1997(7) Supreme 219
SUPREME COURT OF INDIA
(From Patna High Court)
S.B. Majmudar & M. Jagannadha Rao, JJ.
State of Bihar & Ors. -Appellants
versus
Hanuman Mal Jain -Respondent
Civil Appeal Nos. 4749-4750 of 1997
(Arising out of S.L.P (C) Nos. 17016-17017 of 1996)
Decided on 17.7.1997
Counsel for the Parties :
For the Appellants : S.B. Sanyal, Sr. Advocate and A.K. Jha, Advocate.
For the Respondent : T.C. Ray, Sr. Advocate, Bikas Kumar Gupta, and D.P. Mukherjee, Advocates.
Held : This objection on the face of it shows that according to the defendants the arbitrator had wrongly allowed the claims which were time barred as per Clause 11. Thus the objection was not on the ground of absence of jurisdiction of the arbitrator but on merits meaning thereby that the arbitrator wrongly held the claim to be within time. This obviously was in the domain of the jurisdiction of arbitrator and even if he had decided wrongly the question of limitation it could not be made a subject-matter of objection under Section 30 of the Act against a non-speaking award. Nor would it show any misconduct on his part. The Court obviously could not sit as a Court of Appeal against the decision rendered by the arbitrator on this ground. Much more so when the awards were non-speaking awards. (Para 7)
Further held that the claims have been adjudicated after going through all the documents and arguments by both the parties. Consequently it must be held that even though the learned Trial Judge as well as the High Court had not noticed the second proviso to Clause 11 of the Agreement both the parties had joined issue on the point before the arbitrator and the arbitrator having considered all the relevant contentions of the parties on this aspect had passed the impugned awards which even according to the defendants were passed on consideration of Clause 11 as a whole but only fault sought to be found by the defendants against the awards was that the arbitrator had wrongly treated the claims not be time barred. That question would squarely get connected with the second proviso to Clause 11 to which we have made a reference earlier and not dehors it. (Para 7)
(ii) Arbitration - Award -made rule of Court-Validity challenged on ground that award of interest by arbitrator was without jurisdiction as it was contrary to tender notice clause 2.32-Whether claim of interest was barred by clause 2.32?-Held, No-Neither Trial Judge nor High Court considered this issue-These being old claims, to avoid unnecessary protraction of litigation, controversy decided by this Court.
Held that it was the case of the plaintiff before the arbitrator that his claims were unreasonably delayed by the Executive Engineer before considering the same. It is this contention which is accepted by the arbitrator by passing the impugned awards though in a non-speaking manner. Therefore, it is not possible to agree with the contention of learned senior counsel for the appellants that the claim for interest was barred by clause 2.32 of the Tender Terms. If the contention of the plaintiff before the arbitrator was that his claims were unduly delayed they would obviously rule out the applicability of the said clause as that would not amount to unavoidable delay on the part of Executive Engineer in making the final payment. On the contrary it would be avoidable delay which would take out the claims from the fetters of Clause 2.32, even assuming that Shri Sanyal, learned senior counsel for the appellants is right in his submission that the said clause would cover all money claims pertaining to the amounts which may not be lying with the department and still would be within the sweep of the first part of the said clause. The defendants joined issue on the question whether any interest could have been awarded against the defendants by the arbitrator. Implicit in this contention would be the moot question whether there was any unavoidable delay on the part of the Executive Engineer in making the final payment which according to the plaintiff fell short of his claim and it is this contention which, as noted by the arbitrator in the Minutes was pressed for consideration of the arbitrator. He ultimately came to his own conclusion regarding the same by rejecting this contention on merits by non-speaking awards. It is, therefore, not possible to agree with the learned senior counsel for the appellants that applicability of Clause 2.32 of the terms of tender was not kept in view by the arbitrator and consequently his awards suffered from any patent error of law. We have to undertake this exercise on the facts of the present cases as neither the learned Trial Judge nor the High Court had come to the grip of this issue and in order to avoid unnecessary protraction of litigation we thought it fit, as noted earlier, after hearing the parties to decide this controversy. (Para 10)
JUDGMENT
S.B. Majmudar. J.- Leave granted in both these Special Leave Petitions.
2. By consent of learned advocates of parties the appeals were heard finally and are being disposed of by this common judgment. The appellants in both these appeals are State of Bihar and its officers in Rural Engineering Organisation. Respondent in both these appeals is also one and the same contractor. The appeals is also one and the same contractor. The grievance raised by the appellants centers round the orders passed by learned Subordinate Judge, Chaibasa, making awards rules of the Court in two Title Suits filed by the respondent against the appellants. These orders of the learned Subordinate Judge in turn were confirmed by the High Court of Patna in appeal moved by the appellants and that is how the appellants are before us in these proceedings. We shall refer to the respondent as plaintiff and the appellants as defendants in latter part of this judgment.
3. The plaintiff filed two Title Suits for recovering money dues from the defendants, in the Court of the Subordinate Judge, Chaibasa. His contention was that while carrying out contract work entrusted to him by the defendants he had incurred expenditure over various extra items which were not paid for by the authorities concerned. He also raised certain ancillary claims against the defendants seeking money decrees against the defendants in both these suits.
4. The defendants resisted the suits on diverse grounds. After hearing the parties the Trial Court appointed the Superintending Engineer, Rural Engineering Organisation, Works Circle, Ranchi as the sole arbitrator to adjudicate upon the disputes raised in the suits. It was subsequently found that before the arbitrator could finish the arbitration proceedings his office fell vacant due to retirement. Consequently the plaintiff moved another application under the Arbitration Act, 1940 (hereinafter referred to as the Act ) for appointment of a fresh arbitrator. The appellant-defendants agreed to the name of one Shri T. Ghosh, retired Chief Engineer to act as sole arbitrator and that is how the disputes between the parties in both these suits were referred to the said arbitrator who after hearing the parties gave his award on 6th July 1992 for a sum of Rs. 3,99,400/- in favour of the plaintiff in Title Suit No. 7 of 1988 with 18 interest. He passed another award dated 7th July 1992 for a sum of Rs. 2,38,200/- along with interest and cost in favour of the respondent-plaintiff in Title Suit No. 8 of 1988. The plaintiff moved applications under Section 20 of the Act in both the suits for making the awards rules of the Court. The defendants filed objections to these awards under Section 30 of the Act. The learned Subordinate Judge, Chaibasa, after hearing the parties overruled the objections of the defendants and decreed both the suits in terms of the arbitration awards. As noted earlier the appellant-defendants aggrieved by both these awards decrees approached the High Court of Patna at Ranchi in appeal. The High Court dismissed the appeal and confirmed the arbitration awards.
5. Learned senior counsel Shri Sanyal in support of these appeals placed before us two contentions for our consideration :
1. The awards which were made rules of the Court suffered from patent error of law on the ground that Clause 11 of the Agreement between the parties was not complied with by the plaintiff and hence both the awards were barred by limitation as per the second proviso to the said Clause and both the Subordinate Court as well as the High Court had patently erred in relying upon Clause 11 dehors the second proviso while confirming the awards.
2. The award of interest by the arbitrator was patently erroneous and without jurisdiction as it was contrary to the tender notice Clause 2.32 which prohibited grant of such interest on the disputed amounts. Initially when these Special Leave Petitions reached admission hearing bef
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.