SUPREME COURT OF INDIA
5th , December 1961
P.B. GAJENDRAGADKAR, A.K. SARKAR, K.N. WANCHOO, K.C. DAS GUPTA AND N. RAJAGOPALA AYYANGAR, JJ.
State of W.B., Appellant
Versus
M/s. B. K. Mondal and Sons, Respondents.
Civil Appeal No. 286 of 1958. 780
Advocates appeared
Mr. B. Sen, Senior Advocate (M/s. P. K. Chatterjee and P. K. Bose, Advocates, with him), for Appellant; Mr. N. C. Chatterjee, Senior Advocate (M/s. A. N. Sinha and P. K. Mukherjee, Advocates, with him), for Respondents.
Judgment
GAJENDRAGADKAR, J. : This appeal by special leave arises out of a suit filed by the respondent B. K. Mondal and Sons against the appellant the State of West Bengal on the Original Side of the Calcutta High Court claiming a sum of Rs. 19,325/- for works done by it for the appellant. This claim was made out in two ways. It was alleged that the works in question had been done by the respondent in terms of a contract entered into between the parties and as such the appellant was liable to pay the amount due for the said works. In the alternative it was alleged that if the contract in question was invalid then the respondent s claim fell under S. 70 of the Indian Contract Act. The respondent had lawfully done such works not intending to act gratuitously in that behalf and the appellant had enjoyed the benefit thereof.
2. The respondents case was that on February 8, 1944, it offered to put up certain temporary storage godowns at Arambagh in the District of Hooghly for the use of the Civil Supplies Department of the State of Bengal and that the said offer was accepted by the said department by a letter dated February 12, 1944. Accordingly the respondent completed the said construction and its bill for Rs. 39,476/- was duly paid in July 1944. Meanwhile, on April 7, 1944, the respondent was requested by the Sub-Divisional Officer, Arambagh, to submit its estimate for the construction of a kutcha road, guard room, office, kitchen and room for clerks at Arambagh for the Department of Civil Supplies. The respondent alleged that the Additional Deputy Director of Civil Supplies visited Arambagh on April 20, 1944 and instructed the respondent to proceed with the construction in accordance with the estimates submitted by it. Accordingly the respondent completed the said constructions and a bill for Rs. 2,322/8/- was submitted in that behalf to the Assistant Director of Civil Supplies on April 27, 1944. Thereafter the Sub-Divisional Officer, Arambagh required the construction of certain storage sheds at Khanakul and the Assistant Director of Civil Supplies wrote to the respondent on April 18, 1944, asking it to proceed with the construction of the said storage sheds. This work also was completed by the respondent in due course and for the said work a bill for Rs. 17,003/- was submitted. In the present suit the respondent claimed that the two bills submitted by it in which the respondent had claimed Rs. 2,322/8/- and Rs. 17,003/- respectively had remained unpaid and that was the basis of the present claim.
3. The appellant denied all the material allegations made by the respondent in its plaint. It alleged that the requests in pursuance of which the respondent claims to have made the several constructions were invalid and unauthorised and did not constitute a valid contract binding the appellant under S.175(3) of the Government of India Act, 1935 (hereafter called the Act). It pleaded that there was no privity of contract between the respondent and itself and it denied its liability for the entire claim. The written statement filed by the appellant was very vague and general in terms and no specific or detailed pleas had been set out by the appellant in its pleading.
4. However, G.K. Mitter, J., who tried the suit, framed five material issues on the pleadings and recorded his findings on them. He held that having regard to the provisions of S. 175(3) of the Act there was no valid and binding contract between the respondent and the appellant for the construction of huts and sheds at Khanakul and Arambagh. This finding was in favour of the appellant. He held that the respondent s claim against the appellant was, however, justified under S. 70 of the Indian Contract Act, and he came to the conclusion that the said claim was not barred by limitation. He also rejected the plea of the appellant that the liability of the Province of Bengal had not devolved upon the appellant under the provisions of the Indian Independence (Rights, Property and Li
Relied on : Bhikraj Jaipuria v. Union of India
Distinguished : Chatturbhuj Vithaldas Jasani v. Moreshwar Parashram and others
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.