Supreme Court of India
THE HONOURABLE MR. JUSTICE AFTAB ALAM & THE HONOURABLE MR. JUSTICE T.S. THAKUR
M/s. Rashtriya Chemicals & Fertilizers Ltd.
Versus
M/s Chowgule Brothers & Others
CIVIL APPEAL NO.5286 OF 2006
Decided on : 07-07-2010
(b) Arbitration law – Arbitrators cannot travel beyond specific terms of contract. (Para 16)
(1999) 8 SCC 122; (2002) 5 SCC 679; (2003) 8 SCC 154; (2004) 9 SCC 619; AIR 1992 SC 232; AIR 2005 SC 4430; (2003) 4 SCC 80 232 – Relied upon
(c) Arbitration law – Respondent making three claims – Claim of Rs.27,91,984.29 on account of escalation of the rates consequent upon statutory increases in the wages of M.D.L.B. and a further claim of Rs.9,88,713.20 on account of escalation in the wages of other categories of workers such as Tally Clerks, Stichers, Foreman, Asst. Foremen, Supervisors etc. during the extended period of contract – In addition, a claim for the recovery of Rs.8,63,953/- towards the final payment due and payable with interest @ 18% p.a. – Entitlement of the respondent to claim any amount on account of escalation consequent upon the increase in the wages of M.D.L.B. workers not established – The first two claims on account of escalation could not have been allowed by the Arbitrators nor could the incidental claim for payment of interest on that claim be granted – Claim of Rs.8,63,953/- with the interest @ 9% p.a. from 1st April, 1985 till the date of actual payment thereof held payable to respondent. (Para 23, 24)
Facts of the case:
In response to an advertisement issued by the appellant inviting tenders for allotment of clearing, forwarding, handling and stevedoring jobs at Mormugao Port initially for a period of one year commencing from 15th January 1983 upto 14th January 1984 but extendable at the option of the appellant for a further period of one year on the same terms and conditions except statutory increases in the wages of Dock labourers referred to in Clause 2.03 of tender notice, the respondent’s tender was accepted and work order dated 10th January 1983 was issued in its favour. The contract was extended in terms of Clause 2.03 of the NIT for a further period of one year ending 14th January 1985.
The respondent alleged that pursuant to a settlement between the M.D.L.B. and the Dock workers the respondent had incurred an additional amount of Rs.24.74 lakhs towards the increase in the wages payable to such workers. A claim for reimbursement of the said amount was made by the respondent-company, which was refuted by the appellant on the strength of Clause 2.03 of Schedule II to the NIT.
Denial of the claim made by the respondent thus gave rise to a dispute which was referred to a panel of three Arbitrators for adjudication. The Arbitrators examined rival contentions urged before them but failed to arrive at a unanimous decision on the true and correct interpretation of Clause 2.03. Two awards, therefore, came to be made, one by Shri R.P. Bhatt who dismissed the claim and the other by M/s R.C. Cooper and N.A. Modi who held the respondents entitled to recover from the appellant a lump sum amount of Rs.61,73,067.90.
Aggrieved by the majority Award, the appellant filed Arbitration Petition before the High Court for setting aside the same. A Single Judge of the High Court allowed that prayer and set aside the award holding that the same was contrary to clause 2.03 of the NIT forming part of the contract executed between the parties. Even the plea of limitation succeeded before the learned Single Judge.
Undeterred, the respondents assailed the said order before a Division Bench of the High Court which allowed the appeal, set aside the order passed by the Single Judge and restored the majority Award made by the two Arbitrators.
Finding of the Court:
Respondent is entitled to part of the claim.
Result:
Appeal partly allowed.
Judgment :-
T.S. THAKUR J.
1. This appeal by special leave is directed against an order dated 5th April 2006 passed by the High Court of Bombay whereby Appeal No.884 of 1997 has been allowed, the order passed by a learned Single Judge of that Court set aside and the majority award passed by the arbitrators restored.
2. The appellant, a Government of India undertaking invited tenders for allotment of clearing, forwarding, handling and stevedoring jobs at Mormugao Port initially for a period of one year commencing from 15th January 1983 upto 14th January 1984 but extendable at the option of the appellant for a further period of one year on the same terms and conditions except statutory increases in the wages of Dock labourers referred to in Clause 2.03 of tender notice. In response, the respondent submitted a tender which was accepted culminating in the issue of a work order dated 10th January 1983 in its favour. It is common ground that the appellant by its communication dated 13th October 1983 exercised the option available to it in terms of Clause 2.03 of the NIT and extended the contract for a further period of one year ending 14th January 1985.
3. The extension aforementioned was accepted by the respondent in terms of its communication dated 7th December 1983 in which it was inter-alia pointed out that statutory revisions in the wages of Mormugao Dock Labour Board (for short M.D.L.B.) that had come about during the period of one year need be considered while extending the contractual period. In response, the company by its letter dated 27th January 1984 pointed out that Clause 2.03 of Schedule II of N.I.T. provided for increases on account of statutory revisions made upto 15th January 1984 alone to be considered for purposes of granting rate escalation. Increases in wages that may have been under negotiations or those granted on a later date with retrospective effect could not consequently be considered, said the appellant. The respondent-Company was on that basis called upon to furnish documentary evidence regarding increase if any in wages allowed by the M.D.L.B. upto 15th January 1984 without waiting for issuance of any fresh circulars.
4. It is not the case of the respondents that any revision in wages effective as on 15th January, 1984 was demonstrated before the appellant at any time before the commencement of the extended contractual period. What was alleged by the respondent was that pursuant to a settlement between the M.D.L.B. and the Dock workers the respondent had incurred an additional amount of Rs.24.74 lakhs towards the increase in the wages payable to such workers. A claim for reimbursement of the said amount was accordingly made by the respondent-company in terms of a legal notice served upon the appellant on its behalf, which claim was refuted by the appellant on the strength of Clause 2.03 of Schedule II to the notice inviting tenders forming part of the contract between the parties. The appellant asserted that the rates at which the contract was initially awarded had to remain firm throughout the period of one year from the date of award and were not subject to any escalation whatsoever. Rates for the extended period were also similarly to remain firm throughout the extended period subject to any statutory revision upto 15th January, 1984 being taken into consideration. Any subsequent increase in the wages payable to the Dock labourers granted retrospectively by the M.D.L.B. was according to the appellant wholly inconsequential.
5. Denial of the claim made by the respondent thus gave rise to a dispute which was in terms of the contract referred to a panel of three Arbitrators for adjudication. Before the Arbitrators, the appellant disputed the claim on merits as also on the ground that the same was barred by limitation. The Arbitrators examined rival contentions urged before them but failed to arrive at a unanimous decision on the true and correct interpretation of Clause 2.03. Two awards, therefore, came
Steel Authority of India Ltd. v. J.C. Budharaja, Government and Mining Contractor
W.B. State Warehousing Corporation v. Sushil Kumar Kayan
Bharat Coking Coal Ltd. v. Annapurna Construction
MD, Army Welfare Housing Organisation v. Sumangal Services (P) Ltd.
Associated Engineering Co. v. Government of Andhra Pradesh
Jivarajbhai Ujamshi Sheth v. Chintamanrao Balaji
State of Rajasthan v. Nav Bharat Construction Co.
Food Corporation of India v. Surendra, Devendra & Mahendra Transport Co.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.