SUPREME COURT OF INDIA
BEFORE B.P. JEEVAN REDDY AND M.K. MUKHERJEE, JJ.
Civil Appeal No. 8223 of 1995
PLEASANT STAY HOTEL AND ANOTHER
Versus
PALANI HILLS CONSERVATION COUNCIL AND OTHERS
With
Civil Appeal No. 8224 of 1995
PLEASANT STAY HOTEL AND ANOTHER
Versus
PALANI HILLS CONSERVATION COUNCIL AND OTHERS
With
Civil Appeal No. 8228 of 1995
PLEASANT STAY HOTEL AND ANOTHER
Versus
PALANI HILLS CONSERVATION COUNCIL AND OTHERS
With
Civil Appeals Nos. 8225-27 of 1995
STATE OF T.N. AND ANOTHER
Versus
PALANI HILLS CONSERVATION COUNCIL AND OTHERS
Civil Appeals Nos. 8223, 8224, 8228 and 8225-27 of 1995{From the Judgment and Order dated 10-4-1995 of the Madras High Court in W.P. No. 13231 of 1992},
Decided on 13-9-1995
Advocates appeared:
G. Ramaswamy and Dr Rajeev Dhavan, Senior Advocates (Sanjay Hegde, E.R. Kumar, P.H. Parekh, Ms A. Subhashini, A. Ranganadhan, Sriram Panchu, Dayan Krishnan, Gopal Singh, Nikhil Nayyar and P.P. Tripathi, Advocates, with them) for the appearing parties.
Tamil Nadu District Municipalities Act, 1920 - Tamil Nadu Societies Registration Act, 1975 - Amendment Act 58 of 1992 - Section 217-Q - Section 217-B - Section 217-C - Sub-section (5) of Section 217-C - Section 217-D - Section 217-O - Section 217-K - Permission To Construct A Hotel - Proposal To Construct More Than Two Floors - Pleasant Stay Hotels Pvt. Ltd. applied to Kodaikanal Township Committee for permission to construct a hotel building in town of Kodaikanal - Along with application it submitted plan and other necessary documents - According to plan building was to comprise a ground floor and a first floor - Hotel sent a revised plan to Committee for its approval with a forwarding letter addressed to its Executive Officer - In reply thereto Committee informed Hotel, by its letter that application for sanction of revised plan was rejected as proposal to construct more than two floors was against clause 8.6.1 of Master Plan Rules - Hotel was also informed that no construction work should be commenced or proceeded with without obtaining licence or permission – Held, Hotel resorted to in spite of repeated opportunities given and reminders issued to retrace their steps and any sympathy shown to Hotel would be wholly misplaced – Court need not, however, dilate on this aspect of matter as it appears to court that there is some confusion as to nature of above-quoted direction, given by High Court and it requires to be clarified - According to first part of direction Respondents 1 and 2 are to demolish building constructed by Hotel to the extent to which it is contrary to plan sanctioned by second respondent - If this direction is to be complied with thenin that case demolition has to be of five floors below road level for plan was sanctioned showing road level as ground level, while other part of direction seems to indicate, that besides two floors above natural ground level of site rest of construction has to be demolished - In other words, from order it is not clear as to whether High Court intended that construction of two floors above road level has to be kept intact and rest demolished, or stepped structure of two floors arising from natural ground level has to be kept intact and rest demolished irrespective of what sanctioned plan indicates - This is a matter which High Court should clarify now - While upholding judgment of High Court, court remand matter to it for limited purpose of issuing fresh directions in light of observations - Appeal disposed Of.
JUDGMENT
M.K. MUKHERJEE, J.- Special leave granted. Heard the learned counsel appearing for the parties.
2. These six appeals have been heard together as they stem from a common judgment rendered by a Division Bench of the Madras High Court disposing of three writ petitions. Facts leading to these appeals and relevant for their disposal are as under.
3. In April 1981 Pleasant Stay (Kodai) Hotels Pvt. Ltd. (hereinafter referred to as the Hotel) applied to the Kodaikanal Township Committee (hereinafter referred to as the Committee) for permission to construct a hotel building in the town of Kodaikanal. Along with the application it submitted the plan and other necessary documents. According to the plan the building was to comprise a ground floor and a first floor. The plan was sanctioned by the Committee on 1-11-1991 subject to the following, amongst others, conditions:
(i) the construction should be completed by 31-10-1992 and should not be continued thereafter without renewal;
(ii) if the construction was to be different from the sanctioned plan a new plan must be drawn and fresh permission obtained, in default, construction in breach of the plan should be removed; and
(iii) nothing should be done in variation of the sanctioned plan.
4. On 29-1-1992 the Hotel sent a revised plan to the Committee for its approval with a forwarding letter addressed to its Executive Officer, wherein it stated, inter alia, "the revised plan has been necessitated as the natural earth level of our site leaves us with 20 to 50 feet beam and column structure below the approved plan at different levels". In reply thereto the Committee informed the Hotel, by its letter dated 7-2-1992 that the application for sanction of the revised plan was rejected as the proposal to construct more than two floors was against clause 8.6.1 of the Master Plan Rules. The Hotel was also informed that no construction work should be commenced or proceeded with without obtaining licence or permission, otherwise action would be taken under the Tamil Nadu District Municipalities Act, 1920(Act for short). Aggrieved by such rejection the Hotel preferred an appeal on 11-2-1992 to the Secretary to the Government of Tamil Nadu, Housing and Urban Development, through the Executive Officer of the Committee and the Director of Town and Country Planning. In the appeal the Hotel took the stand that the Contour Plan (attached therewith) of the land was such that while constructing the ground floor and first floor of the proposed building it had to leave open column and beam structure of 20 feet to 50 feet at different levels and that through the revised plan it wanted permission to fill up the open space under the already approved plan with rooms and other facilities of tourist interest for otherwise the open space would have to be filled up with stone and sand which, necessarily, would be a national waste. It was also stated therein that leaving the space under the building open as per the approved plan would project it only as a big water tank.
5. As in spite of rejection of the revised plan, the Hotel continued with the construction work. The Committee issued another notice on 22-4-1992 asking it to remove the offending constructions with a warning that action would be taken under Section 317 of the Act. In reply thereto the Hotel alleged that the Committee was acting with ulterior motive and denied to have made any construction against the Rules and Regulations. The Committee then filed a suit against the Hotel in the Court of the District Munsif, Kodaikanal, for a mandatory injunction directing the demolition of the building unlawfully constructed in the suit property over and above the ground and the first floor and for a permanent injunction restraining the Hotel from raising any construction without prior approval and permission of the Committee.
6. Immediately after the suit was filed Palani Hills Conservation Council (Council for short), a Society formed with the object, amongst others,
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.