By Arun Nair , Legal Research & News.
Add Arun Nair on Google
Section 79 of the Electricity Act 2003
Subject : Civil Law - Energy and Electricity Law
In a significant ruling for the renewable energy sector, the
The petition, brought by
The developers argued that external factors, specifically changes in land allotment policy by the
ReNew argued that their transmission arrangement and PPA were parts of a single "composite transaction." They contended that when the PPA was frustrated, the transmission infrastructure requirements vanished, making the levy of charges by CTUIL arbitrary. They heavily relied on the
CTUIL, however, maintained a starkly different view. They argued that generation and transmission are distinct functions. The utility contended that developers are responsible for assessing and providing the start date for LTA, regardless of their progress on construction. For CTUIL, the PPA is simply a commercial contract to which they are not a party, and obligations under the BPTA (Bipartite Transmission Agreement) remain binding despite any internal operational setbacks faced by the generator.
The Commission observed that the LTA and PPA operate in entirely different spheres. CERC emphasized that the liability to pay transmission charges is a regulatory requirement rooted in the reservation of ISTS (Inter-State Transmission System) capacity, not a derivative of the success or failure of a specific PPA.
CERC also clarified that the
Ameet Lalchand Shah
judgment could not be extended to regulatory liability cases, as the facts in that case were limited to the arbitration of composite commercial transactions. Furthermore, CERC noted that the waiver of transmission charges, as per
The judgment is characterized by a strong emphasis on regulatory compliance and the independence of contractual obligations:
The CERC dismissed the Petitioners' pleas, solidifying the precedent that developers cannot use PPA termination to escape their transmission commitments. The Commission directed the recovery of transmission charges in accordance with the 2010 and 2020 Sharing Regulations depending on the applicable timeframes.
This decision serves as a firm reminder to renewable energy developers: the start date and capacity of LTA requested in applications represent binding commitments to the transmission utility. Companies must plan their infrastructure and operational timelines for transmission access as an independent financial risk, distinct from the potential termination or frustration of their power sales contracts.
View the social posts created for this story.
transmission charges - power purchase agreement - force majeure - long-term access - renewable energy - commissioning
#CERC #ElectricityAct
Ernst & Young Announces Applications for Senior Associate Role in Legal Practice
08 Aug 2026
Kerala High Court Salutes R. Rajesh's Supreme Sacrifice, Urges Vigilance in Kochi Flood Prevention
08 Aug 2026
Supreme Court Backs Balanced Calcutta High Court Order on TMC Frozen Accounts in ED Probe
12 Aug 2026
Subsisting Contract Cannot Create Continuing Cause of Action for Time-Barred Debt: Supreme Court
13 Aug 2026
Supreme Court Records Centre's Assurance That Pre-2026 Transgender Identity Cards Stay Valid
17 Aug 2026
Allahabad High Court Grants Bail to Javed Akhtar in GST ITC Fraud Case, Citing Undue Delay
19 Aug 2026
SC Collegium Recommends Appointing Advocate, Judicial Officer to Gauhati High Court
19 Aug 2026
Supreme Court Rules Caste Abuse Inside Closed Room Not Public View Under SC/ST Act
21 Aug 2026
Bombay High Court Pulls Up BMC for Defying Assurance on Bandra Football Ground
21 Aug 2026
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.