SUPREME COURT OF INDIA
31st January, 1961
J.L. KAPUR, HIDAYATULLAH AND J.C. SHAH, JJ.
Mahabir Prasad Rungta (in both the appeals), Appellant
Versus
Durga Datta (in both the appeals), Respondent.
Civil Appeals Nos. 54 and 55 of 1957.
Advocates appeared
Mr. B. C. Misra, Advocate, for Appellant (in both the Appeals); Mr. Tarachand Brijmohan Lal, Advocate, for Respondent (in both the Appeals.)
CONTRACT - BREACH - PAYMENT OF BILLS - ROAD REPAIR - RESCISSION OF CONTRACT - INTEREST - AWARD OF INTEREST - RATE OF INTEREST.
Fact of the Case:
Rungta and Durga Datt entered into an agreement for the transportation of coal from Rungta's colliery to the railway station. Rungta alleged that Durga Datt breached the contract by stopping work in July 1951, while Durga Datt claimed that Rungta had breached the agreement, leading to the work stoppage. Both parties filed suits for damages.
Finding of the Court:
The Judicial Commissioner found that Rungta was responsible for the breach of contract due to withholding payments to Durga Datt and failing to keep the road in repair, dismissing Rungta's suit and awarding damages to Durga Datt.
Issues: 1. Who was responsible for the breach of contract? 2. Whether Rungta was justified in withholding payments to Durga Datt? 3. Whether Rungta was responsible for the poor state of the road? 4. Whether Durga Datt was entitled to rescind the contract? 5. Whether interest should be awarded and at what rate?
Ratio Decidendi: 1. The court held that Rungta was responsible for the breach of contract as he had withheld payments to Durga Datt and failed to keep the road in repair, in breach of the agreement. 2. The court found that Rungta was not justified in withholding payments to Durga Datt as the presentation of bills was not a condition precedent to payment and Rungta had withheld substantial amounts over a long period without any reasonable cause. 3. The court found that Rungta was responsible for the poor state of the road as he was required to keep the road in repair under the agreement. 4. The court held that Durga Datt was entitled to rescind the contract as Rungta had breached a very important condition of the agreement. 5. The court held that interest up to the date of suit was not claimable as there was no agreement, usage of trade, statutory provision, or notice specifying the sum demanded. However, interest pendente lite was within the court's discretion, and the rate of 6% was reduced to 4%.
Final Decision: The court dismissed Rungta's appeals, except for reducing the amount decreed by Rs. 3,750, disallowing interest up to the date of the suit, and reducing the rate of interest pendente lite from 6% to 4%. Rungta was ordered to pay the costs in the Supreme Court.
Certainly. Based on the provided legal document, here are the key points summarized:
The case involves a dispute over a contract for transportation of coal, where one party (Rungta) alleged breach by the other (Durga Datt), who in turn claimed breach by Rungta (!) (!) .
The court found that Rungta was responsible for the breach due to withholding payments and failing to keep the road in repair, which were breaches of important contractual conditions (!) (!) .
Rungta's argument that the presentation of bills was not a condition precedent to payment was rejected; the court held that Rungta had unreasonably withheld substantial payments over a long period, which justified Datt's rescission of the contract (!) (!) .
The court determined that the breach by Rungta was significant enough to justify rescission under the relevant contractual law provisions, specifically Section 55 of the Indian Contract Act (!) (!) .
Regarding the amount owed for transportation, the court adjusted the claimed amount, acknowledging that the estimate of coal transported was approximate, and reduced the payment claim accordingly (!) (!) .
The issue of interest was addressed, with the court ruling that interest prior to the filing of the suit was not claimable due to lack of agreement or statutory basis, and that interest pendente lite should be reduced from 6% to 4% (!) (!) .
The court dismissed Rungta's appeals in most respects, except for the reduction of the amount decreed by a specified sum, the disallowance of pre-suit interest, and the lowering of the interest rate during the pendency of the suit (!) (!) .
The final decision included an order for Rungta to pay costs, with detailed modifications to the original decree based on the findings (!) (!) .
Please let me know if you need further analysis or specific advice based on this case.
Judgment
HIDAYATULLAH, J. : Mahabir Prasad Rungta, appellant in these two appeals, was plaintiff in his own suit and defendant in a counter suit filed by Durga Datt, the respondent. The two appeals have been filed on certificates granted by the Judicial Commissioner, Vindhya Pradesh against a common judgment and decree of the Judicial Commissioner s Court in four appeals filed by the rival parties, two in each civil suit. Certificate was also granted to the respondent; but he did not take steps in that behalf, and we are, therefore, concerned only with the appeals of Mahabir Prasad Rungta.
2. The two suits were filed in the following circumstances : Rungta owns a colliery at Budhar in Madhya Pradesh. On October 30, 1950, an agreement was executed between Rungta and the respondent, Durga Datt. Durga Datt agreed to transport coal from the colliery to the railway station at the rate of Rs. 2-8-0 per ton for a period of two years commencing from November 11, 1950 to November 10, 1952. That agreement is Ex. P-1. The case of Rungta was that Durga Datt broke the contract from July 29, 1951, by stopping the work of transport. Durga Datt in his suit, on the other hand, averred that Rungta had broken the agreement and work of carriage as a result was stopped from July 30, 1951. The difference of a day between them is of no consequence. Rungta s case was that as a result of the breach of the contract on the part of Durga Datt, he was required to employ other carriers and to pay them at Rs. 3 per ton, and he incurred demurrage and damages to his constituents for delay in supplies. He, therefore, claimed a sum of Rs. 60,000 as damages, including Rs. 20,000 as general damages for loss of business, credit and reputation. He admitted that a sum of Rs. 15,087-5-0 was owed by him to Durga Datt on account of coal carried by the latter, and he thus claimed Rs. 44,912-11-0, after allowing credit for that sum.
3. Durga Datt, in his suit, asked for a decree for Rs. 49,544-12-0. This included Rs. 26,139-11-0 on account of arrears of bills and Rs. 905-1-0 as interest on the amount The balance (Rs. 22,500) was claimed as damages for loss of business and profits of the unexpired period of the contract at Rs. 1,500 per month. In giving the particulars for Rs. 26,139-11-0, Durga Datt stated that he had transported 15,844 tons 2 Cwts of coal to the end of July 1951, which were loaded in the wagons and despatched. He also claimed Rs. 7,500 in respect of 3000 tons of coal which he had transported to the railway yard, but which had not been loaded on the wagons. After adjusting sundry amounts and allowing credit for rupees 21,861-7-6, he claimed Rs. 26,139-11-0, as stated above. Durga Datt alleged that Rungta was guilty of breach of the contract particularly of cls. (4), (5) and (8) thereof, which compelled him to rescind the contract. These clauses may be quoted here :
"(4) Petrol :- It will be arranged by party No. 1 himself but party No. 2 will help in time of need to get the petrol; the expenses incurred by party No. 2 for securing such petrol will be borne by party No. 1. If party No. 2 in spite of his best efforts cannot arrange for petrol then in such case party No. 1 will not be responsible for any loss in regard to transportation of coal.
(5) Payment of Bills : party No. 2 will make payment of Bills of party No. 1 for actual despatch of coal on the 10th of the following months;
(8) The road will be kept in repair by party No. 2."
4. The two suits were consolidated by the trial Judge, and evidence was partly recorded separately and partly for the two suits together. The trial Judge held that the breach of the contract proceeded form Durga Datt, and the suit of Rungta was decreed in the sum of Rs. 12,900 as damages due to him. In the other suit, the trial Judge held that Durga Datt was entitled to a payment of Rs. 26,695-6-6 and a decree for rupees 13,795-6-6 was passed in his favour after setting off the two amounts against each other. The rest of the claims
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.