2005(2) Supreme 622
Supreme Court of India
(From Madras High Court)
R.C. Lahoti, CJI, G.P. Mathur & P.P. Naolekar, JJ.
Union of India —Appellant
versus
Tecco Trichy Engineers & Contractors —Respondents
Civil Appeal No. 1784 of 2005
(@ SLP (C) No. 20446 of 2002)
Decided on 16-3-2005
Counsel for the Parties :
For the Appellant : K. Radhakrishnan, Sr. Advocate, T.A. Khan, S.N. Terdal and Mrs. Anil Katiyar, Advocates.
For the Respondent : Arvind Kumar, Ms. Poonam Prasad and Ms. Laxmi Arvind, Advocates.
Held : Form and contents of arbitral award are provided by Section 31 of the Act. The arbitral award drawn up in the manner prescribed by Section 31 of the Act has to be signed and dated. According to sub-Section (5), “after the arbitral award is made, a signed copy shall be delivered to each party”. The term “party” is defined by clause (h) of Section 2 of the Act as meaning `a party to an arbitration agreement’. The definition is to be read as given unless the context otherwise requires. Under sub-Section (3) of Section 34 the limitation of 3 months commences from the date on which “the party making that application” had received the arbitral award. We have to see what is the meaning to be assigned to the term “party” and “party making the application” for setting aside the award in the context of the State or a department of the Government, more so a large organization like the Railways. (Para 6)
In the present case, the Chief Engineer had signed the agreement on behalf of Union of India entered into with the respondent. In the arbitral proceedings the Chief Engineer represented the Union of India and the notices, during the proceedings of the Arbitration, were served on the Chief Engineer. Even the arbitral award clearly mentions that the Union of India is represented by Deputy Chief Engineer/Gauge Conversion, Chennai. The Chief Engineer is directly concerned with the Arbitration, as the subject matter of Arbitration relates to the department of the Chief Engineer and he has direct knowledge of the arbitral proceedings and the question involved before the arbitrator. The General Manager of the Railways has only referred the matter for arbitration as required under the contract. He cannot be said to be aware of the question involved in the arbitration nor the factual aspect in detail, on the basis of which the arbitral tribunal had decided the issue before it unless they are all brought to his notice by the officer dealing with that arbitration and who is in-charge of those proceedings. Therefore, in our opinion, service of arbitral award on the General Manager by way of receipt in his inwards office cannot be taken to be sufficient notice so as to activate the Department to take appropriate steps in respect of and in regard to the award passed by the arbitrators to constitute starting point of limitation for the purposes of Section 34(3) of the Act. The service of notice on the Chief Engineer on 19.3.2001 would be the starting point of limitation to challenge the award in the Court. (Para 10)
The learned Single Judge of the High Court as also the Division Bench have erred in holding the application under Section 34 filed on behalf of the appellant as having been filed beyond a period of 3 months and 30 days within the meaning of sub-Section (3) of Section 34. There was a delay of 27 days only and not of 34 days as held by the High Court. In the facts and circumstances of the case, the delay in filing the application deserves to be condoned and the application under sub-Section (1) of Section 34 of the Act filed on behalf of the appellant deserves to be heard and decided on merits. (Para 12)
Judgment
P.P. Naolekar, J.—Leave granted.
2. The Southern Railway entered into a contract with respondent No. 1 for gauge conversion from Madras Beach to Trichchirappalli Villupuram Section - construction of a bridge being agreement No. 136/Cn/95 dated 29.9.95. On behalf of the Southern Railway, the contract was signed by the then Chief Project Manager, presently, the Chief Engineer. Disputes arose touching the claims arising out of the execution of works under the contract and in exercise of the power conferred by the arbitration clause contained in the contract, the General Manager, Southern Railway appointed an arbitrator as also a Presiding Arbitrator, while respondent No. 1 nominated its arbitrator. The arbitral tribunal so constituted gave its award on 10/11.03.2001 and signed the same. A copy of the award was delivered in the office of the General Manager, Southern Railway on 12.3.2001. The receipt seems to have been acknowledged by someone in the office, probably the inwards clerk. The Chief Engineer received the copy of the award from the tribunal on 19.3.2001.
3. On 10.7.2001, the Chief Engineer presented an application for setting aside the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the Act’ for short). An application seeking condonation of delay under sub-Section (3) of Section 34 was also filed. The delay sought to be condoned was of 27 days only based on an assumption that the copy of the award was received on 19.3.2001. The application for condonation of delay was contested by respondent No. 1 on the ground that arbitral award was delivered on 12.3.2001 and calculated from that date there was a delay of 34 days in filing the application beyond the period of limitation prescribed by sub-section (3) of Section 34 of the Act while the proviso appended to the said provision does not permit any delay beyond the period of 30 days being condoned by the Court. The objection raised by respondent No. 1 has found favour with the learned Single Judge of the High Court, who rejected the application holding it as barred by limitation. The decision has been upheld by the Division Bench of the High Court. Feeling aggrieved, the appeal has been filed by special leave.
4. The short question which arises for decision in this appeal is : which is the effective date on which the appellant was delivered with and received the arbitral award as that would be the date wherefrom the limitation within the meaning of sub-Section (3) of Section 34 of the Act shall be calculated.
5. Sub-sections (1) and (3) of Section 34 are relevant for our purpose and are reproduced hereunder :
34. Application for setting aside arbitral award.—(1) Recourse to a Court against an arbitral award may be made only by an application for setting aside such award in accordance with sub-section (2) and sub-section (3).
xxx xxx xxx xxx
(3) An application for setting aside may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal:
Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter.”
6. Form and contents of arbitral award are provided by Section 31 of the Act. The arbitral award drawn up in the manner prescribed by Section 31 of the Act has to be signed and dated. According to sub-Section (5), “after the arbitral award is made, a signed copy shall be delivered to each party”. The term “party” is defined by clause (h) of Section 2 of the Act as meaning `a party to an arbitration agreement’. The definition is to be read as given unless the context otherwise requires. Under sub-Sectio
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.