Assistant Commissioner, Gadag Sub Division, Gadag – Appellant
Versus
Mathapathi Basavannewwa – Respondent
ORDER
An interesting question has been raised by Shri Nagaraja, learned counsel for the petitioner, in this case.
2. The admitted facts are that the petitioner had taken possession of the lands on 23-1-1971, but the notification under S.4(1) of the Land Acquisition act (for short the Act) was published in the Gazette on 2-8-1984. The award came to be made by the Land Acquisition Officer on 15-1-1986. The question is from what date the respondents-owners are entitled to the benefit of S.23(1-A) of the Act as amended by Act 68 of 1984.
Section23(1-A) reads thus :
"23(1-A) : In addition to the market value of the land, as above provided, the Court shall in every case award an amount calculated at the rate of twelve per centum per annum on such market value for the period commencing on and from the date of the publication of the notification under Section 4, sub-section (1), in respect of such land to the date of the award of the Collector or the date of taking possession of the land whichever is earlier."
(Emphasis supplied).
3. Learned counsel contended that conjoint reading of the dates of notification and making of award would connote that taking possession referable under the expressio
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.