Delhi High Court Orders NHPC To Pay 16 Crore To Hindustan Construction Co Ltd

The High Court of Delhi, led by Justice Subramonium Prasad, has delivered a significant ruling concerning the enforcement of arbitral awards in the construction sector. The Court held that interim payments released under the relief schemes of the National Institution for Transforming India (NITI Aayog) do not supersede the established legal principles for the appropriation of payments once an arbitral award attains finality.

Background of the Dispute

The conflict originated from a 2006 contract between Hindustan Construction Co. Ltd. (HCC) and the National Hydro Electric Power Corporation Ltd. (NHPC) for the execution of civil works at the Teesta Low Dam Hydroelectric Project, Stage IV. Following contractual disputes, an Arbitral Tribunal awarded HCC approximately ₹53.73 crore in 2015.

During the prolonged legal challenges against this award, the Government of India introduced specific Office Memorandums (OMs) in 2016. These measures aimed to ease the liquidity crunch for contractors by allowing Public Sector Undertakings to release 75% of awarded amounts against bank guarantees. HCC accepted these interim payments, which became the subject of contention when NHPC claimed that the acceptance of these funds constituted an agreement to deviate from standard interest-appropriation methods.

Legal Arguments and Judicial Analysis

HCC argued that payments should be adjusted first towards accrued interest and subsequently toward the principal amount, citing the precedent set by the Supreme Court of India in Leela Hotels Ltd. v. Housing & Urban Development Corporation Ltd.

Conversely, NHPC contended that the letters of acceptance provided by HCC during the implementation of the NITI Aayog scheme indicated an agreement to adjust payments differently, effectively arguing that the debt had been fully settled.

Justice Subramonium Prasad rejected the argument that administrative relief measures could override judicial mandates. The Court observed: “Once the Award has attained finality then the amount under the Award has to be paid in accordance with the law laid down by the Apex Court in Leela Hotels Ltd. (supra) in execution proceedings after adjusting the amounts already received under the OMs.”

Key Observations

  • "Once the Award has attained finality then the amount under the Award has to be paid in accordance with the law laid down by the Apex Court in Leela Hotels Ltd."
  • "The communications do not have any effect once the Award has been upheld."
  • "The correspondence entered into between the parties for the implementation of the OMs reproduced above is not part of the execution proceedings but only an interim measure."

Final Order and Implications

The High Court concluded that the correspondence regarding the interim relief scheme was merely a procedural mechanism to assist contractors during pendency and did not represent a waiver of their rights under the final award. Consequently, the Court allowed the application, directing NHPC to pay the outstanding balance of ₹16,39,87,708 to HCC within six weeks from the uploading of the judgment. This decision clarifies that administrative schemes intended for temporary financial support cannot be exploited to circumvent established legal rules governing debt appropriation in arbitration enforcement.