The Bombay High Court has established a firm threshold for granting interim protection under the Arbitration and Conciliation Act, 1996, ruling that the mere existence of a disputed monetary claim is insufficient to justify judicial intervention. In a recent order, the Court emphasized that a party seeking protection under Section 9 must demonstrate a "real risk" that a future arbitral award could become unenforceable without immediate judicial action, rather than simply relying on the existence of a debt.

The ruling follows a property dispute between homebuyer Hemlata Ajay Ramani and developer Alag Property Constructions Pvt. Ltd. The Court, presided over by Justice Amit Borkar, directed the developer to deposit ₹58,97,600 into a fixed deposit with a nationalized bank within four weeks. While the order ensures the potential security of the funds, the Court explicitly barred the release of this amount to the claimant at this preliminary stage, emphasizing that the underlying liability remains a matter to be adjudicated by the arbitral tribunal.

Developer Ordered to Secure Funds Pending Arbitration

The dispute originated from a flat purchase agreement signed on 31 March 2021, concerning a unit in the Alag Endeavour Project, which promised possession by 31 December 2025. Following the developer’s failure to meet the delivery timeline, the parties entered into a registered cancellation deed on 28 March 2026 to facilitate a full refund of the investment.

The developer issued a post-dated cheque for ₹58.97 lakh as part of this cancellation agreement; however, the instrument was dishonored on 1 July 2026 due to insufficient funds in the developer’s account. Subsequent to the dishonor, the parties entered into a legal impasse, with the purchaser asserting a claim for the refund and the developer challenging the underlying liability. During the proceedings, the claimant highlighted additional concerns regarding the developer’s business conduct, specifically pointing to the transfer of redevelopment rights regarding two housing societies under registered deeds dated 14 July 2026.

Justice Borkar addressed these concerns by examining whether the developer’s financial transactions suggested an intent to strip assets and defeat the claimant’s ability to recover funds in the future. The Court noted that while the transfers of redevelopment rights were undisputed, they were conducted for "lump-sum consideration." The bench concluded that these transfers, on their own, did not definitively establish an intention to frustrate the claimant’s recovery, as the consideration received from those deals could still remain available as corporate assets.

High Court Defines Threshold for Arbitral Interim Protection

In articulating the legal standard for Section 9 applications, the Court cautioned against the indiscriminate use of judicial power to secure money claims. Justice Borkar remarked: “The power under Section 9 cannot be used merely because there is some disputed claim for money. The party asking for protection has to show circumstances because of which such protection is necessary, so that the final arbitral award, if passed in its favour, does not become difficult to enforce.”

The Court maintained that while there is no "fixed formula" applicable to every case, the burden rests on the applicant to present material before the court that demonstrates a clear, tangible necessity for an interim measure. By focusing on the "real risk" of non-enforcement, the judiciary aims to balance the protection of creditors with the need to prevent the overuse of court machinery in purely commercial disputes that are already destined for arbitration.

This ruling underscores the judiciary’s reluctance to pre-determine the merits of a dispute before the arbitral tribunal has had the opportunity to weigh the evidence. The Court explicitly clarified that its order to deposit the money was a measure to secure the amount, not an endorsement of the validity of the debt. The developer remains fully entitled to contest its liability before the arbitrator, and the deposit serves as a protective layer rather than a premature payment.

Navigating the Intersection of Commercial Debt and Arbitration

The current situation highlights the complexities often faced by litigants in the real estate sector, where the failure to deliver a property often snowballs into disputes over refund instruments like cheques and settlement deeds. For legal practitioners, the decision serves as a reminder of the evidentiary burden required to move a court under the Arbitration and Conciliation Act. Rather than assuming that a dishonored cheque automatically warrants an interim freezing order or deposit, advocates must present evidence suggesting a pattern of financial distress or asset dissipation that places future enforcement in genuine jeopardy.

The Court’s decision to mandate the deposit without authorizing payment to the claimant reflects a cautious approach to interim relief. By placing the funds in a fixed deposit with a nationalized bank, the High Court has effectively neutralized the risk of the funds being dissipated while simultaneously preserving the developer's right to argue the case on its merits. This middle-ground approach ensures that the claimant is not left entirely vulnerable to the developer's financial maneuvers, while the developer is not subjected to a mandatory payout before the arbitration process has concluded.

As the matter proceeds to arbitration, the developer must now comply with the four-week window for the deposit. Failure to do so would likely invite further legal scrutiny, while the developer’s actions in the interim—particularly concerning its assets—will remain under the watchful eye of the parties involved. For now, the legal proceedings underscore the High Court's commitment to ensuring that Section 9 remains a tool for preventing the frustration of decrees, rather than a method for achieving premature debt recovery in contested arbitration disputes. Both parties are now expected to move forward with the arbitration process to determine the final liability regarding the cancellation deed and the associated financial obligations.