SUPREME COURT OF INDIA
S. RANGANATHAN AND K.N. SAIKIA, JJ.
M/s. G. J. Fernandez, Petitioner
Versus
State of Karnataka and others, Respondents
Civil Appeal No. 1027 of 1990 (arising out of Special Leave Petn.(Civil) No.13495 of 1988), D/- 1-2-1990.
the High Court was right in declining to interfere.
Judgment
RANGANATHAN, J.:- The petitioner is aggrieved by the award of a contract by the Karnataka Power Corporation Ltd. (KPC), an instrumentality of the State of Karnataka, in favour of the Mysore Construction Co. (MCC). His writ petition and a further writ appeal in the Karnataka High Court having been unsuccessful, he has preferred this Special Leave Petition from the judgment of the High Court in the writ appeal. We have heard counsel for both sides at length. We grant special leave and proceed to dispose of the appeal.
2. Though, at an earlier stage of the proceedings there were some allegations of favouritism, the plea of the petitioner, as urged before us, is that the KPC should not at all have entertained the tender of MCC as the MCC did not fulfill certain preliminary requirements which, under the Notification Inviting Tenders (NIT), had to be fulfilled even before the forms of tender could be supplied to any intending contractor.
3. The contract pertained to the construction of a Main Station Building of a Power House at the Raichur Thermal Power Plant at an estimated cost of about Rs. 1.8 crores. The NIT dated 27-12-1988 invited tenders from registered contractors of appropriate class. Paragraph I of the notification listed three "Minimum qualifying requirements" viz., that the intending tenderer:
(1) should have executed civil and architectural works including insulation in a power plant/ industrial complex, preferably in power plant;
(2) should have executed at least 1000 cubic metres per month of concrete pouring at least 300 cubic metres per month of brick work at one site; and
(3) should have had an annual turnover of at least 1 crore for each of the preceding three years.
Para V required the intending tenderers to furnish the following information "along with the application for issue of blank tender books", namely:
(a) Audited Balance Sheet/ Certificate from Chartered Accountant for, preceding three years;
(b) Latest income-tax clearance certificate;
(c) Copy of the Registration Certificate;
(d) Annual output of the works of all the above nature at any site accompanied by a certificate from the organisation for whom the tenderer had carried out the works furnishing details such as rate of pouring ofconcrete, manufacturing of hollow concrete blocks, precast concrete blocks......etc., and period of completion scheduled/ envisaged, equipments and their deployment i.e., man months etc.
4. The NIT specified January 17,1989, as the last date for receipt of application forms for issue of blank tender books. The issue of blank tender books was to be between 23rd January to 27th January, 1989 and the completed tender books had to be submitted by 3-00 p. m. on 6-2-89. It is common ground, however, that subsequently this time frame was altered. The last date for receipt of application form for issue of blank tender books remained as 17th January, 1989 but the other items were altered to read as follows:
"1. Last date for receipt of clarification: 10-2-89
2. Period to issue blank tender books: 13-3-89 to 16-2-89
3. Last date and time for receipt of completed tender books: 27-2-89 upto 3. p.m."
5. It appears that six parties applied for tender books. These were scrutinised with reference to the pre-qualifying requirements and date on experience, work done etc. as furnished by each of the applicants. Four of the firms were found to be pre-qualified by the Chief Engineer and tender books were issued to them. Only three of them, however, submitted completed, tender books by February 27, 1989. These tenders were examined by the Chief Engineer as well as an independent firm of Engineering Consultants, namely, Tata Consulting Engineers (TCE). Both the Chief Engineer as well as TCE recommended acceptance of the tender of MCC (which was the lowest tender) in view of the fact that MCC had adequate experience in the construction of RCC works and they were capable of mobilising the work-force required. for the work. It may be mentioned that aft
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.