SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1989 Supreme(SC) 607

SUPREME COURT OF INDIA
K.N. SAIKIA AND M. FATHIMA-BEEVI, JJ.
General Manager-cum-Chief Engineer, Bihar State Electricity Board and others. Appellants
Versus
Rajeshwar Singh and others, Respondents
Civil Appeal No. 221 of 1987, D/- 24-11-1989.

Advocates:
B.D.SHARMA, RANJIT GHOSAL, S.K.JAIN, SOLI J.SORABJI

Headnote:

Electricity Act, 1948 – Section 78 – Disconnection of Electric supply – Monthly Bills - Period from August many as 15 monthly bills were submitted to firm which, however, did not pay any of those bills firm was intimated that a sum outstanding against Consequently after giving statutory notice electric connection was disconnected – Thereafter in terms of aforesaid agreement minimum demand charges continued to be charged from firm on contract of demand – After disconnection was effected it appears firm also wrote to Board asking for disconnection on ground that floods had damaged their factory and they were not in need of electric energy – Notwithstanding disconnection firm was being charged minimum demand charges on basis of contract of demand minimum guaranteed charges and outstanding rose – Held, Incentive Scheme prior to that unless registration was with retrospective effect supply stood disconnected minimum guaranteed charges were still payable by firm and benefit to that extent would be available to firm – Electric connection was restored – Incentive Scheme was amended reducing benefit to a maximum of Unless Resolution itself so provided new Scheme will supersede earlier one – From that benefit will accordingly be reduced until the firm completed five years of production. As we do not have materials to show that firm was entitled to exemption and subsidy irrespective of its registration with the Industries Department, we are inclined to hold that it would be entitled only of its registration and till it completed five years of production – It will be exempted even if the electric energy supply was disconnected, provided it was still liable to pay minimum guaranteed charges – Appeal allowed.

Judgment

K. N. SAIKIA, J.:- This appeal by special leave is from the Judgment and Order of the High Court of Judicature at Patna, dated 10th March, 1983, in Civil Writ Jurisdiction Case No. 4581 of 1978 (reported in AIR 1983 Patna 194) allowing the writ petition and quashing the electricity bills dated 25-5-1978 and the Order dated 24-5-1978 refusing to apply the Incentive Scheme, and directing the Bihar State Electricity Board, hereinafter referred to as the Board to restore electrical connections immediately on payment of fresh bills.

2. The Board entered into an agreement on 12-8-1974 with the respondents who are partners of M/s. Alakha Rubber Industry, hereinafter referred to as the firm, to supply 100 KVA electric energy to the firm. Cl. 4(c) of the agreement read thus :

"The maximum demand charge for the supply in any month will be based on actual maximum KVA demand for the month or 75 per cent of the contract of the demand whichever is higher subject to provisions of Cl. 13. For the first 12 months service the maximum demand charge for any month will however be based on actual monthly maximum demand for that month."

During the period from August 1974 to October 1975 as many as 15 monthly bills were submitted to the firm which, however, did not pay any of those bills. On 6-9-1975 the firm was intimated that a sum of Rs. 51,789/- was outstanding against them. Consequently on 16-10-1975, after giving the statutory 7 days notice the electric connection was disconnected. Thereafter, in terms of aforesaid Cl. 4(c) of the agreement the minimum demand charges continued to be charged from the firm on the basis of 75 per cent of the contract of demand. After the disconnection was effected, it appears the firm also wrote to the Board asking for disconnection on the ground that floods had damaged their factory and they were not in need of electric energy. Notwithstanding the disconnection the firm was being charged the minimum demand charges on the basis of 75 per cent of the contract of demand, hereinafter referred to as the minimum guaranteed charges and the outstanding rose to Rs. 92,213 /- by 24-4-1977. The electric connection was restored on 15-6-1977 on the firms executing a fresh agreement dated 30-5-1977 and furnishing a fresh security deposit of Rs. 11,950/-. The firm submitted a representation to the Industrial Department of the State Government to take up the question of remission of current charges as well as for granting benefit under the Incentive Scheme in terms of the Government Resolution No. 16808 dated 29-9-1973. The Board allowed remission of minimum guaranteed charges under Clause 13 of the agreement for the financial year 1975-76 on account of flood damages caused to the firm, but rejected the claim in respect of years 1974-75 and 1976-77 and after adjustment on that account the firms outstanding stood at Rs. 59,369.15p. The Government Resolution No. 16808 dated 29-9-1973 was amended in 1976 with effect from 1-4-1976 restricting the Government subsidy in respect of minimum guaranteed charges to a maximum of Rs. 1,000 /- only per year. The Electrical Executive Engineer of the Board wrote to the firm on 23-5-1978 demanding the arrear dues. On 19-4-1978 the supply line was again disconnected; and on 23-5-1978 the Board wrote to the firm that the Incentive Scheme could not be extended to it as the name of the Industry did not find mention in the list of registered small scale industries. On 25-5-1978 the firm was served with a bill for Rs. 1,06,795/- being the outstanding dues mainly for minimum guaranteed charges for the entire period minus the remission granted for 1975-76. The firm moved the High Court of Judicature at Patna for quashing the bills, for grant of the benefit under the Incentive Scheme and for restoration of the connection.

3. Before the High Court the Board contended that the disconnection on 16-10-1975 was on the firms failure to pay the outstanding dues. The restoration thereafter was on execution o







Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top