SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2010 Supreme(SC) 286

2010 (2) Supreme 697
SUPREME COURT OF INDIA
R.V. Raveendran and R. M. Lodha —JJ.
State of Maharashtra — Appellant
Versus
M/s. Hindustan Construction Company Ltd. — Respondent
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 2928 OF 2010
(Arising out of SLP(C) No. 3937 of 2009)
Decided on : April 1, 2010.

IMPORTANT POINT
New grounds containing new material/facts could not have been introduced for the first time in an appeal when these were not originally raised.

Headnote:(a) Code of Civil procedure, 1908 – Order VI, Rule 17 – Amendment in the pleadings is a matter of procedure – Grant or refusal thereof is in the discretion of the court – Like any other discretion, such discretion has to be exercised consistent with settled legal principles. (Para 14)

       (1978) 2 SCR 614; Vol XXXII The Weekly Reporter 262; (1920) LR 47 IA 255; (1957) SCR 438; (1957) SCR 595; (1969) 1 SCC 869 – Relied upon

       (b) Code of Civil procedure, 1908 – Order XLI Rules 2 and 3 – Appellate court has power to grant leave to amend the memorandum of appeal. The memorandum of appeal has same position like the plaint in the suit. (Para 21)

       (1982) 3 SCC 408 – Relied upon

       (c) Arbitration and Conciliation Act, 1996 – Section 34 r/w section 37 – Courts would, as a rule, decline to allow amendments, if a fresh claim on the proposed amendments would be barred by limitation on the date of application – That would be a factor for consideration but does not affect the power of the court to order it – Every amendment in the application for setting aside an arbitral award cannot be taken as fresh application. (Paras 25 and 26)

       (1957) SCR 438; (1957) SCR 595; (1978) 2 SCR 614; (1994) 6 SCC 117 – Relied upon

       1987 (Supp.) SCC 93; 2001 (2) Arb. LR 315 (Bombay) – Distinguished

       (d) Arbitration and Conciliation Act, 1996 – Section 37 – Amendment of arbitration petition for setting aside award – New grounds containing new material/facts could not have been introduced for the first time in an appeal when these were not originally raised in the arbitration petition. (Para 28)

       Facts of the case:

       The question in this appeal is : whether in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 from an order refusing to set aside the award, an amendment in the memorandum of appeal to raise additional/new grounds can be permitted.

       Finding of the Court:

       There is no merit in the appeal.

Judgement Key Points

Key Points: - New grounds containing new material or facts cannot be introduced for the first time in an appeal if they were not originally raised in the arbitration petition (!) (!) . - The memorandum of appeal has the same position as the plaint in a suit, and amendments are guided by principles of justice and discretion of the court (!) (!) . - Amendment in the application for setting aside an arbitral award cannot be treated as a fresh application if it does not amount to raising an independent ground after the limitation period (!) (!) . - The time limit for setting aside an award under Section 34 is absolute and cannot be extended beyond three months plus thirty days on sufficient cause (!) (!) . - Where new grounds are sought to be added in the memorandum of appeal without having been raised in the arbitration petition, the appeal lacks merit and must be dismissed (!) (!) .

What is the prerequisite for introducing new grounds in an appeal under Section 37 of the Arbitration and Conciliation Act?

How to determine whether an amendment adding new grounds to an appeal is permissible?

What is the consequence of raising new grounds in an appeal that were not originally raised in the arbitration petition?


JUDGEMENT

R.M. Lodha, J.

Leave granted.

2. The question presented in this appeal by special leave is : whether in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (for short ‘1996 Act’) from an order refusing to set aside the award, an amendment in the memorandum of appeal to raise additional/new grounds can be permitted.

3. M/s. Hindustan Construction Company Limited (respondent) and the State of Maharashtra (Irrigation Department, the Executive Engineer - appellant) entered into a contract on March 14, 1992 being ICB Contract No. II/1992 for the construction of civil work of Pressure Shafts and Power House Complex at Koyana Hydro Electric Project, Stage-IV. The contract work was completed by respondent within the extended period i.e., by March 31, 2000. However, it appears that disputes arose between the parties in respect of the work carried out by respondent in relation to (a) revision of percentages for hidden expenses, over breaks and profit for further additional cases of extract items/rate revision; (b) claim for extended stay at site; (c) revision of rate for Pressure Shaft excavation; (d) fixation of new rate on account of variation in the item of Transformer hall arch concrete; and (e) fixation of new rate on account of variation in the item of Transformer Hall excavation. These disputes were referred to the Arbitral Tribunal. The Arbitral Tribunal made award on June 26, 2003 and a signed copy thereof was forwarded to the appellant along with the letter dated June 30, 2003. By the said award the Arbitral Tribunal awarded an amount of Rs. 17,81,25,152/- to respondent and further directed that if the said amount was not paid by appellant within two months from the date of the award, then the awarded sum shall carry an interest at the rate of 15 per cent per annum from June 27, 2003.

4. Not satisfied with the award dated June 26, 2003, appellant made an arbitration application on August 22, 2003 for setting aside the award. The appellant also relied upon Sections 28, 33 and 16 of 1996 Act in assailing the award being in contravention of the provisions of 1996 Act and set up the grounds viz., (i) waiver (final bill was accepted by respondent without protest and the claims are not arbitrable); (ii) acquiescence (contract ceased to exist after accepting final payment which was made on March 30, 2001 after completion of maintenance period); (iii) delay (claims are time barred under the provisions of the Limitation Act); (iv) laches (respondent’s Arbitrator was not appointed before expiry of 30 days from the defect liability and, therefore, the claimant was not entitled to bring claim Nos. 3, 4 and 5 to arbitration) and (v) res judicata (claim No. 1 was referred to the earlier Arbitration Panel in the year 1998 and hence the said claim is barred by principles of res judicata).

5. The District Judge, Ratnagiri vide order dated June 29, 2006 rejected the application for setting aside the award dated June 26, 2003.

6. The appellant aggrieved thereby preferred an appeal under Section 37 of 1996 Act on February 6, 2007 before the High Court of Judicature at Bombay.

7. On June 23, 2008, appellant made an application before the High Court seeking amendment to the memorandum of arbitration appeal by adding additional grounds, namely, that the Arbitral Tribunal exceeded jurisdiction in awarding revision of percentage for hidden expenses over-heads and profits for further additional items (Claim No. 1); that the Arbitral Tribunal acted beyond the scope of arbitration with regard to extended stay charges (Claim No. 2); the Arbitral Tribunal exceeded jurisdiction and, in fact, committed error of jurisdiction in granting claim pertaining to revision of rate for pressure shaft excavation and mis-conducted themselves in awarding escalation considering March 2000 Indices.

8. The aforesaid application was opposed by respondent on diverse grounds, inter alia, that the additional grounds sought to be inco









































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top