SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1999 Supreme(SC) 145

1999(1) Supreme 344
Supreme Court of India
(From Madhya Pradesh High Court)
Mrs. Sujata V. Manohar & R.C. Lahoti, JJ.
M/s. M.K. Shah Engineers & Contractors etc. -Appellants
versus
State of Madhya Pradesh -Respondent
Civil Appeal No. 5961 of 1983
with
Civil Appeal No. 5962 of 1983
Decided on 5-2-1999
Counsel for the Parties :
For the Party-in-person : M.K. Shah, Advocate.
For the Respondents in C.A. No. 5961-62/83 : A.K. Chitale, Sr. Advo­cate, (Sakesh Kumar) Advocate for S.K. Agno­hotri, Advocate.
For the Appellant in C.A. No. 5962/83 : G.L. Sanghi, Sr. Advocate (Aseem Meh­rotra) Advocate for S.K. Gambhir, Advocate.

Important Point
Where agreement provides for taking certain steps preceding the coming into force of the arbitration clause, though such steps are essential if one party has by its own conduct or the conduct of its officials disabled such preceding steps being taken, it will be deemed that the procedural pre-requisites were waived. The party at fault cannot be permitted to set up the bar of non-performance of pre-requisite obligation so as to exclude the applica­bility and operation of the arbitration clause.

Headnote:Arbitration Act, 1940-Sections 16 and 30-Arbitration proceedings-Validity of-Agreement providing for reference of dispute to Superintending Engineer first-Aggrieved party could seek arbitra­tion thereafter within time stipulated in contract-Appellant’s dis­pute not decided by Superintending Engineer-At request of appellant Government appointing sole arbitrator - Subsequent objection before arbitrator by Government that disputes not arbitrable as they were not processed by Superintending Engineer-Proceed­ing u/s 33 initiated but got dismissed as infructuous on death of arbitrator - Subsequent appointment of arbitrator by Court u/s 8(2) -Government submitting to arbitration - Award challenged on ground condition precedent to arbitration of disputes i.e. processing of dispute first by Superintending Engineer not complied with and there­fore award not sustainable-Lower Court and High Court upholding plea-Whether correct?-No-Steps preceding operation of arbitration clause essential are capable of being waived-Conduct of Government amounts to waiver-Having acquiesced Govt. cannot turn around and plead invalidity of arbitration proceedings.

       Held : The Superintending Engineer unreasonably delayed the decision and in spite of persuasion and protests by the contractor, did not promptly take and communicate his decision on the disputes. The State Govern­ment ultimately yielded to the demand of the contractor by appointing an arbitrator. Once the arbitrator commenced the arbitration proceed­ings, the State of M.P. gave a second thought and receded its steps by choosing to raise an objection to the maintainability of the arbitration. The arbitrator allowed time to the Government of Madhya Pradesh for securing a judicial pronouncement on its objection under Section 33 of the Act. The State of M.P. initiated proceedings under Section 33 of the Act, but did not pursue the same. Rather it agreed to the appointment of a new arbitrator in place of the previous one. (Para 15)

       No one can be permitted to take advantage of one’s own wrong. The respondent-State of M.P. cannot and could not have been heard to plead denial of the two appellants’ right to seek reference to arbitration for non-compliance with the earlier part of clause 3.3.29. In this case of M/s. Chabaldas & Sons, the clause was complied with. Alterna­tively, even if it was not complied with in the case of M/s. Chabaldas & Sons but certainly in the case of M/s. M.K. Shaw, the fault for non-compliance lies with the respondent-State of M.P. through its offi­cials. The plea of bar, if any, created by the earlier part of Clause 3.3.29 cannot be permitted to be set up by a party which itself has been responsible for frustrating the operation thereof. It will be travesty of justice if the appellants for the fault of the respondents are denied right to have recourse to the remedy of arbitration. A closer scrutiny of Clause 3.3.29 clearly suggests that the parties intended to enter into an arbitration agreement for deciding all questions and disputes arising between them through arbitration and thereby excluding the jurisdiction of ordinary civil courts. Such reference to arbitration is required to be preceded by a decision of the Superintending Engineer and a challenge to such decision within 28 days by the party feeling aggrieved therewith. The steps preceding the coming into operation of the arbitration clause though essential are capable of being waived and if one party has by its own conduct or the conduct of its officials disabled such preceding steps being taken, it will be deemed that the procedural pre-requisites were waived. The party at fault cannot be permitted to set up the bar of non-performance of pre-requisite obligation so as to exclude the applica­bility and operation of the arbitration clause. (Para 17)

       The subsequent conduct of the respondents in voluntarily agreeing to the appointment of the arbitrators in both the cases and not pursuing their objections under Section 33 of the Arbitration Act amounts to waiver on their part of the plea of non-compliance with the earlier part of clause 3.3.29, if only there was such non-compliance. The respondent-State of M.P. has acquiesced in the appointment of arbitrators and the proceedings for settlement of disputes by arbitration. The respondent cannot be permitted to turn around and plead invalidity or non-maintainability of arbitration proceedings by reference to clause 3.3.29. (Para 18)

       For the foregoing reasons, we are of the opinion that the trial Court and the High Court were not justified in setting aside the awards and remitting them back for decision afresh by the arbitrator on the ground of non-compliance with the earlier part of clause 3.3.29. The award except to the extent to which it allows interest, was not liable to be interfered with by the Court. (Para 19)

       Held, consequently both the appeals are allowed. The impugned judgments of the High Court and the trial Court-both are set aside in both the appeals. Instead it is directed that both the awards dated 26.9.1978 shall be made rule of the court subject to the modification that the contrac­tor-claimants shall not be entitled to interest up to the date of the reference. (Para 22)

       (ii) Arbitration Act, 1940-Time limit to invoke arbitration clause-When get relaxed.

       Held : The arbitration agreements may contain a clause which requires a certain act to be completed within a specified period and which provides that if that act is not done either the claim or the ability to commence an arbi­tration will be barred. Such clauses are sometimes known as ‘Atlantic Shipping’ clauses. The consequences of the expiry of a contractual limitation period before the completion of the specific act may howev­er be avoided in three circumstances : (i) if the Court exercises its discretion statutorily conferred on it, to extend the period to avoid undue hardship; (ii) if the arbitration clause confers a discretion on the arbitrator to extend the period and he exercises it; (iii) if the conduct of the either party precludes his relying on the time bar against the claimant. (Para 14)

       (iii) Arbitration Act, 1940-Arbitrator-Scope of power-Power to award pendente lite interest. (Paras 21 & 21.1)

       

Judgment

R.C. Lahoti, J.-These two civil appeals have been preferred by two contractors feeling aggrieved by the orders of trial Court upholding the objections preferred by the respondent-State under Sections 16 and 30 of the Arbitration Act, 1940 and setting aside the awards given by the Arbitrator which orders have been maintained in revision by the High Court of Madhya Pradesh. The facts of the two cases are similar and the questions of law arising for decision are common. The two appeals have been heard analogously and are being disposed of by this common order.

2. The disputes relating to the two contracts are referable to con­struction of Barna Main Dam across River Barna, a tributary of Narmada near Bhopal. The entire work was divided into five groups namely 1 to 5. The main dam came under groups 1 and 2 consisting of blocks 1 to 23. Contract for construction of group No. 1 consisting of block numbers 1 to 10 was given to M/s. M.K. Shah, Engineers and Contrac­tors, the appellant in Civil Appeal No. 5961 of 1983. Contract for construction of group No. 2 consisting of block numbers 11 to 23 was entered into with M/s. Chabaldas & Sons, Contractors. It appears that both the contractors could not complete the work assigned to them and disputes arose between them and the respondent-State. The contracts were terminated in between and the remaining parts of the work were got executed through other agencies.

3. The contracts entered into with the two contractors by the respond­ent-State of MP have an arbitration clause around which centers the controversy arising for decision in the two appeals. The same is extracted and reproduced hereunder.

3.3.29 : Decision of Superintending Engineer to be final except where otherwise specified in the contract.

“The decision of the Superintending Engineer of the Circle for the time being in respect of all questions and disputes relating to the meaning of the specifications designs drawing and, instructions here-in-before mentioned and as to the quality of workman ship or material used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications estimates, instructions orders or those conditions or otherwise concerning the work of execution or failure to execute the same, whether arising during the progress of the work or after the completion or abandonment thereof, shall be final.

Provided that if any party to the contract is dissatisfied with the final decision of the Superintending Engineer, in respect of any matter, he may within 28 days after receiving the notice of such decision give notice in writing to the Superin­tending Engineer, re­quiring that the matter may be referred to arbitrator and furnishing detailed particulars of the dispute or difference and specifying clearly the point at issue. If any party fails to give such notice within 28 days as stipulated above, the decision of the Superintending Engineer, already given shall be conclusive, final and binding on the parties.

In case an arbitration is to be held it shall be effected by an arbi­trator to be appointed by the State Government out of panel of three names suggested by the State Government to the contractor, who shall give concurrence within a period of one month from the date of the communication. In case the contractor does not communicate the concur­rence, the State Government shall appoint an arbitrator whose decision shall be conclusive final and binding on the parties.

If the work under the contract has not been completed when a dispute is referred to arbitrator work shall continue during the arbitration proceedings if it is reasonably possible and no payment due to con­tractor should be withheld on account of arbitration proceedings unless it is required by the arbitrator.”

4. Hereafter the facts of the two cases have a little different narra­tion and hence are stated separately.

5. C.A. No. 5961/83: M/s. M.K. Shah s

















































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top