Chhattisgarh High Court Rules Defective Permit Application Cannot Be Cured After Consideration

In a significant ruling on permit applications under the Motor Vehicles Act, the Chhattisgarh High Court has held that once a statutory authority finds an application for a stage carriage permit to be incomplete and defective on the date of its consideration, the only legally permissible consequence is rejection—not an opportunity for the applicant to subsequently cure the defects.

A single bench of Justice Amitendra Kishore Prasad allowed a writ petition filed by Royal Travels, setting aside an order of the State Transport Appellate Tribunal (STAT) that had remanded the matter to the Regional Transport Authority (RTA) with liberty to rectify deficiencies. The Court directed STAT to freshly adjudicate the revision petition strictly on the basis of the record as it stood when the RTA originally considered the application.

The Dispute and Procedural History

Royal Travels, a stage carriage operator holding permits on the Durg-Trishuli route, objected to an application by respondent Mohd. Shahbuddin for a permanent stage carriage permit on the overlapping Odgi-Raipur route. The petitioner contended that Shahbuddin's application was incomplete and failed to meet mandatory statutory requirements. Despite these objections, the RTA, by order dated December 27, 2024, granted the permit.

Aggrieved, Royal Travels preferred a revision before STAT. The Tribunal recorded a categorical finding that the application was indeed incomplete and not in accordance with law, relying on the principle in Shailesh Vijayvargia v. State of M.P. that an incomplete application is liable to be rejected. However, instead of rejecting the application, STAT set aside the RTA’s order and remanded the matter back with a direction that Shahbuddin be allowed to cure the defects and have the application reconsidered afresh.

Arguments Before the High Court

Mr. B.L. Dembra, counsel for Royal Travels, argued that STAT’s order suffered from patent illegality. Once the Tribunal found the application incomplete, the only legal consequence was rejection. Allowing post-hearing rectification would enable the applicant to fill up lacunae, prejudicing competing operators who had objected based on the application as originally filed. He further submitted that the legality of an application must be tested on the date it is taken up for consideration, and rights crystallize on that date. Reliance was also placed on the Full Bench decision in Surendra Mohan Chaurasiya v. State Transport Appellate Tribunal , which holds that remand of permit matters to the RTA is ordinarily impermissible.

The State counsel and counsel for Shahbuddin opposed the petition, submitting that STAT had wide revisional powers under Section 90 of the Motor Vehicles Act, which includes the power to remand for fresh consideration. They argued that no prejudice was caused to the petitioner, as all objections remained open before the RTA. They also contended that the questions of timing conflicts and overlapping routes were factual matters best left to the transport authorities.

Court’s Legal Analysis

The High Court examined Sections 72, 80(2), and 90 of the Motor Vehicles Act, 1988, as well as Rule 70-B of the Chhattisgarh Motor Vehicles Rules, 1994, which govern the determination of timings and procedure for grant of permits.

The Court held that while the Act adopts a liberal approach toward grant of permits, the process must strictly comply with the prescribed procedure. The permit-granting authority is required to consider the application as presented, invite objections, and decide based on the material available on record.

Justice Prasad observed that STAT had recorded a categorical finding that the application was incomplete. Despite this, the Tribunal directed that the defects be cured and the matter reconsidered. “ In the considered opinion of this Court, the aforesaid course adopted by the Tribunal is legally unsustainable, ” the Court stated.

The Court emphasized that rights of the parties must be adjudged on the application as it existed on the date of consideration. “ Permitting an applicant to subsequently cure deficiencies after the matter has already undergone adjudication would amount to allowing such applicant to improve upon his case and fill up lacunae which existed on the relevant date, ” the judgment noted.

Further, the Court found that STAT had not rendered conclusive findings on issues such as the effect of the deficiencies, overlapping routes, and timing conflicts. Instead of adjudicating the revision on its merits, the Tribunal abdicated its jurisdiction by remanding the matter.

Key Observations

The Court made several powerful observations on the principles of fairness and transparency:

Such a course not only militates against the principles of fairness and transparency governing the grant of permits but also causes prejudice to competing operators who had raised objections with reference to the application in its original form.

The impugned direction virtually grants respondent No.3 a fresh opportunity to rectify deficiencies in the application, notwithstanding the Tribunal's own finding that the application was incomplete. Such an approach is inconsistent with the law governing consideration of permit applications and defeats the sanctity of the statutory procedure.

The Final Decision

The High Court allowed the writ petition and set aside the STAT order dated December 19, 2025. The matter was remanded to STAT for fresh adjudication of the revision petition on its own merits, strictly based on the material that was before the RTA at the time of original consideration. The Court directed that respondent Shahbuddin shall not be permitted to supplement, rectify, or fill up any alleged deficiency in the original application for the purpose of the revision proceedings.

The Tribunal was directed to independently examine all contentions, including the legal effect of the incompleteness of the application and the objections on overlapping routes and timings, without being influenced by its earlier order. The Court expressed no opinion on the merits and left all questions of fact and law open before the Tribunal, with a direction to decide the revision expeditiously, preferably within three months.

The ruling reinforces the principle that statutory procedures governing permit applications must be strictly adhered to, and applicants cannot be allowed to improve their case after the date of consideration at the expense of other stakeholders.