SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1994 Supreme(SC) 237

SUPREME COURT OF INDIA
B.L.Hansaria : B.P.Jeevan Reddy
Tarapore And Company
Versus
State Of M.P.
Case No. : 1246 of 1992
Date of Decision : 2/16/94
Advocates Appeared: Agnihotri S.K. : Deshpande S.V. : Deshpandey S.V. : Nambiar A.R. : Nambiar K.R. : Nariman F.S. : Raghavan T. : Rao V.R. : Sanghi G.L. : Sharma S.C.

Advocates:
A.R.Nambiar, F.S.NARIMAN, G.L.SANGHI, K.R.NAMBIAR, S.C.Sharma, S.K.AGNIHOTRI, S.V.DESHPANDEY, T.RAGHAVAN, V.R.Rao

Headnote:

Arbitration Act, 1940 - Section 30 – Claim of compensation – Jurisdiction - Reference was made on an application made by appellant under Section 20(1 of the Act - That application was based on the terms of the agreement entered into by the appellant with the State of Madhya Pradesh relating to construction of Masonry Dam. One of the terms of the agreement as incorporated in clause settlement of dispute arising out of contract by arbitration. The appellants averment was that after the contract was entered into, minimum wages were raised by the State and the appellant was required to pay wages accordingly - Rates quoted by the appellant, however, related to wages as were prevalent at the time when the tender was invited - Revision of wages upset all the calculations as extra amount had to be paid on this count – Held, Insofar as acceptance of component, which is primary reason for finding of fault as to quantum brings to our notice the statement made at the end of the 6 of award according to which the respondents tacitly accepted" by their own component in the type of work done by the appellant - Award further states that documents placed on record in this regard "have not been denied by the respondent during the arguments and have been taken on record - BECAUSE of the above, we hold that the fault found by the High court regarding the basis on which the second award was made was not the correct view to be taken. But, as we have held that the appellant is entitled to be reimbursed for the extra payment made only on account of rise in the rates of fair wages and as the arbitrators had not calculated the extra amount paid on this count separately, we remit the case back to the High court to give its finding on this aspect, for which purpose parties would be allowed to place further material on record, if prayed for – Court make it clear that while calculating amount as stated earlier High court would take into account that part of enhanced rate of fair wage which was, if at all above rate of minimum wages prevailing at the relevant time – Court have said so because conceptually fair wage is higher than minimum wage and is required to be so – Court also state that the total sum to be determined by the High court would not, in any case exceed a sum of which is the amount awarded by the arbitrators on the second occasion also - FROM the above, it would appear that all that was possible on the part of the appellant to prove actual payment was done. It is a different matter that because of lapse of time many of the piece workers were not available and despite notices issued to them only four replied of whom two were examined as noted in award - Appeal is allowed

Judgment

B.L.HANSARIA, J.

(1) THE appellant impugns the judgment of the High court of Madhya Pradesh by which it has upheld the order of the District Judge, Jabalpur, setting aside the award of the arbitrators in exercise of power conferred by Section 30(a) of the Arbitration Act, 1940, hereinafter the Act.

(2) THE award to be set aside was one which had come to be passed following the order of the District Judge dated 6/05/1987 in Civil Suit No. 1-A/87 by which an earlier award had come to be remitted to the arbitrator for reconsideration keeping in view the legal arguments advanced. The first award owes its origin to the following question referred for determination by the two arbitrators named in the order of the District Judge passed on 12/04/1985:

"WHETHER the State is not liable to reimburse to the applicant Rs. 3,42,69,847.00 for the period 7/08/1979 to august 31/08/1984 on account of difference in wages,"

(3) THE reference was made on an application made by the appellant under Section 20(1 of the Act. That application was based on the terms of the agreement entered into by the appellant with the State of Madhya Pradesh relating to construction of Bargi Masonry Dam. One of the terms of the agreement as incorporated in clause 4.3.29(2 provided for settlement of dispute arising out of contract by arbitration. The appellants averment was that after the contract was entered into, minimum wages were raised by the State and the appellant was required to pay wages accordingly. The rates quoted by the appellant, however, related to wages as were prevalent at the time when the tender was invited. The revision of the wages upset all the calculations as extra amount had to be paid on this count. The Superintending Engineer rejected the claim of reimbursement on the ground of no escalation clause in the contract, whereupon the appellant called upon the Superintending Engineer to appoint an arbitrator on behalf of the State. This not having been done and the appellant having appointed one Brigadier D.R.Kathuria as arbitrator, it approached the court to direct the State to file the arbitration agreement and to make an order of reference. The non-applicant did not oppose; indeed it filed no reply. Not only this, it even named one Shri V.M. Chitale as arbitrator while filing the arbitration agreement.

(4) IN these circumstances the aforesaid question was referred for determination by the two named arbitrators. After the reference was entered into by the arbitrators the appellant claimed a sum of Rs. 3,42,69,847.00 on the aforesaid count. The State admitted that the contractor was liable to pay the increased wages under the Minimum Wages Act, but took a stand in paragraph 12 of its counter that the claimant was not entitled to the increased amount on account of revision of wages and denied its liability to reimburse. The arbitrators, however, by order dated 20/11/1986 awarded a sum of Rs. 236 lakhs with simple interest per cent to the claimant-appellant. It may be stated that by the time the award was passed one Shri K.C. Goel had stepped into the shoes of Brigadier D.R. Kathuria.

(5) THE State approached the District Judge to set aside the award, inter alia, on the ground that the arbitrators had not decided the question of the liability of the State to reimburse the claim due to escalation of wages which was one of the matters referred to the arbitrators. This is what appears from the States petition filed on 23/01/1987 under Section 30 of the Act. When the matter came to be taken up by the District Judge the main contention advanced was, however, relating to quantum of award, as it would appear from paragraph 5 of the order of the District Judge passed on 6/05/1987. The attack on this score was on the ground that the arbitration could not have calculated the amount on the task-basis of the sub-contractor and piece workers. The District Judge took the view that the difference in wag
















































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top