Electricity Act 2003, Section 62 and 79(1)(a)
Subject : Energy and Electricity Law - Tariff Determination
In a landmark decision concerning the power sector's fuel supply chain, the Central Electricity Regulatory Commission (CERC) has finalized the determination of the input price of coal for NTPC Ltd.’s Pakri Barwadih Mine (West & East) for the tariff period 2019–2024. The ruling provides much-needed regulatory clarity for the state-run power giant while balancing the concerns of various state distribution companies (Discoms).
The Pakri Barwadih coal block, situated in Jharkhand’s Hazaribagh district, is a critical asset allocated to NTPC to fuel its various generating stations. Following the development of the mine under the Mine Developer and Operator (MDO) model, the mine reached its Commercial Operation Date (COD) on April 1, 2019.
NTPC approached the CERC seeking approval for the input price of coal supplied during the 2019–2024 period, citing significant challenges—ranging from the COVID-19 pandemic to local law-and-order issues—that had hampered its ability to meet production targets.
The proceeding became a battleground between NTPC and a large number of respondent Discoms, involving arguments over: * Time Overrun: NTPC argued that delays in reaching COD were due to land acquisition resistance and policy shifts in the State of Jharkhand. Discoms, however, alleged that these delays were due to a lack of proactive management by NTPC. * Production Shortfalls: NTPC sought relaxation of the Annual Target Quantity (ATQ) for the years 2020-21 and 2021-22, citing the pandemic and heavy rainfall. Discoms vehemently opposed this, arguing that mining was an "essential service" and that the Petitioner failed to meet production targets due to poor operational planning. * Infrastructure Cost Recovery: A major point of friction was the recovery of capital expenditure for the Coal Handling Plant (CHP). NTPC argued that because this fixed infrastructure was funded by the company (and not part of the MDO mining fee), the capital cost and associated O&M should be recovered through the input price.
The Respondents (including MSEDCL, TANGEDCO, and BSPHCL) argued that the input price claimed by NTPC was higher than Coal India Limited (CIL) notified prices. They contended that there was an "inordinate delay" in project execution and warned that passing on costs associated with operational inefficiencies—such as road transportation during the construction of the CHP—would unfairly burden electricity consumers.
NTPC rejoined by highlighting that the mine operates under "unique geo-mining conditions" with a high stripping ratio, making direct price comparisons with mature CIL mines fundamentally flawed and unfair.
The Commission, led by Chairperson Shri Jishnu Barua, recognized that the delays were largely "uncontrollable factors." The bench observed that the Petitioner had made sustained efforts to resolve land acquisition issues in collaboration with both State and Central authorities.
In its final order, the CERC ruled: 1. Delay Condonation: The delay in commencing production was condoned, accepting the Petitioner's detailed timeline and evidence regarding external roadblocks. 2. ATQ Relaxation: Invoking its power to relax, the Commission reduced the ATQ for FY 2020-21 by 15% and allowed the ATQ for FY 2021-22 at the level of actual dispatch, acknowledging the impact of the second wave of COVID-19 and atypical rainfall. 3. Cost Recovery: The Commission approved the input price calculation, allowing the recovery of capital expenditure for the CHP while noting that it was distinct from the MDO mining charges.
The judgment clarifies that while Discoms have a right to challenge costs, the Commission must adopt a "prudence check" approach that accounts for the harsh realities of mining operations.
> "The material on record indicates that the delay was not due to any inaction or negligence on the part of the Petitioner, but was largely attributable to external factors such as changes in the State R&R policy, delay in approval of the R&R plan... and law and order problems."
> "Having regard to the difficulties faced by the Petitioner on account of the Covid-19 pandemic as well as the law and order situation resulting in suspension of mining activities, we are of the view that the present case is fit for relaxation of ATQ."
> "Considering the fact that the expenditure for construction of CHP is in the scope of the Petitioner and it has put to use... we allow the claim... subject to truing up."
This ruling settles a complex, multi-party dispute and provides a structural framework for how integrated mines will be priced in competitive environments, setting a significant precedent for future power tariff filings.
View the social posts created for this story.
Input-Price - Mining-Charges - Tariff-Regulations - ATQ-Relaxation - Capital-Cost
#CERC #TariffDetermination
SC Notifies Over 7,300 Cases for Listing During Partial Working Days of 2026
24 May 2026
Religious Discrimination in Housing: A Silent Civil Crisis
24 May 2026
Senior Advocate Menaka Guruswamy Named to Corporate Panel
24 May 2026
Congress Leader Alka Lamba Convicted Under BNS Sections 132, 221, 223(a), 285 for 2024 Protest Violence: Rouse Avenue Court
26 May 2026
Supreme Court Grants Bail to Former Chhattisgarh Excise Commissioner in PMLA and Corruption Cases
26 May 2026
Regulating the Fiat-Crypto Gateway: A Critical Analysis
26 May 2026
Kerala High Court Adopts Calcutta Child Custody Guidelines
02 Jun 2026
High Court Upholds Acquittal in Murder Case Citing Tainted Investigation and Ante-Dated FIR
03 Jun 2026
Incorrect Statutory Provision in Bail Appeal Does Not Bar Substantive Rights: Punjab and Haryana HC Grants Bail in UAPA Case
03 Jun 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.