SupremeToday Landscape Ad
Back
Next

Section 34 and Section 37 of the Arbitration and Conciliation Act, 1996

Courts Cannot Act as Appellate Bodies or Modify Arbitral Awards: Delhi High Court in FAO 351/2010 - 2026-05-26

Subject : Civil Law - Arbitration Law

Listen Audio Icon Pause Audio Icon
Courts Cannot Act as Appellate Bodies or Modify Arbitral Awards: Delhi High Court in FAO 351/2010

Supreme Today News Desk

The 'Lakshman Rekha' of Arbitration: Delhi High Court Clarifies Judicial Limits

In a significant reinforcement of the finality of arbitration, the High Court of Delhi has reiterated that courts must not function as appellate authorities when reviewing arbitral awards. Presiding over M/S Brij Lal & Sons v. Union of India & Anr. , Hon'ble Mr. Justice Dharmesh Sharma dismissed an appeal against an arbitral award, underscoring that the judicial "corrective lens" is restricted strictly to the parameters set by the Arbitration and Conciliation Act, 1996.

A Long Road to Resolution

The dispute originated from a construction contract awarded to M/S Brij Lal & Sons by the Union of India for the construction of NACEN at Sector-29, Faridabad. While the project was initially scheduled for completion by October 1999, delays pushed the date to April 2000.

Following the completion of the work, the relationship between the contractor and the government soured over compensation for delays, material substitution, and requests for higher rates due to market fluctuations. After a convoluted process involving multiple arbitrator appointments, a final award was rendered in 2005. The appellant moved to challenge this award, claiming the arbitrator overlooked core evidence and failed to address substantive grievances regarding costs and interest.

Arguments from the Trenches

The appellant contended that the arbitrator erred in the assessment of claims, particularly regarding the use of 50mm tiles instead of 40mm and the refusal to grant damages for the delay, which the appellant blamed on the government. They further argued that the delay in the announcement of the award invalidated the proceedings.

In response, the Union of India maintained that the appellant was solely responsible for the project’s delay due to mismanagement of resources and procurement. They argued that the compensation levied under Clause 2 of the agreement was an "excepted matter," final and binding, and that the appellant’s claims were merely "afterthoughts" designed to prolong litigation after the final bill had been processed.

The Court’s Analysis: Drawing the Line

Justice Dharmesh Sharma’s analysis rested on the established legal principle that Section 34 of the Arbitration Act is neither an appellate nor a revisional remedy. The Court held that unless an award is in conflict with the public policy of India, or patently illegal, the judiciary has no authority to re-appraise evidence or second-guess the arbitrator's conclusions.

Drawing heavily on the Supreme Court’s mandate in NHAI v. M. Hakeem , the Court noted that including a power to modify or vary an award under Section 34 would be "crossing the Lakshman Rekha."

Key Observations

  • On the finality of the process: "The arbitrator is a Judge chosen by the parties and his decision is final. The Court is precluded from reappraising the evidence."
  • On the scope of intervention: "It suffices to indicate that the jurisdiction of the Court under Section 34 of the Act is neither in the nature of an appellate remedy nor is in the nature of a revisional remedy."
  • On the power of modification: "Quite obviously if one were to include the power to modify an award in Section 34, one would be crossing the Lakshman Rekha and doing what, according to the justice of a case, ought to be done."
  • On judicial restraint: "Courts under Section 34 are not granted the corrective lens and cannot re appreciate the decision on merits unless the conclusions drawn are patently perverse."

The Final Verdict: Implications for Future Disputes

The Delhi High Court’s decision serves as a stern reminder to litigants that challenging an arbitral award is not a mechanism for a "second bite at the cherry." By dismissing the appeal, the Court has reinforced that for arbitration to remain a viable alternative to traditional litigation, the finality of the arbitrator's decision—errors and all—must be respected unless the award shocks the conscience of the Court or borders on patent illegality. Parties entering into arbitration agreements must recognize that they are relinquishing their right to a full-blown judicial appeal in favor of a speedy, final resolution.

judicial review - arbitral award - contractual disputes - public policy - Section 34 - appellate jurisdiction

#ArbitrationLaw #DelhiHighCourt

logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top