2011 AIR(SC) 3517
Supreme Court of India
ALTAMAS KABIR & CYRIAC JOSEPH
Yograj Infrastructure Ltd.
Versus
Ssang Yong Engineering & Construction Co. Ltd.
CIVIL APPEAL NO.7562 OF 2011 (Arising out of SLP(C) No.25624 of 2010)
Decided on : 01-09-2011
Judgment :
ALTAMAS KABIR, J.
1. Leave granted.
2. The Appellant is a company incorporated under the Companies Act, 1956, while the Respondent is a company incorporated under the laws of the Republic of Korea with its registered office at Seoul in Korea and its project office at New Delhi.
3. On 12th April, 2006, the National Highways Authority of India, New Delhi (NHAI) awarded a contract to the Respondent, SSang Yong Engineering and Construction Co. Ltd., hereinafter referred to as “SSY”, for the National Highways, Sector II Project, Package: ABD-II/C-8, for upgradation to Four Laning of Jhansi-Lakhnadon Section, KM 297 to KM 351 of NH 26 in the State of Madhya Pradesh. The total contract amount was 2,19,01,16,805/-. On 13th August, 2006, SSY entered into a Sub- Contract with the Appellant Company for carrying out the work in question. The Work Order of the entire project was granted to the Appellant by the Respondent on back-to-back basis. Clause 13 of the Agreement entered into between the Respondent and the Appellant provided that 92% of all payments for the work done received by the Respondent from NHAI, would be passed on to the Appellant. Clauses 27 and 28 provided for arbitration and the governing law agreed to was the Arbitration and Conciliation Act, 1996. On 31st October, 2006, the Appellant furnished a Performance Bank Guarantee for 6,05,00,000/- to the Respondent and it also invested about 88.15 crores in the project. Three more Bank Guarantees, totaling 5,00,00,000/-, for release of mobilization advance were also furnished by the Appellant on 29th May, 2009. On 22nd September, 2009, the Respondent Company issued a notice of termination of the Agreement, inter alia, on the ground of delay in performing the work under the Agreement.
4. On account of the above, the Appellant filed an application before the District and Sessions Judge, Narsinghpur, Madhya Pradesh, under Section 9 of the Arbitration and Conciliation Act, 1996, praying for interim reliefs. A similar application under Section 9 of the above Act was filed by the Appellant before the same Court on 30th December, 2009, also for interim reliefs. Ultimately, on 20th May, 2010, the dispute between the parties was referred to arbitration in terms of the Agreement and a Sole Arbitrator, Mr. G.R. Easton, was appointed by the Singapore International Arbitration Centre on 20th May, 2010. On 4th June, 2010, the Appellant filed an application before the Sole Arbitrator under Section 17 of the aforesaid Act being SIAC Arbitration No.37 of 2010, inter alia, for the following reliefs :
“a. restrain the SSY from encashing Performance Bank Guarantee No.101BGPGO63040001 dated 31.10.06 of Syndicate Bank, Nehru Place, Delhi of 6.05 crores;
b. restrain the SSY from enchashing three Bank Guarantees furnished towards the mobilization advance bearing numbers 101 BGFG 091490001 of 1 Crore, 101 BGFG 091490002 of 1 Crore and 101 BGFG 091490003 of 3 Crores, totaling to 5 Crores;
c. direct SSY to release a sum of 144,42,25,884/- along with the interest @ 36% till realization of nationalized bank of India for the aforesaid amount and keep it alive till passing of the final Award.
d. restrain SSY from removing, shifting, alienating or transferring in any manner either itself or through any of its agents/employees, the plant, machineries, equipments, vehicles and materials, in other words maintain status-quo, till the passing of the final arbitral award;
e. grant any other appropriate interim measures of protection in favour of the Cross-Claimant/applicant, which in the esteemed opinion of this Hon'ble Tribunal are just and proper in the facts and circumstance of the case;”
5. The Respondent also filed an application under Section 17 of the above Act before the Sole Arbitrator on 5th June, 2010, for interim reliefs. After considering both the applications, the Arbitrator passed an interim order on 29th June, 2010, in the following manner :
“1. The respondent is to immediately release, f
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.