SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1988 Supreme(SC) 512

SUPREME COURT OF INDIA
S.Ranganathan : Sabyasachi Mukharjee
State Of Rajasthan
Versus
R.S.Sharma And Company
Case No. : 3054 of 1988
Date of Decision : 8/16/88
Advocates Appeared: Das Rathin : Kulad Paras : Nariman Rohinton F. : Parasaran K. : Saruparia B.L. : Sharma Badri Das : Sorabjee Soli J.

Advocates:
B.L.SARUPARIA, Badri Das Sharma, K.PARASARAN ATTORNEY, PARAS KUHAD, RATHIN DAS, ROHINTON F.NARIMAN, SOLI J.SORABJI

Headnote:

Construction - Dam Division - This appeal challenges order of High court of Rajasthan - Respondents tender for construction of complete masonry dam was accepted by appellant for a sum and a provisional agreement was entered into between parties - Construction was commenced by respondent-company but it did not complete same and, it is alleged, left work unfinished which was of the value - It is stated that respondent did not start (sic complete) work in spite of written notices and, ultimately, by a letter of the Executive Engineer (Dam Division), respondent was informed that as it had committed breach of conditions of contract, same had been terminated and that State government would complete work under clauses and conditions of contract - Work had to be completed departmentally at cost and risk of respondent-company - After some litigation between the parties when the civil revision was pending in High court - A compromise between parties was arrived - It was agreed that dispute would be settled through arbitration - By an agreement parties named their arbitrators – Held, in that context it was held in those cases that arbitrator had power to grant interest - It was contended before us that this was a similar case - There was a court proceeding in this case regarding the appointment of arbitrator and, as such, on the same analogy it should be treated that the arbitrator had power to grant interest - Court are unable to accept this - In that view of the matter this part of award, which was affirmed by High court of granting of interest, must be deleted - Court do so accordingly - Learned Attorney General, assures court that amount awarded as modified, would be paid within eight weeks - Appeal is thus disposed of.

JUDGMENT

SABYASACHI MUKHARJEE, J.

(1) LEAVE granted. Appeal is disposed of by the judgment herein.

(2) THIS appeal challenges the order of the High court of Rajasthan, dated 16/03/1988. The respondents tender for construction of complete masonry dam (Civil Engineering Works) Mani Bajaj-Sagar Project, Banswara, was accepted by the appellant for a sum of Rs. 5,90,30,791.00 vide letter dated 29/04/1974 and a provisional agreement was entered into between the parties on 23/05/1975. The construction was commenced by the respondent-company but it did not complete the same and, it is alleged, left the work unfinished in the year 1979, which was of the value of Rs. 1,79,80,054.00.

(3) THE letter of acceptance was dated 23/05/1975. It is stated that the respondent did not start (sic complete) the work in spite of written notices and, ultimately, by a letter dated 24/12/1979 of the Executive Engineer (Dam Division), Banswara, the respondent was informed that as it had committed breach of the conditions of the contract, the same had been terminated and that the State government would complete the work under the clauses and conditions of the contract. The work had to be completed departmentally at the cost and risk of the respondent-company. After some litigation between the parties when the civil revision was pending in the High court of Rajasthan at Jodhpur. a compromise between the parties was arrived at on 13/04/1982. It was agreed that the dispute would be settled through arbitration. By an agreement dated 13/06/1982 the parties named their arbitrators.

(4) THE arbitrators entered upon the reference on 19/06/1982. On 5/05/1982, the respondent-company presented its claims under 40 heads claiming a total sum of Rs. 1,90,53,059.28. This amount was later on revised to Rs. 1,82,20,261-02. The State filed a counter claim for a sum of Rs. 1,70,63,026.37 which was revised to Rs. 1,25,706.17. It is stated that the arbitration proceedings were conducted for 52 days during which the number of sittings was 25. Various issues were framed. Minutes of the proceedings were recorded. The arbitrators gave the award on 8/12/1982. It is stated that the award did not contain any reason as to why and how they had arrived at the figure of Rs. 75,41,755.00 in favour of the respondent company. The award, however, mentioned that the State of Rajasthan committed breach of contract and was also guilty of wrongful revocation of the agreement and the actions taken under Clauses 2 and 3 of the conditions of the contract, were wrongful and unjustified. However, no reasons were indicated as to how the arbitrators arrived at those findings.

(5) THE respondent filed an application in the court of the learned District Judge for making the award rule of the court. The appellant, however, filed an objection on the grounds inter alia that no reasons had been given by the arbitrators for the award and the amount of interest awarded was unjustified. It was further averred that the award being ambiguous, showed non-application of mind and the question as regards the plant and machinery of the respondent-company lying at the dam site, were beyond the scope of the arbitrator.

(6) THE learned District Judge by his judgment and order dated 11/08/1987 allowed the objection and set aside the award on the ground of ambiguity and non-application of mind. The award also suffered from the vice of non-statement of reasons, according to the learned District Judge. According to him, the award was not in accordance with law. He further held that the plant and machinery lying at the dam site was beyond the reference made to the arbitrators. He was of the opinion that the interest amount was ambiguous and thus liable to be set aside. There was an appeal to the High court. The High court allowed an appeal and passed a decree for Rs. 75,41,755.00 being the amount of all claims and directed that the State should pay interest @ 5 per cent










Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top