Calcutta High Court Quashes TMC Vacate Order Citing Lack of Fair Hearing

The Calcutta High Court has set aside a fire services evacuation order that directed the All India Trinamool Congress (TMC) to vacate its sixth and seventh floor offices on Camac Street in Kolkata, ruling that the authority passed the order without considering the party’s detailed reply and without carrying out a fresh inspection after the alleged fire safety deficiencies were said to have been remedied.

Justice Krishna Rao, hearing a writ petition filed by TMC, held that the order of September 4, 2026, issued by the Director-in-Charge of the West Bengal Fire and Emergency Services, was procedurally flawed and could not be sustained.

A Swift Evacuation Order Under Fire

The fire authority had issued a show-cause notice on September 1, 2026, alleging multiple violations: an expired fire safety certificate, a mild steel structure encroaching the driveway, LPG cylinders stored in a seventh-floor cafeteria, an inadequate and non-functional fire alarm system, and only one exit from the office to the internal corridor.

TMC submitted a detailed reply on September 3, stating that the encroaching structure had been removed, the LPG cylinders had been taken away, the riser system was operational (the butterfly valve had merely been kept non-operational during maintenance), and that there were in fact two exits. The party also listed the number of fire sprinklers and smoke detectors already installed and expressed full willingness to cooperate and install all required equipment.

Despite this, the very next day—September 4—the Director-in-Charge passed the impugned evacuation order. The order was not even served on TMC, but only on the building owner.

The State’s Maintainability Challenge

The Advocate General for West Bengal, Mr. Surojit Nath Mitra, argued that the writ petition was not maintainable because an appeal was available under Section 11-I of the West Bengal Fire Services Act, 1950, and Rule 24 of the 2003 Rules.

Justice Rao examined the statutory scheme and rejected the objection. He noted that the notice of hearing was issued under Section 37A of the Act, which falls under Chapter VI (Miscellaneous). Section 11-I provides an appeal only against orders passed under Chapter IIIA (Fire Prevention and Fire Safety), while Section 38 provides appeals against orders under Sections 35, 36, or 37—not Section 37A.

“Considering the above, this Court finds that neither Section 11-I nor Section 38 is applicable to the petitioner for preferring an appeal against the impugned order,” the court held, making the writ petition maintainable.

The Crucial Flaw: Reply Ignored, Inspection Skipped

On the merits, the court found a clear failure of natural justice. TMC had submitted its reply on September 3, but the impugned order passed the next day did not deal with any of the points raised.

“In the impugned order, the respondent no. 4 has not dealt with the reply submitted by the petitioner to the hearing notice dated 1st September, 2026,” the court observed.

Further, no inspection was conducted after the reply to verify whether the alleged defects had actually been cured. The court stated:

“This Court finds that the respondent no. 4 without considering the reply submitted by the petitioner and without carrying out any inspection after the reply submitted by the petitioner, has passed the impugned order.”

The court also noted that the order was not served on TMC, whose rights were directly affected. The building owner’s reply, submitted on September 4 at 16:32 hours, was filed only after the order had already been passed.

A Second Chance for Compliance

Emphasizing that TMC had expressed readiness to comply with all fire safety requirements, the court held that the authority ought to have granted time for compliance rather than rushing an evacuation.

The court set aside and quashed the September 4, 2026 order. It directed the Director-in-Charge to reconsider TMC’s September 3 reply, conduct a fresh inspection after issuing notice to the party, and if any further shortcomings are found, inform TMC to complete them. The court clarified that if TMC fails to comply even after such notice, the authority will be at liberty to take appropriate action in accordance with law.

The ruling is a straightforward application of natural justice: a hearing must be real, not a formality. The judgment does not hold that the premises are fire-safe—it only holds that the evacuation order was passed in a manner that violated the right to be heard. The authority retains full power to act if defects persist after a proper re-inspection.