holds MOU for TDR , quashes against developer
Justice Aarti Sathe of the set aside a trial court’s in a purchase dispute, ruling that a which is cannot be . The decision quashes the injunction that had restrained the developer from dealing with the TDR pending suit, sending the matter back for expedited disposal.
The TDR Deal That Fell Through
The dispute arose from an MOU dated between M/s Sada Anand Developers (the appellant) and Shree Balaji Realty (the respondent). The developer had proposed to sell 5,200 sq. mtrs. of TDR from a slum rehabilitation project on final plot no.57 at Mangalwar Peth, Pune, for a total consideration of ₹8.23 crore. The respondent paid ₹4 crore in instalments – ₹2.47 crore on and ₹1.48 crore on .
Under the MOU, the developer was to obtain a from the Competent Authority by . When technical difficulties prevented this, the developer issued a cancellation notice on , offering to refund the amount. The respondent refused the refund and instead filed Special Civil Suit No.387 of 2024 in , seeking of the MOU and a to prevent the developer from alienating the TDR.
The trial court granted the injunction on , citing the large sum paid and the risk of . The developer appealed.
Appellant: MOU Is Determinable, Barred
, appearing for the developer, argued that the trial court had failed to consider the true nature of the MOU. He contended that Clauses 4A and 4B of the MOU made it – the parties could cancel it ‘due to any reason whatsoever’ – and therefore was barred under . He relied on the decision in Narendra Hirawat and Company vs. Sholay Media Entertainment Pvt. Ltd. (2020(5)-Mh.L.J.-173), which held that a contract that is cannot be .
Kadam further submitted that the developer had issued post-dated cheques for the entire amount and given an irrevocable consent for their encashment. “The respondent’s refusal to accept the refund and insistence on is erroneous,” he argued.
Respondent: Right to Terminate Lies With Us
, for the respondent, maintained that Clause 4B gave the purchaser – and only the purchaser – the option to terminate the MOU. The developer’s was therefore invalid. He argued that the developer, having accepted ₹4 crore, was likely to create in the TDR once the DRC was obtained, causing to the respondent.
Court’s Analysis: Both Clauses Must Be Read Holistically
Justice Sathe reproduced Clauses 4A and 4B and observed that they cannot be read in isolation. “On a plain reading of the aforesaid clauses, it is clear that both the clauses have to be given a and cannot be read in isolation with each other.” Clause 4A stated that the agreement could be cancelled “due to any reason whatsoever or due to lapse of time period agreed herein to procure the proposed DRC.” In that event, the developer would issue security cheques. Clause 4B gave the purchaser the option to claim interest or terminate, but the overarching scheme was that the MOU was .
“Therefore, on a reading of the aforesaid two clauses, it is clear that the MOU is of such a nature that the same is determinable, inasmuch as, the same would be as the parties do not have to assign any reason to terminate the same and the terms of termination are envisaged in the contract itself.”
Once that finding was reached, the court held that Section 14(d) of the Specific Relief Act barred its . The trial court had erred by granting an injunction under without first deciding whether the MOU was enforceable.
Key Observations
The court made the following notable observations:
“The Trial Court has not rendered any finding in respect thereof and has proceeded to straight away grant injunction under the provisions of Order XXXIX, Rule 1 of CPC which to my mind is an incorrect approach adopted by the Trial Court.”
“Non granting of injunction in respect of the property which is not in existence, would not cause any harm or loss to the Respondent (Original Plaintiff) and therefore is in favour of the Appellant (Original Defendant).”
“In the facts of the present case, there is no existence of the property or a threat of dispossessing the Respondent (Original Plaintiff) from any property and hence question of exercising the jurisdiction under Order XXXIX, Rule 1 of CPC by the Trial Court without first giving its view on the issue of of the MOU dated 13th July 2022, is an incorrect approach adopted by the Trial Court.”
Decision: Injunction Quashed, Suit to Proceed Expeditiously
The High Court allowed the appeal, quashing the trial court’s order dated . It directed the to decide the suit as expeditiously as possible and in accordance with law. No costs were awarded.
The ruling reinforces the principle that an cannot protect a contract that is by its very nature determinable. Parties who agree to a termination clause that requires no reason will find their remedies limited to damages or refund, and not .