Cannot Justify Withholding Contractor Dues:
"
.
"
In a significant ruling reinforcing the rights of contractors dealing with government departments, the has directed the State to release ₹5 lakh to a contractor for work completed on a pontoon bridge, holding that cannot be used as a shield to indefinitely delay legitimate payments.
Background: A Bridge Built, Payment Pending
The petitioner, Jitendra Singh Tomar, had executed work relating to assembling, dismantling, erection, installation, and maintenance of a Pontoon Bridge at Atar Ghat, Sabalgarh, District Morena, pursuant to a work order issued by the State authorities. Despite completing the work and the competent authorities taking steps for payment, the of ₹5 lakh remained unpaid.
Tomar approached the High Court under , seeking a directing the respondents—the and its departments—to release the amount along with from the date of the 's order.
State's Defense: Budgetary Hurdles
The Government Advocate, appearing for the State, did not dispute the fact that Tomar had submitted his claim and that the department had acknowledged it. The reply filed by the respondents revealed that the Chief Engineer, , Gwalior, had directed payment of ₹5 lakh, and the Sub-Engineer had preferred a bill for ₹4,99,905 before the Executive Engineer, P.W.D. Division, Morena.
The State's stand was that the authorities had repeatedly requested allotment of funds, and vide letter dated , the Executive Engineer had again demanded payment in the prescribed form, but the requisite allotment was awaited.
Court's Ruling: Administrative Convenience Cannot Trump Entitlement
Justice Milind Ramesh Phadke, after hearing both sides, observed that from the reply, particularly paragraph 9, it was evident that the respondents themselves had demanded the requisite amount on towards payment of the petitioner's claim. The court categorically held that the respondents cannot on the ground of non-availability of , especially when the liability to make payment had already been acted upon by competent departmental authorities.
"It is well settled that a person who has completed the work entrusted to him cannot be deprived of the
due to him merely because the department has not made necessary
,"
the court stated.
Key Observations
The court emphasized that while the respondents stated that as soon as the amount is received under the relevant budget head, action would be taken, the petitioner had already been awaiting payment for a considerable period. The stand taken by the respondents, the court said,
"does not furnish sufficient justification for keeping the
unpaid any further."
The Decision: Payment Within Four Weeks with Interest
Disposing of the petition, the court directed the /respondents to release and pay the amount of ₹5 lakh to the petitioner within four weeks from the date of production of a certified copy of the order, without insisting upon any further representation from the petitioner.
Recognizing that the payment had remained outstanding for a considerable period, the court ordered that the amount shall carry from —the date on which the respondents themselves demanded the amount—till the date of actual payment.
The court made it clear that the concerned authority shall not defer compliance merely on the ground of non-availability of and shall take all necessary steps for arranging the requisite funds in accordance with law.