29 November 2024 had been executed—specifying an entitlement of eight flats, each measuring 600 square feet, along with four parking spaces—the respondents later attempted to assert claims for larger properties and additional amenities. By November 2025 , the respondents began questioning the commercial understanding of the agreement, ultimately writing to the local housing society in December 2025 to request that all further permissions for the redevelopment be withheld.

This communication created a significant bottleneck, effectively preventing the developer from securing a final No Objection Certificate (NOC) necessary to progress to the next phase of construction. Despite a separate dispute with another occupant being resolved via consent terms in June 2026 , the respondents maintained their request to the housing society, leading the developer to approach the High Court under Section 9 of the Arbitration and Conciliation Act, 1996 . The developer contended that the ongoing obstruction threatened the viability of the project, highlighting an investment of over ₹15 crore and the progress already made in securing possession of several premises and settling claims with various residents.

In its defense, the respondents argued that the petition was premature, citing the absence of a formal notice under Section 21 of the Arbitration Act . They also contended that the developer had failed to demonstrate a genuine, immediate intent to move toward arbitration and suggested that the court’s intervention would amount to granting final relief at an interim stage. Justice Borkar rejected these preliminary objections, clarifying that a Section 9 petition for interim protection does not require a prior notice under Section 21. The Court emphasized that while an intent to arbitrate must be bona fide , the Act provides a window for developers to protect the subject matter of a dispute while transitioning into the formal arbitration process.

The Court’s decision was heavily influenced by Clause 85 of the Development Agreement , which explicitly stipulated that construction work should not be halted during arbitral proceedings unless the dispute concerned the title of the property. Justice Borkar held that arguments regarding the square footage of flats or the allocation of parking spaces did not constitute title disputes, thereby precluding the respondents from using such arguments to paralyze the construction process. The Court observed, “However, when a registered Development Agreement is in force and the parties have agreed to resolve their disputes through arbitration , one party cannot use correspondence with the Society merely to force the other party to accept fresh commercial terms.”

Addressing the respondents’ concern that the requested injunctions would grant the developer final relief prematurely, the Court distinguished between protective measures and substantive adjudication . It noted that requiring the respondents to cooperate and withdraw their obstructive communications was a limited, restorative measure necessary to prevent irreparable damage to the redevelopment project . Justice Borkar stated, “An order preventing obstruction, protecting the property and requiring the parties to act according to their existing Agreement does not, only because of that reason, finally decide the Petitioner's claim for specific performance .”

The Court ordered the respondents to withdraw their 17 December 2025 communication to the housing society within seven days to the extent that it sought to withhold permissions based on the disputed contractual claims. This order is specifically intended to clear the administrative path for the project to proceed without pre-empting the findings of a future arbitral tribunal. Furthermore, the developer was directed to issue a formal notice under Section 21 of the Arbitration and Conciliation Act within fourteen days to invoke the arbitration clause, ensuring that the matter is moved into the appropriate forum for a final decision.

Recognizing the delicate balance between the rights of the property owners and the developer’s obligations toward other occupants and stakeholders, the Court allowed the redevelopment to continue under strict judicial monitoring. The interim protection is set to remain in force for a period of ninety days, providing a clear timeline for the commencement of arbitration proceedings. Throughout the process, the housing society remains free to exercise its discretion in granting the final NOC, provided its decision remains in accordance with its internal rules and applicable laws.

During the pronouncement of the judgment, it was noted that the respondents had recently attempted to terminate the agreement. The Court clarified that this new development did not invalidate the current orders, noting that the petitioner remains free to pursue separate legal proceedings to challenge the termination or seek additional relief as necessary. By directing the parties to resolve their fundamental commercial grievances within the scope of an arbitral tribunal, the High Court has reaffirmed that registered development contracts must remain stable, preventing parties from using tactical delays as leverage to renegotiate terms mid-project.