SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1994 Supreme(SC) 349

SUPREME COURT OF INDIA
K. RAMASWAMY AND N. VENKATACHALA, JJ.
K. Sasidharan, Appellant
Versus
Kerala State Film Development Corpn., Respondent.
Civil Appeal No. 4022 of 1994 (arising out of S.L.P. (Civil) No. 2588 of 1987).
D/ 17-3-1994.

Advocates:
A.T.M.SAMPATH, DILIP PILLAI, E.M.S.ANAM, G.VISHVANATHA IYER

Headnote:

Arbitration Act, 1940 – Section 20 - Dispute for Arbitration - Appellant had entered into a contract with respondent to construct a theatre - He completed the work and handed over same to the respondent During execution of the contract dispute had arisen on certain items of work which was sought to be decided by arbitration - Appellant, filed O.S. in Court of Subordinate Judge, Trivandrum for short Act for reference to an Arbitrator - Respondent contended that there is no arbitrable agreement under contract - Overruling objection, Subordinate Judge by his order held that Clause 73 of Madras Detailed Standard Specifications for short MDSS would apply to dispute which contains an arbitrable clause and, by order appointed a retired District Judge as an Arbitrator - On appeal by respondent by order Division Bench of Kerala High Court held that Clause 73 of MDSS is inapplicable - There is no arbitrable agreement for reference to the Arbitrator – Held, Appellant and respondent having specifically excluded the arbitration clause in the contract, by necessary implication they excluded the clause 73 in MDSS. If it were to be contract it must expressly and specifically be incorporated in the contract which admittedly was not done. When the parties to the agreement, in terms of the documents, have not incorporated the arbitration agreement in clause 73 of MDSS, it cannot, by implication, be imported by interpretation that the terms of clause 73 including arbitration clauses therein stands attracted. By necessary implication, it conflicts with the expressly agreed terms of the contract - It is manifest that what the terms in MDSS, referred to in clause 12 is only of the terms referable to the execution of the work, etc. and not one concerned with an agreement to refer any dispute arising between parties to an arbitration, at later point of time, or during the course of execution of work or after completion thereof of any dispute arising between parties in relation to contract - Appeal dismissed.

JUDGMENT

Leave granted. Heard both the counsel.

2. The appellant had on January 27, 1982 had entered into a contract with the respondent to construct a theatre. He completed the work and handed over the same to the respondent in May, 1985. During the execution of the contract a dispute had arisen on certain items of the work which was sought to be decided by arbitration. The appellant, therefore, filed O.S. No. 20 of 1986 in the Court of Subordinate Judge, Trivandrum under S. 20 of the Arbitration Act, 1940, for short the Act for reference to an Arbitrator. The respondent contended that there is no arbitrable agreement under the contract. Overruling the objection, the Subordinate Judge by his order dated June 5, 1986 held that Clause 73 of the Madras Detailed Standard Specifications for short MDSS would apply to the dispute which contains an arbitrable clause and, therefore, by order dated 2nd July, 1986 appointed a retired District Judge as an Arbitrator. On appeal by the respondent in M.F.A. No 460 of 1986, by order dated December 15, 1986, the Division Bench of the Kerala High Court held that Clause 73 of MDSS is inapplicable. There is no arbitrable agreement for reference to the Arbitrator. Thus, this appeal by special leave.

3. Sri E.M.S. Anam, learned counsel for the appellant, placing reliance on clause 12 of the "General Condition of the Contract" contended that all items of work referred to therein would include MDSS in the addenda volume. Clause 73 of the arbitrable agreement therein gets attracted to the dispute. Therefore, the trial Court was right in its conclusion that the dispute is arbitrable under clause 73. The High Court was not right in its contra conclusion.

4. Having given our anxious consideration, we find that the contention raised by the appellant is not tenable. Admittedly, the contract contains Article 60 which provide "arbitration of any dispute or difference between the parties to the contract either during the progress or after completion of the works or the interpretation of the contract of any matter or thing arising thereunder except as to the matters left to the sole discretion of the Corporation Engineer under the clauses of the contract." While entering into the contract this clause was admittedly excluded, In Article 2 of the "General Conditions of the Contract" clause (b) provides that "the Original Agreement, with its accompanying Schedules form part of the Contract Documents and shall be kept by the Corporation but the Contractor shall be supplied with a copy of the agreement and copies of Tender Notification, General Conditions of the Contract, Specifications, Drawings and relevant schedules all duly attested by the Contractor and the Managing Director". Clause (f) postulates that "the terms of the Contract cannot be added to varied or reduced by any oral agreement previous or subsequent to its signature."

5. Clause 12 relied upon by Sri Anam, the relevant part reads thus: "And item of work shall be carried out as per Madras Detailed Standard Specifications and its addenda volume and shall be deemed to have been included here". What clause 12 postulates is that the General conditions regarding the execution of the work will be as carried on in accordance with the conditions etc. contained in MDSS and addenda. General Conditions of the Contract provided the accepted rates, units, tentative quantities etc. which were given in the Schedule A and the time schedules for the work was given in Schedule B. The list and details regarding supply of drawings were given in Schedule C. The short description given in the Schedule A for different items were only the General specifications. Thereafter, the above 12th clause has been added, namely, "All items of work shall be carried out as per Madras Detailed Standard Specifications and its addenda volume and shall be deemed to have been included here." The arbitration agreement is collateral to the substantial stipulation of the contract. It is merely pro






Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top