2011 Supreme(SC) 234

R.M.LODHA, AFTAB ALAM
State of Maharashtra – Appellant
Versus
Ark Builders Pvt. Ltd. – Respondent


JUDGMENT

Aftab Alam, J. —

1. Leave granted.

2. Whether the period of limitation for making an application under section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the Act’) for setting aside an arbitral award is to be reckoned from the date a copy of the award is received by the objector by any means and from any source, or it would start running from the date a signed copy of the award is delivered to him by the arbitrator? This is the short question that arises for consideration in this appeal.

3. The material facts of the case are brief and admitted by both sides. These may be stated thus. On March 20, 2003 the arbitrator gave a copy of the award, signed by him, to the claimant (the respondent) in whose favour the award was made. No copy of the award was, however, given to the appellant, the other party to the proceedings, apparently because the appellant had failed to pay the costs of arbitration. The respondent submitted a copy of the award in the office of the Executive Engineer (appellant no.4) on March 29, 2003, claiming payment in terms of the award. On April 16, 2003, the Executive Engineer submitted a proposal to challenge the award before the Chief E


































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top